Loading...
HomeMy WebLinkAboutPR 25015: EXECUTE AMENDMENT NO. 2 TO THE CONTRACT BETWEEN THE CITY OF PORT ARTHUR AND FREESE & NICHOLS, INC. FOR THE CONSTRUCTION PHASE SERVICES OF THE MAIN WASTEWATER TREATMENT PLANT Gity of ort rthu tar www.PortArthurTx.gov INTEROFFICE MEMORANDUM Date: June 22, 2026 To: The Honorable Mayor and City Council Through: Ronald Burton, CPM, City Manager From: Calvin Matthews, P.E., Water Utilities Director RE: PR 25015 —Amend Construction Engineering Services Contract with Freese & Nichols, Inc. of Pearland, Texas Introduction: This agenda item is seeking the Council's approval to execute Amendment No. 2 with Freese and Nichols, Inc. for the Main Wastewater Treatment Plant(WWTP) Improvements Project for an increased amount of$899,392.00 to the new updated contract amount of$2,999,392.00. Background: On April 12, 2022, the City Council approved Resolution No. 22-170, awarding Freese & Nichols, Inc. a contract in the amount of $2,100,000.00 to provide construction phase engineering services for the Main Wastewater Treatment Plant Improvements Project. On October 22, 2024, the City Council approved Resolution No. 24-415, authorizing Amendment No. 1, which modified project staffing levels without increasing the contract amount. Since the commencement of construction, the project schedule has been extended by a cumulative 390 calendar days through change orders previously approved by the City Council pursuant to Resolutions Nos. 22-586, 25-140, 25-355, and 25-548. Those change orders authorized modifications necessary to accommodate evolving project needs, including staffing adjustments, additional construction work,revisions to quantities and materials, and other field- driven changes required to facilitate the successful completion of this complex infrastructure project. Accordingly,the project's anticipated completion date has been extended to October 28, 2027. Because construction-phase engineering services are required throughout the construction period, the extended project schedule has significantly increased the level of professional services needed to complete the project. These services include construction administration, engineering review of contractor submittals, responses to requests for information, field observations, coordination among project stakeholders, review of change order documentation, "Remember,we are here to serve the Citizens of Port Arthur" P.O.Box 1089 X Port Arthur,Texas 77641-1089 X 409.983.8101 X FAX 409.982.6743 City of Tit- o rtlru Tei u www.PortArthurTx.gov testing oversight, regulatory coordination, project documentation, and final project closeout. Analysis: The Main Wastewater Treatment Plant Improvements Project is one of the City's largest infrastructure investments, with a current construction value of approximately $70.87 million. The proposed amendment does not expand the project's scope of work; rather, it provides the engineering services necessary to support the project through its revised completion date. The requested increase of$899,392.00 is directly attributable to the approximately 13-month extension of the construction schedule and the continued need for professional engineering oversight during that period. Without this amendment, the City would lack the engineering support necessary to administer the construction contract, review contractor work, evaluate technical issues, process project documentation, and ensure that the completed facility meets applicable engineering standards,regulatory requirements, and contract specifications. Following approval of Amendment No. 2, the total engineering services contract will be $2,999,392.00,representing approximately 4.23% of the project's current construction value of $70,866,440.82. Likewise, the proposed increase of $899,392.00 represents approximately 1.27% of the total construction contract. Given the size, technical complexity, and extended duration of this major wastewater infrastructure project, these costs are reasonable and proportionate to the professional services required to ensure successful project delivery. Approval of this amendment will provide continuity of engineering oversight through project completion, reduce construction risk, facilitate timely resolution of technical issues, and help protect the City's substantial investment in critical wastewater infrastructure. Budget Impact: The proposed amendment increases the contract by $899,392.00, bringing the total contract amount to $2,999,392.00. Funding is available in Account No. 405-40-000-8516-00-00-000, Project No. WSOO23. Recommendation: It is recommended that the City Council approve Proposed Resolution No. 25015 authorizing the City Manager to amend the contract previously approved with Freese & Nichols, Inc. of Pearland, Texas, to provide continued construction phase engineering services for the Main WWTP Improvements Project as described/outlined above. "Remember,we are here to serve the Citizens of Port Arthur" P.O. Box 1089 X Port Arthur,Texas 77641-1089 X 409.983.8101 X FAX 409.982.6743 PR No. 25015 6/22/26 cm-tnr RESOLUTION NO. A RESOLUTION AUTHORIZING THE CITY MANAGER TO EXECUTE AMENDMENT NO. 2 TO THE CONTRACT BETWEEN THE CITY OF PORT ARTHUR AND FREESE & NICHOLS, INC. OF PEARLAND, TEXAS FOR THE CONSTRUCTION PHASE SERVICES OF THE MAIN WASTEWATER TREATMENT PLANT, INCREASING THE CONTRACT AMOUNT BY$899,392.00, FOR A NEW TOTAL CONTRACT AMOUNT OF $2,999,392.00; FUNDING IS AVAILABLE IN ACCOUNT NO. 405-40-000-8516-00-00-000, PROJECT NO. WS0023. WHEREAS, pursuant to Resolution No. 22-170, adopted on April 12, 2022, the City Council awarded a professional engineering services contract to Freese & Nichols, Inc. (FNI) of Pearland, Texas, in the amount of $2,100,000.00 to provide construction phase engineering services for the Main Wastewater Treatment Plant Improvements Project located on the Procter Street Extension; and WHEREAS, pursuant to Resolution No. 24-415, adopted on October 22, 2024, the City Council approved Amendment No. 1 to the contract,which modified project staffing levels without increasing the contract amount; and WHEREAS, the Main Wastewater Treatment Plant Improvements Project is one of the City's largest and most significant public infrastructure investments, with a current construction contract value of$70,866,440.82, and is essential to maintaining the City's wastewater treatment capacity, regulatory compliance, and long-term utility infrastructure; and WHEREAS, since execution of the original engineering services agreement, the construction schedule has been extended by an aggregate of 390 calendar days through Change Orders approved by Resolutions Nos. 22-586, 25-140, 25-355, and 25-548, resulting in a revised substantial completion date of October 28, 2027; and WHEREAS, the substantial extension of the construction schedule has increased the duration of construction administration, field observation, engineering review, coordination with the contractor, evaluation of submittals and requests for information, testing oversight, project documentation, design modification, TWDB outlay pay submittal, ARPA grant management, and other professional services required to successfully complete a project of this magnitude; and WHEREAS, Amendment No. 2 will provide the additional professional engineering services necessary to support the project through final completion by extending Freese&Nichols, PR No. 25015 6/22/26 cm-tnr Inc.'s construction phase services through October 31,2027,and will increase the contract amount by $899,392.00, for a new total contract amount of$2,999,392.00; and WHEREAS,the Utilities Department has determined that the proposed amendment is fair, reasonable, and necessary because the additional compensation is directly attributable to the extended construction duration and continued professional engineering services required for a project exceeding $70 million in construction value and represents an appropriate and proportionate investment to ensure proper oversight,quality assurance,regulatory compliance,and successful project delivery. NOW THEREFORE,BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF PORT ARTHUR, TEXAS: THAT,the facts and recitals in the preamble are true and correct; and, THAT, the City Manager of the City of Port Arthur is hereby authorized and directed to execute Amendment No. 2 to the contract with Freese & Nichols, Inc. of Pearland, Texas, increasing the contract by $899,392.00, to a new total contract amount of$2,999,392, attached hereto as Exhibit"A"; and, THAT, funding is provided for in Account No. 405-40-000-8516-00-00-000. Project No. WS0023; and, THAT, a copy of the caption of this Resolution shall be spread upon the Minutes of the Meeting of the City Council. READ, ADOPTED, AND APPROVED this day of , 2026 at a Regular Meeting of the City Council of the City of Port Arthur, Texas by the following vote: AYES:Mayor Councilmembers: NOES: CITY OF PORT ARTHUR, TEXAS: Charlotte M.Moses, Mayor ATTEST: Christe Ned, City Secretary PR No. 25015 6/22/26 cm Page 3 of 3 APPROVED AS TO FORM: Roxann Pais Cotroneo City Attorney APPROVED FOR ADMINISTRATION: irgr Ronald B on, CPM City ► .nager Suhail Kanwar, P.E. Director of Public Services alvin Ma ews, P.E. Water Utilities Director APPROVED AS TO THE AVAILABILITY OF FUNDS: y (Lyn Boswell, MA ICMA- M Finance Director Clifton E. Williams Jr., CPPB Purchasing Manager Exhibit "A" (Amendment No. 2) FREESE PROFESSIONAL SERVICES AGREEMENT NICHOLS AMENDMENT#02 City of Port Arthur FNI Project: PRT22379 444 4th Street Client Contract: PR22416 Port Arthur,Texas 77640 Date: 06/30/2026 Project Name: Port Arthur Main WWTP Construction Engineering Services Description of Services: Continue Construction Management and Inspection Services, Submittal and RFI Reviews, PLC factory and field testing Schedule: All services are anticipated to extend through October 31st, 2027 Compensation Type: Not to Exceed Fee Current Contract Amount: $2,100,000.00 Amount of this Amendment: $899,392.00 Revised Total Amount Authorized: $2,999,392.00 The services described above shall proceed as amended upon execution of this Amendment. All other provisions, terms, and conditions of the Professional Services Agreement which are not expressly amended shall remain in full force and effect. City of Port Arthur FREESE AND NICHOLS, INC. By: By: Name: Name: Matthew R. Cartwright Title: Title: Vice President and Principal Date: Date: 6/25/26 Professional Services Agreement Amendment Page 1 of 1 Rev 07/22 CONSTRUCTION PHASE SERVICES OF THE PORT ARTHUR MAIN WWTP IMPROVEMENTS PROJECT FREESE I aNICHOLS 11200 Broadway Street,Suite 2320 • Pearland,Texas 77584 • 832-456-4700 • FAX 832-456-4701 SCOPE OF SERVICES AND RESPONSIBILITIES OF CLIENT Project Understanding: The City of Port Arthur (City) obtained Loan No. L1001023 and Grant No. LF1001024 through the Texas Water Development Board (TWDB) Clean Water State Revolving Fund (CWSRF) program for construction of the Main Wastewater Treatment Plant (WWTP) Improvements Project. The total funding amount is $60,560,000,which includes$2,100,000 allocated for construction phase engineering services. The City and Freese and Nichols, Inc. (FNI) previously executed a professional services agreement under Resolution No. 22-170 for construction phase engineering services in the amount of $2,100,000. This agreement covered construction phase services for 51 months with 24 months of Inspection Services. At the end of the Inspection Services period, Amendment No. 1 to the agreement was approved as per Resolution No. 24-415 as a zero-cost change with staffing level modifications resulting in construction phase services through September 30, 2025. Construction of the Main WWTP improvements has been extended by a total of 390 days due to change orders, approved as per Resolution No's. 22-586, 25-140, 25-355, and 25-548, with an anticipated construction completion date of October 28, 2027. Although FNI's original construction phase services agreement under Resolution No. 22-170 and Resolution No. 24-415 covered services through September 30, 2025, FNI continued providing construction phase services from October 1, 2025 through June 30, 2026 through a separate amendment (Resolution No. 26-137) to its design phase services agreement under Resolution No. 15-056. The purpose of this amendment is to extend FNI's construction phase services under Resolution No. 22- 170 through October 28, 2027,for the remainder of the construction period. Scope Amendment Summary: The contract amendment scope includes the following tasks required to provide Construction Phase Services through October28, 2027: • General and project management. • General and project representation. • Construction management and inspection services. • Storm drainage redesign. ARTICLE I BASIC SERVICES: FNI shall render the following professional services in connection with the development of the Project: A. GENERAL AND PROJECT MANAGEMENT: FNI will provide general administrative and project management services necessary to support continued construction phase engineering during the amendment period, including coordination with the City, Contractor, and TWDB; progress monitoring and scheduling coordination; routine correspondence,documentation,and invoicing;preparation and submittal of monthly TWDB Outlay Reports;coordination with TWDB staff to support loan compliance; and budget tracking and reporting to support management of the remaining loan funds. B. GENERAL REPRESENTATION: FNI will continue to provide construction phase general representation services to support ongoing construction activities during the amendment period.These services are intended to supplement the existing construction phase engineering contract and include the following: Attachment A: Amendment Scope of Services—Additional Construction Phase Services of Port Arthur Main WWTP Improvements I June 2026 I Resolution No. 22-170 Page 2 of 4 1. Participate in up to sixteen (16) monthly construction progress meetings with the City and Contractor and perform up to sixteen (16) site visits,typically conducted in conjunction with the monthly progress meetings, to observe construction progress and general conformance with the Contract Documents. 2. Review and processing of up to sixteen (16) contractor pay applications, including evaluation of supporting documentation and recommendation of payment to the City. 3. Review and response to up to eight (8) Requests for Information (RFIs). 4. Review of up to twelve (12)submittals, including shop drawings and product data,with up to two(2) review cycles per submittal. 5. Review and processing of up to six (6) contract modification items, including change orders, field orders, or proposal requests. 6. Factory and field acceptance testing for four(4) plant PLCs, including up to 4 trips to the Port Arthur Main Wastewater Treatment Plant with overnight stays for two (2)days. 7. Substantial and final completion walkthroughs with associated punch lists. 8. Record drawings and project close-out activities. 9. Maintenance of project documentation and tracking of submittals, RFIs, and contract modifications using FNI's document management system. Construction phase general representation services under this amendment are anticipated to extend through project completion coinciding with the Contractor's current anticipated completion date of October 28, 2027. C. CONSTRUCTION MANAGEMENT AND INSPECTION (CM&I)SERVICES: Furnish the services of one (1) Resident Project Representative(RPR),and one(1) Construction Manager(CM)through October 28, 2027.Total hours assumed for RPR services are based on one (1) RPR for 15 hours per week during this period,and total hours assumed for CM services are based on one (1)CM for 10 hours per week. D. STORM DRAINAGE REDESIGN:The original contract drawings included a portion of the Main WWTP site draining to an existing onsite pond.At the beginning of construction,the Contractor requested that the existing pond be filled to provide additional laydown area, and the City approved this request.As a result, minor modifications to the site grading and storm drainage design are required. AWC, as a subconsultant to FNI, will perform the additional analysis and prepare the necessary recommendations and drawing revisions to address the approved change. FNI assumes that revisions to the contract drawings will be handled by Field Order and incorporated into a subsequent change proposal from the Contractor. ARTICLE II ADDITIONAL SERVICES: Any services performed by FNI that are not included in the Basic Services described above are Additional Services. Attachment A: Amendment Scope of Services—Additional Construction Phase Services of Port Arthur Main WWTP Improvements I June 2026 I Resolution No. 22-170 Page 3 of 4 ARTICLE III TIME OF COMPLETION: FNI is authorized to commence work upon execution of this Amendment and agrees to perform the services in accordance with the Basic Services identified herein. The services authorized under this Amendment are limited through October 28, 2027. The current anticipated final completion date for the Project is October 28, 2027. Continued construction past the anticipated completion date may require a subsequent contract amendment. ARTICLE IV RESPONSIBILITIES OF CLIENT: City shall perform the following in a timely manner so as not to delay the services of FNI: A. City recognizes and expects that change orders may be required to be issued during construction. The responsibility for the costs of change orders will be determined on the basis of applicable contractual obligations and professional liability standards. B. Designate in writing a person to act as City's representative with respect to the services to be rendered under this Agreement. Such person shall have contract authority to transmit instructions, receive information, interpret and define City's policies and decisions with respect to FNI's services for the Project. C. Provide all criteria and full information as to City's requirements for the Project, including design objectives and constraints, space, capacity and performance requirements, flexibility and expandability, and any budgetary limitations; and furnish copies of all design and construction standards which City will require to be included in the drawings and specifications. D. Assist FNI by placing at FNI's disposal all available information pertinent to the Project including previous reports and any other data relative to design or construction of the Project. E. Arrange for access to and make all provisions for FNI to enter upon public and private property as required for FNI to perform services under this Agreement. F. Examine all studies, reports, sketches, drawings, specifications, proposals and other documents presented by FNI,obtain advice of an attorney, insurance counselor and other consultants as City deems appropriate for such examination and render in writing decisions pertaining thereto within a reasonable time so as not to delay, or cause rework in,the services of FNI. G. Furnish approvals and permits from all governmental authorities having jurisdiction over the Project and such approvals and consents from others as may be necessary for completion of the Project. H. City shall make or arrange to have made all subsurface investigations, including but not limited to borings, test pits, soil resistivity surveys, and other subsurface explorations. City shall also make or arrange to have made the interpretations of data and reports resulting from such investigations. All costs associated with such investigations shall be paid by The City. Provide such accounting, independent cost estimating and insurance counseling services as may be required for the Project,such legal services as City may require or FNI may reasonably request with regard to legal issues pertaining to the Project including any that may be raised by Contractor(s), such auditing service as City may require to ascertain how or for what purpose any Attachment A:Amendment Scope of Services—Additional Construction Phase Services of Port Arthur Main WWTP Improvements I June 2026 I Resolution No. 22-170 Page 4 of 4 Contractor has used the moneys paid under the construction contract, and such inspection services as City may require to ascertain that Contractor(s) are complying with any law, rule, regulation,ordinance, code or order applicable to their furnishing and performing the work. J. If City designates a person to serve in the capacity of Resident Project Representative who is not FNI or FNI's agent or employee, the duties, responsibilities and limitations of authority of such Resident Project Representative(s)will be set forth in an Attachment attached to and made a part of this Agreement before the Construction Phase of the Project begins. Said attachment shall also set forth appropriate modifications of the Construction Phase General Representation services as defined in Attachment SC, Article I, D, together with such adjustment of compensation as appropriate. K. Attend the construction progress and other job-related meetings and substantial completion inspections and final payment inspections. L. Give prompt written notice to FNI whenever City observes or otherwise becomes aware of any development that affects the scope or timing of FNI's services,or any defect or nonconformance of the work of any Contractor. M. Furnish, or direct FNI to provide, Additional Services as stipulated in Attachment SC, Article III of this Agreement or other services as required. N. Bear all costs incident to compliance with the requirements of this Article IV. ARTICLE V DESIGNATED REPRESENTATIVES: FNI and Client designate the following representatives: Client's Designated Representative—Calvin Matthews, P.E. Director of Water Utilities calvin.matthews@portarthurtx.gov (409) 983-8226 Client's Accounting Representative—Lynda "Lyn" Boswell, M.A., ICMA-CM Director of Finance Lynda.Boswell@portarthurtx.gov (409) 983-8186 FNI's Designated Representative—Matthew Cartwright, P.E. Project Manager matt.cartwright@freese.com (832) 602-4547 FNI's Accounting Representative—Kristina Isaac Operations Analyst Kristina.lsaac@freese.com (713) 600-6860