HomeMy WebLinkAboutP.R. NO. 25140 SABINE PASS PIPE BURSTING PROJECT PHASE V CHANGE ORDER NO. 1.V
City of
urt rthu���
Texas
INTEROFFICE MEMORANDUM
Date: September 22, 2026
To: The Honorable Mayor and City Council
Through: Ronald Burton, C.P.M., City Manager
From: Calvin Matthews, P.E.,Water Utilities Director
RE: PR 25140— Sabine Pass Pipe Bursting Project Phase V Change Order No. 1
Introduction:
The intent of this Agenda Item is to seek the City Council's approval for Change Order No. 1
for the Sabine Pass Pipe Bursting Project Phase V with Global Drilling, Inc. of Winnie, Texas,
increasing the amount by $134,663.20 and extending the contract by 30 days with a now
scheduled completion date of November 12, 2026.
Background:
Resolution No. 26-156 approved the contract with Global Drilling, Inc. of Winnie, Texas, for
the Sabine Pass Pipe Bursting Project Phase V for the continued improvements to the wastewater
collection system in the Sabine Pass area in accordance with the Texas Commission on
Environmental Quality (TCEQ) SSOI agreement that requires the systematic rehabilitation and
replacement of aging sewer infrastructure. The proposed Change Order No. 1 will increase the
contract amount by$134,663.20 and extend the contractual duration by 30 days,thereby shifting
the original completion date from October 13, 2026, to November 12, 2026.
The sub-total for Change Order No. 1 is $184,663.20, but it subtracts the $50,000.00
contingency amount as stipulated in the contract document. After excavating the area, it was
found that a 10" sewer pipe needed to be installed by cured-in-place pipe (CIPP) instead of an
8"sewer pipe by pipe bursting, as stated in the bid documents. Furthermore, after inspecting the
sewer line to be replaced, it was discovered that an additional sewer pipe extending across
Dowling Rd would also need to be replaced to prevent it from affecting the newly installed sewer
pipe and to service the gas station and surrounding areas.
Budget Impact:
The initial contract amount was $564,910.00. This proposed Change Order No. 1 will increase
the contract amount by $134,663.20 to the new contract amount of$699,573.20, increasing the
change order percentage allowed by 23.8%. Funding is available in CIP Account No. 405-40-
000-8516-00-00-000, Project No. WS0006.CON
Recommendation:
It is recommended that the City Council adopt Proposed Resolution No. 25140, authorizing the
Change Order No. 1 for the project as discussed/outlined above.
"Remember,we are here to serve the Citizens of Port Arthur"
PR No. 25140
8/4/26 cm
Page 1 of 4
RESOLUTION NO.
A RESOLUTION AUTHORIZING THE CITY MANAGER TO
EXECUTE CHANGE ORDER NO. 1 TO THE SABINE PASS PIPE
BURSTING PROJECT PHASE V WITH GLOBAL DRILLING, INC
OF WINNIE, TEXAS, INCREASING THE CONTRACT AMOUNT
BY$134,663.20(SUB-TOTAL AMOUNT OF$184,663.20 MINUS THE
CONTRACT CONTINGENCY AMOUNT OF $50,000.00) TO THE
NEW TOTAL CONTRACT AMOUNT OF $699,573.20, AND
EXTEND THE CONTRACTUAL DURATION BY 30 DAYS,
THEREBY SHIFTING THE ORIGINAL COMPLETION DATE
FROM OCTOBER 13, 2026, TO NOVEMBER 12, 2026; FUNDS ARE
AVAILABLE IN CAPITAL IMPROVEMENTS PROJECTS
ACCOUNT NO. 405-40-000-8516-00-00-000, PROJECT NO.
WS0006.CON.
WHEREAS, pursuant to Resolution No. 26-156, the Sabine Pass Pipe Bursting Project
Phase V was awarded to Global Drilling Inc. of Winnie, Texas, with a total budgetary amount of
$564,910.00; and,
WHEREAS,the project scope of work consisted of replacing approximately 1,860 L.F. of
sewer lines by pipe bursting in a section of Greenwhich Street and across to Mechanic Street, as
well as, 285 L.F. of sewer lines by direction drilling in a section of Broadway Street,including the
installation of three (3) new manholes, replacement of one (1) existing manhole, and the lining of
two (2) existing manholes; and,
WHEREAS, after excavating the area, it was found that a 10" sewer pipe needed to be
installed by cured-in-place pipe (CIPP) instead of an 8" sewer pipe by pipe bursting as stated in
the bid documents; and,
WHEREAS, furthermore, after inspecting the sewer line that was to be replaced, it was
discovered that further sewer pipe reaching across Dowling Rd would also need to be replaced to
prevent affecting the newly installed sewer pipe, and also needed to service the gas station and
surrounding areas; and,
WHEREAS,Global Drilling,Inc.has submitted proposed Change Order No. 1 (EXHIBIT
"A")for an increased amount of$134,663.20(sub-total amount of$184,663.20 minus the contract
contingency amount of $50,000.00) and extend the contractual duration by 30 days, thereby
shifting the original completion date from October 13, 2026, to November 12, 2026, for the
aforementioned items; and,
WHEREAS, the total increased amount in the proposed Change Order No. 1 is within the
maximum allowed 25% of the original contract amount (EXHIBIT "B"), as per the Texas Local
Government Code Section 252.048(d).
PR No. 25140
8/4/26 cm
Page 2 of 4
NOW THEREFORE,BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY
OF PORT ARTHUR,TEXAS:
THAT,the facts and opinions in the preamble are true and correct; and,
THAT,the City Council hereby approves Change Order No. 1 (EXHIBIT"A")to address
the increased installation requirements, increasing the amount by $134,663.20 (sub-total amount
of$184,663.20 minus the contract contingency amount of$50,000.00) to the new total contract
amount of $699,573.20; and extend the contractual duration by 30 days, thereby shifting the
original completion date from October 13, 2026,to November 12, 2026; and,
THAT,the funding is available in Capital Improvement Projects Account No. 405-40-000-
8516-00-00-000, Project No. WS0006.CON; and,
THAT, a copy of the caption of this Resolution be spread upon the minutes of the City
Council.
READ, ADOPTED, AND APPROVED THIS day of , 2026 at
A Regular Meeting of the City Council of the City of Port Arthur, Texas,by the following vote:
AYES: Mayor:
Councilmembers:
NOES:
Charlotte M. Moses
Mayor
ATTEST:
Christe Whitley Ned, TRMC
City Secretary
PR No. 25091
8/4/26 cm
Page 4 of 4
APPROVED AS TO FORM:
Roxann Pais Cotroneo
City Attorney
APPROVED FOR ADMINISTRATION:
Ronald B on, CPM
City ager
Suhail Kanwar, P.E.
Director of Public Services
Calvin Matthews, P.E.
Water Utilities Director
APPROVED AS TO THE AVAILABILITY
OF FUNDS:
Lynd (Lynda) Boswell,r CGFO
Finance Director
titk
Clifton . Williams Jr. CPPB
Purchasing Manager
EXHIBIT A
(Change Order No. 1)
GLOBAL DRILLING, INC.
C��^ g, �� 3300 Jimmy Johnson Blvd, Port Arthur,Texas 77642
l��JdT:+1 800 956 8720; F:(407)715 6150
DRILLING,INC. Email:info@globaldrillingequipment.com,Website:www.alobaldrillingequipment.com
CHANGE ORDER
Date :
Attn : CITY OF PORT ARTHUR September 1, 2026
Project Name : 26-156
SABINE PASS PIPE BURSTING PROJECT PHASE V
Location : Sabine Pass, Port Arthur TX
Item Unit Price Total Price
No. Description Unit Qty (USD) (USD)
CHANGE ORDER NO. 1
1 Installation of 10"Sewer Pipe by CIPP along Greenwich St LF 680 110.00 74,800.00
-Less: Charge for 8"Pipe Bursting LF 680 80.00 -54,400.00
20,400.00
2 Plugging the Manhole#10 going to Broadway St.. EA 1 3,500.00 3,500.00
We will put concrete
3 Point of Repair EA 1 7,000.00 7,000.00
4 Repair of Manhole on South 6th and Broadway St EA 1 3,500.00 3,500.00
5 Pre-TV Inspection from Manhole#3 to Cleanout#14 LF 151 8.00 1,208.00
6 Post-TV Inspection from Manhole#3 to Cleanout#14 LF 258.4 8.00 2,067.20
7 Jetting and Cleaning using Directional Drilling for 10"sewerline EA 1 6,500.00 6,500.00
along Greenwich St from S5th Rd going to Dowling Rd
Approximately 700LF
8 Installation of 8"Sewer Pipe by CIPP LF 1079.4 80.00 86,352.00
- From new Manhole#3 to existing Cleanout#14 (258.4 LF)
-From new Manhole#3 to new Manhole#13Z(570 LF)
- From new Manhole#13Z to existing Manhole#13 (251 LF)
9 Pre-TV Inspection LF 821 8.00 6,568.00
10 Post-TV Inspection LF 821 8.00 6,568.00
- From new Manhole#3 to new Manhole#13Z(570 LF)
- From new Manhole#13Z to existing Manhole#13 (251 LF)
9 Furnish and Install 4"Sanitary Sewer Service Line (Long Side) EA 6 4,500.00 27,000.00
10 Installation of New Manhole EA 1 14,000.00 14,000.00
11 Time Extension for 30-Days
SUB-TOTAL : $184,663.20
Less: Contigency -50.000.00
TOTAL: $ 134,663.20
Amount in Words(US Dollars) : One Hundred Thirty Four Thousand Six Hundred Sixty-Three &20/100 Only
For :
GLOBAL DRILLING, INC.
JASMIN BERSOBIO
A
EXHIBIT B
(Change Order Tracking)
Contract Status
Contract Name: Sabine Pass Pipe Bursting Project Phase V
Contractor: Global Drilling, Inc.
Contract#: 26-1563
Original Contract Amount: $ 564,910.00
Statutory Range: $ 141,227.50
Pursuant to 252.048(d)(+/-)
Amount Percentage of Percentage
Original Contract to Date
Original Contract $ 564,910.00
Proposed Change Order 1 $ 134,663.20 23.8% 23.8%
Total Change Orders to Date $ 134,663.20 23.84%
New Total Contract Amount $ 699,573.20