INTEROFFICE MEMORANDUM
Date: March 4, 2026
To: The Honorable Mayor and City Council
Through: Ron Burton,CPM,City Manager
From: Suhail Kanwar,P.E.,M.S.,CFM,Director of Public Services/City Engineer
RE: PR No.24827:Request for Approval of Amendment No. 1 —9th Avenue Pavement Improvement Project,
most westward lane from Jimmy Johnson Boulevard to Lake Arthur Drive.Capital Account No. 148-21-
053-8517-00-10-000.Project No. ST5023.CON.Brystar Contracting,Inc.,(Brystar)of Beaumont,Texas
Introduction:
The intent of this memorandum is to request City Council's approval of Amendment No. 1 to the construction agreement
with Brystar, of Beaumont,Texas, for the 9th Avenue Pavement Improvement Project,most westward lane from Jimmy
Johnson Boulevard to Lake Arthur Drive,for a 150-calendar-day time extension.
Background:
The Engineering Department, along with the City Council Members, assembled a list of streets for repair and/or
reconstruction as part of an overall street improvement plan. 9th Avenue from Jimmy Johnson Boulevard to Lake Arthur
Drive was listed and subsequently selected for reconstruction. Planning and design of the 9th Avenue Pavement
Improvement Project,the most westward lane(9th Avenue Project)from Jimmy Johnson Boulevard to Lake Arthur Drive,
was done in-house under the direct supervision of Golden Triangle Consulting Engineers of Beaumont,Texas,which also
sealed the drawings.
Pursuant to Resolution No. 25-410, City Council awarded the construction contract to Brystar for a contract amount of
$1,065,472.00 for the 9th Avenue Pavement Improvement Project most westward lane from Jimmy Johnson Boulevard to
Lake Arthur Drive.
During construction,project progress was delayed while the contractor awaited direction on whether to add a subgrade
improvement component to the project scope. The delay associated with the potential addition of the subgrade
improvement component was mutually discussed and agreed upon by Brystar Contracting,Inc.and the City's Engineering
Department,and although the need for such consideration was not anticipated at the outset of the project,the Engineering
Department has since reviewed the circumstances and determined that the requested time extension is reasonable and
necessary for the proper completion of the project.
Amendment No. 1 is being submitted by Brystar for a 150-calendar-day time extension due to the delay of awaiting a
recommendation to add a subgrade improvement task to the project scope to continue construction.
Budget Impact:
Capital Account No: 148-21-053-8517-00-10-000.Project No. ST5023.CON.
Recommendation:
"Remember,we are here to serve the Citizens of Port Arthur"
444 4th Street X Port Arthur,Texas 77641-1089 X 409.983.8182 X FAX 409.983.8294
CAUsers\trotibi_ch\AppData\Local\Microsoft\Olk\Attachments\ooa-d7e954fa-90ac-4575-Bab5-1b073aacf6dc\ld3bab312bd89157830de6e89291219e0cc4a9d42fdb24c506ebb498f5317d79\Agenda
Me mo_Brysta r_CO 1.docx
It is recommended that the City of Port Arthur's City Council approve PR No. 24827 for Amendment No. 1 to the
construction agreement with Brystar, of Beaumont, Texas, for the 9th Avenue Pavement Improvement Project, the most
westward lane from Jimmy Johnson Boulevard to Lake Arthur Drive, for a 150-calendar-day time extension.
"Remember,we are here to serve the Citizens of Port Arthur"
P.O.Box 1089 X Port Arthur,Texas 77641-1089 X 409.983.8101 X FAX 409.982.6743
PR 24827
03/04/2026 RLD
RESOLUTION NO.
A RESOLUTION AUTHORIZING THE CITY MANAGER TO
EXECUTE AMENDMENT NO. 1 TO THE CONSTRUCTION
CONTRACT WITH BRYSTAR CONTRACTING, INC., OF
BEAUMONT, TEXAS, FOR THE 9TH AVENUE PAVEMENT
IMPROVEMENT PROJECT (MOST WESTWARD LANE) FROM
JIMMY JOHNSON BOULEVARD TO LAKE ARTHUR DRIVE,
PROVIDING FOR A ONE HUNDRED FIFTY (150) CALENDAR
DAY TIME EXTENSION; PROVIDING FOR FUNDING FROM
CAPITAL STREETS ACCOUNT NO. 148-21-053-8517-00-10-000,
PROJECT NO. ST5023.CON
WHEREAS, the City of Port Arthur has developed a comprehensive street rehabilitation
program through the Public Works Engineering Division to address streets that require repair and
reconstruction to maintain the safety and functionality of the City's transportation infrastructure; and
WHEREAS, City Council Members, in coordination with the Engineering Division, identified
and prioritized various streets within their respective districts for rehabilitation and reconstruction as
part of the City's ongoing Capital Streets improvement program; and
WHEREAS, 9th Avenue from Jimmy Johnson Boulevard to Lake Arthur Drive was identified
as a roadway requiring reconstruction and was subsequently included in the City's street improvement
program; and
WHEREAS, the planning and design for the 9th Avenue Pavement Improvement Project,
specifically the most westward lane from Jimmy Johnson Boulevard to Lake Arthur Drive, was
performed by the City's Engineering staff under the supervision of Golden Triangle Consulting
Engineers of Beaumont, Texas, which firm also sealed the project drawings; and
WHEREAS, the City's Purchasing Department advertised for competitive sealed bids for the
project in accordance with state law and City purchasing policies on April 30, 2025, and May 7, 2025,
under Bid No. P25-052; and
WHEREAS, on August 1, 2025, the Purchasing Department received and publicly opened two
(2) sealed bids for the project from Brystar Contracting, Inc., of Beaumont, Texas, and Texas Materials,
a CRH Company of Beaumont, Texas; and
WHEREAS, pursuant to Resolution No. 25-410, the City Council awarded a construction
contract to Brystar Contracting, Inc. in the amount of $1,065,472.00 for the 9th Avenue Pavement
Improvement Project; and
PR 24827
03/04/2026 RLD
WHEREAS, during construction, project progress was delayed while the contractor awaited
direction regarding the potential addition of a subgrade improvement component to the project scope
necessary to proceed with continued construction activities; and
WHEREAS, the delay associated with the potential addition of the subgrade improvement
component was mutually discussed and agreed upon by Brystar Contracting, Inc. and the City's
Engineering Department, and although the need for such consideration was not anticipated at the outset
of the project, the Engineering Department has since reviewed the circumstances and determined that
the requested time extension is reasonable and necessary for the proper completion of the project;
WHEREAS, Brystar Contracting, Inc. has submitted Amendment No. 1 requesting a 150-
calendar-day extension to accommodate the delay associated with evaluating and determining the
appropriate subgrade improvement measures; and
WHEREAS, approval of Purchase Requisition No. 24827 for Amendment No. 1 to the
construction contract is deemed to be in the best interest of the City of Port Arthur.
NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF
PORT ARTHUR, TEXAS:
THAT,the facts and opinions in the preamble are true and correct; and,
THAT, the City Council hereby approves Amendment No. 1 to the construction contract with
Brystar Contracting, Inc., of Beaumont, Texas, for the 9th Avenue Pavement Improvement Project (most
westward lane) from Jimmy Johnson Boulevard to Lake Arthur Drive, providing for a (150) calendar
day extension of the contract time due to delays associated with evaluation of a potential subgrade
improvement component to the project scope, as more particularly described in Exhibit "A"; and
THAT, a copy of the Resolution shall be spread upon the Minutes of the City Council.
READ, ADOPTED AND APPROVED this the day of , A.D., 2026, at a
of the City Council of the City of Port Arthur, Texas, by the following vote:
Ayes: Mayor:
Councilmembers:
Noes:
Charlotte M. Moses
Mayor
PR 24827
03/04/2026 RLD
Page 4 of 4
ATTEST:
Sherri Bellard, TRMC
City Secretary
APPROVED AS TO FORM: APPROVE• 6 ' A► INISTRATION
Roxann Pais Cotroneo, Esq. Ron Bu • P
City Attorney City Manager
APPROVERS TO ABILITY OF FUNDS:
7
Lyn a (Lyn) Boswell, MA, IC -CM
Finance Dir ctor
Suhail Kanwar, PE
Director of Public Services/City Engineer
Clifton Williams, CPPB
Purchasing Manager
EXHIBIT A
REQUEST FOR EXTENSION OF TIME 13 S
A4 DUE TO DELAY
CONTRACTING, INC.
Job No. 25250 Date: 3/3/2026
Project Title: 9th Ave paving Improvments Owner: City of Port Arthur
Month of Request: March
Gentlemen:
We request extension of completion time on our Contract in the amount of 150 Calendar
days specified as follows.
Reasons for Request:
We have been delayed awaiting a recommendation to add a subgrade improvement task to the project scope so that
construction can move forward.
Date: 3/3/2026 By: Dylan Rogers
OWNER/OWNERS REPRESENTATIVE
`lj k APPROVED for extension of 15 d Calendar/Working Days.
DISAPPROVED for extension of Calendar/Working Days.
REMARKS:
Date: 3 - 2{—2D 2 L By: l�-- �.✓.�-✓