HomeMy WebLinkAboutPR 25086: AUTHORIZING THE CITY MANAGER TO EXECUTE A CONTRACT WITH VORTEX SERVICES LLC FOR THE REHABILITATION OF SANITARY SEWER MANHOLES AT THOMAS JEFFERSON MIDDLE SCHOOL THROUGH THE HOUSTONGALVESTON AREA COUNCIL (HGAC) Em
rrrt rtfttr
INTEROFFICE MEMORANDUM
Date: July 31, 2026
To: The Honorable Mayor and City Council
Through: Ronald Burton, C.P.M., City Manager
From: Calvin Matthews, P.E., Water Utilities Director
RE: PR No. 25086 -Execute contract with Vortex Services, LLC for the Rehabilitation
of Sanitary Sewer Manholes at Thomas Jefferson Middle School
Introduction:
This Agenda Item intends to seek the City Council's approval for executing a contract with
Vortex Services, LLC. The contract provides for the rehabilitation of sanitary sewer manholes
at Thomas Jefferson Middle School through the Houston-Galveston Area Council (HGAC)
Cooperative Purchasing Contract No. TP07-25 in the total amount of$53,880.26 from Account
No. 410-40-220-5313-00-00-000, Sewer System Maintenance.
Background:
To cooperate with upcoming planned improvements at Thomas Jefferson Middle School,the
Water Utilities Department will rehabilitate sanitary sewer manholes located within the area of
the school. Vortex Services, LLC has submitted a proposal for the rehabilitation of the sanitary
sewer manholes that will consist of applying a Geopolymer Liner coating which will add
structural stability and extend the service life of the manholes. The scope includes
mobilization,the installation of the liner, infiltration control, and all necessary labor,materials,
and equipment.
Budget Impact:
The projected budgetary impact is $53,880.26. Funds are available from Account No. 410-40-
220-5313-00-00-000, Sewer System Maintenance.
Recommendation:
It is recommended that the City Council approve PR No. 25086, to execute a contract with
Vortex Services, LLC, as discussed/outlined above.
"Remember,we are here to serve the Citizens of Port Arthur"
PR No. 25086
07/31/2026 cm
Page 1 of 3
RESOLUTION NO.
A RESOLUTION AUTHORIZING THE CITY MANAGER TO EXECUTE
A CONTRACT WITH VORTEX SERVICES LLC,OF HOUSTON,TEXAS
FOR THE REHABILITATION OF SANITARY SEWER MANHOLES AT
THOMAS JEFFERSON MIDDLE SCHOOL THROUGH THE HOUSTON-
GALVESTON AREA COUNCIL(HGAC)COOPERATIVE PURCHASING
CONTRACT NO. TP07-25 IN THE TOTAL AMOUNT OF $53,880.26;
FUNDS ARE AVAILABLE IN ACCOUNT NO. 410-40-220-5313-00-00-000,
SEWER SYSTEM MAINTENANCE.
WHEREAS, Chapter 271 of the Texas Government Code allows a city, by resolution of
its governing body,to participate in a cooperative purchasing program as an alternative to a formal
bid process; and,
WHEREAS, pursuant to Resolution No. 11-196, the City of Port Arthur entered into an
interlocal agreement for cooperative purchasing with the Houston-Galveston Area Council
(HGAC) Cooperative Purchasing Program; and,
WHEREAS, to cooperate with upcoming planned improvements at Thomas Jefferson
Middle School, the Water Utilities Department will rehabilitate the sanitary sewer manholes
located within the area of the school; and
WHEREAS,Vortex Service, LLC has submitted a proposal through HGAC Contract No.
TP07-25 for the rehabilitation of the manholes in the total amount of$53,880.26 (Exhibit "A");
and,
WHEREAS, the scope of work consists of applying a Geopolymer Liner coating to the
inside of the sanitary sewer manholes which will add structural stability and extend the service
life, mobilization, infiltration control, and all necessary labor, materials and equipment.
NOW THEREFORE,BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY
OF PORT ARTHUR, TEXAS:
THAT,the facts and recitals in the preamble are true and correct; and,
PR No. 25086
07/31/2026 cm
Page 2 of 3
THAT, the City Manager is hereby authorized to execute, in substantially the same form
as the attached Exhibit "A", with Vortex Services for the rehabilitation of the sanitary sewer
manholes at Thomas Jefferson Middle School, through HGAC Contract No. TP07-25 in the total
amount of$53,880.26; and,
THAT, funding for this contract is available in Water Utilities Account No. 410-40-220-
5313-00-00-000, Sewer System Maintenance; and,
THAT, a copy of the caption of this resolution be spread upon the minutes of the City
Council.
READ, ADOPTED, AND APPROVED THIS day of
2026 at a Regular Meeting of the City Council of the City of Port Arthur, Texas, by the following
vote: AYES: Mayor
Councilmembers:
NOES:
Charlotte M. Moses
Mayor
ATTEST:
Christe Whitley Ned, TRMC
City Secretary
PR No. 25086
07/31/2026 cm
Page 3 of 3
APPROVED AS TO FORM:
-----------C-fumg ----.'----?.---..--.
Roxann Pais Cotroneo
City Attorney
APPROVED FOR ADMINISTRATION:
.._ _.1-)a,pv,,,/...,,... /24.)7.2 /-4(._.,
Ronald Burton, CPM
City Manager
Suhail Kanwar, P.E.
Director of Public Services
f/A44i
Matthews, P.E.
Water Utilities Director
APPROVED AS TO THE AVAILABILITY
OF FUNDS:Zdaoswel , MA CGFO
Finance Director
h ,..., d
ii
Clifton . Williams Jr. CPPB
Purchasing Manager
Exhibit "A"
CONSTRUCTION CONTRACT
AGREEMENT
[Non-Federally Funded Projects]
THIS AGREEMENT, made this day of 2026,by and between the CITY OF PORT
ARTHUR, a municipal corporation organized under the laws of the State of Texas, hereinafter
called "OWNER", and Vortex Services. LLC.,hereinafter called "CONTRACTOR".
WITNESSETH: That for and in consideration of the payments, terms, conditions, and
agreements set forth herein, OWNER and CONTRACTOR agree as follows:
1. The CONTRACTOR will commence and complete the construction of Rehabilitation of
Manholes at Thomas Jefferson Middle School.
2. The CONTRACTOR will furnish at his own expense all the materials, supplies, tools,
equipment, labor, and other services necessary for the construction and completion of the
Project described herein.
3. The CONTRACTOR will commence the work required by the Contract Documents on or
before a date and will complete the same within consecutive calendar days.
4. The CONTRACTOR agrees to perform all the Work described in the Contract Documents and
comply with the terms therein for the estimated total amount of $53.880.26,as shown in
the Service Proposal.
5. Work, following the Contract dated after the Notice to proceed, the Contractor shall
complete the WORK within 45 consecutive calendar days.
6. The term "CONTRACT DOCUMENTS" means and includes the following:
• AGREEMENT
P PROPOSAL
• PAYMENT BOND
• NOTICE TO PROCEED
6. The OWNER will pay to the CONTRACTOR in the manner and at such times as outlined in
the General Conditions such amounts as required by the Contract Documents.
7. This Agreement shall be binding upon all parties hereto and their respective heirs,
executors,administrators,successors,and assigns.
Page 1 of 2
CONSTRUCTION CONTRACT
AGREEMENT
[Non-Federally Funded Projects]
IN WITNESS WHEREOF, the Parties hereto have executed, or caused to be executed by their
duly authorized officials,this Agreement in two (2) copies, each of which shall be deemed an
original on the date first above written.
APPROVED IN FORM: OWNER:
CONTRACTOR: OWNER:
Vortex Services LLC CITY OF PORT ARTHUR
BY By
NAME NAME
ADDRESS
TITLE
Page 2 of 2
B ri e s
To: City Of Port Arthur Contact:
Address: 444 4th St. Phone: (409)983-8193
Port Arthur,TX US Email:
Project Name: TX-Port Arthur-FY26 Manhole Rehab-HGAC Bid Number: 2436562-2
Project Location: Port Arthur,TX Bid Date: 7/24/2026
Proposal Based on HGAC Contract TP07-25
Item# Item Description Estimated Quantity Unit Unit Price Total Price
P49 Mobilization-Texas 1.00 EACH $4,784.00 $4,784.00
G17 Rehabilitation(Standard 4-ft Diameter)- 1-inch 91.00 VF $450.00 $40,950.00
Geopolymer liner
G47 Rebuild Bench and Invert 1.00 EACH $1,000.00 $1,000.00
B18 Infiltration Control-Chemical Grout(Will Bill As 1.00 GAL $250.00 $250.00
Needed)
B19 Infiltration Control-Quad-Plug(5 Gallon)(Will Bill As 1.00 EACH $100.00 $100.00
Needed)
08 Flagmen(per Each) 40.00 HR $150.00 $6,000.00
Bid Price Subtotal: $53,084.00
Total Payment And Performance Bond 1.50%: $796.26
Total Bid Price: $53,880.26
Notes:
• Our manhole rehab is figured utilizing flow through plugs.Any dewatering and or bypass pumping will be provided by Owner(if necessary). Please
note, in order to install our plugs and divert the flow on force mains we assume the incoming lines are protruding at least 3"into the manhole
which will allow us to attach Fernco type coupling systems.If additional bypass,dewatering,or flow control is needed it will be provided by Others.
• Owner will provide a portable hydrant meter and access to onsite water for our use free of charge.
• Owner will provide access to each and every manhole and or structure.This may include but not limited locating,exposing,and raising buried MH's
prior to our crew mobilizing.
• If necessary,Owner will provide Permits&Fees.Vortex will provide our standard insurance coverage. OCP or railroad insurance&or
longshoreman insurance is not included.
• Our Bid Proposal is valid for 30 days from the bid date.
• Site Restoration will be performed by Others.
• This is a unit priced contract and the actual billing will be based on installed quantities.If the installed quantities vary greater than 10%of the bid
quantities,Vortex reserves the right to adjust our unit price accordingly.
• Standard wages are included.Therefore,Prevailing wages and or Union Wage Rates are not included in this bid proposal.Client/GC must notify
Vortex if the project is Certified payroll prior to contract execution or additional fees may apply.
• Our bid proposal as submitted reflects the current material pricing established on or before the bid date listed within our proposal. In the event of
unforeseen price increases of our raw materials,Vortex reserves the right to adjust our unit rate or overall bid proposal accordingly to account for
such price increases.
• Payment terms: Net 30 days.Interest will be added to balances outstanding after 30 days
• Vortex's bid proposal shall be incorporated into the subcontract agreements.Vortex will initiate this project upon an agreement or receipt of a
subcontract or purchase order. Copies of payment and performance bonds must be provided to Vortex.
• Any delays besides weather that is outside of our control will be billed at a standby rate of$1,250/hour,for the CIPP Lining Crew&$650/hour for
the Clean&CCTV Crew.
• Typically any debris collected from the Manhole(MH)rehab process is removed by hand but if there is a significant amount of debris collected,the
Owner shall provide a Vac Truck to remove debris collected and dispose the debris that is pulled from the cleaning process.Please note,Vortex can
also provide a vac truck at$550/HR(*4 hr min,travel time will be billed port to port)
Page 1 of 2
• The Owner will have to provide site access improvements including(but not limited to)clearing of any trees,shrubs,fence,sheds,vegetation etc.
to provide an unobstructed access for our work.This also includes coordinating site access permissions with the property owners and the City.We
are able to complete our work if our trucks can be staged within 50'from both the upstream and downstream manholes.If certain site conditions
restrict this and require us to stage greater than 50',then our trucks will require a road to drive the equipment to each manhole and it needs to be
somewhat of level.Therefore it may be required for the owner to install a temporary easement access road by installing rock/road base,installing
culverts,matting etc to aid in creek crossings or wet areas.The install and removal of these site improvements will be provided by Others.
• r
Since the owner did not provide H2S levels,Vortex is assuming the existing structures to get rehab fall below our manufacturer's recommended
H2S levels.
• Vacuum,hydrostatic,holiday/spark testing are not included in this bid proposal.
ACCEPTED: CONFIRMED:
The above prices,specifications and conditions are satisfactory and Vortex Services LLC
are hereby accepted.
Buyer:
Signature: Authorized Signature:
Date of Acceptance: Estimator: Nate Kennedy
(832)392-1816 nkennedy@vortexcompanies.com