Date: October 01, 2026
To: The Honorable Mayor and City Council
Through: Ron Burton, CPM, City Manager
From: Suhail Kanwar, P.E., M.S., CFM, Director of Public Services/City Engineer
RE: PR No. 25176: Request for Approval of Change Order No. 2 - 7th Street Improvements Project
— Stadium Road to Duff Drive. Project No. ST3047.CON Capital Account No. 307-21-053-
8517-00-10-000. Elite Contractors & Equipment, LTD, of Kirbyville, Texas.
Introduction:
The intent of this memorandum is to request City Council's approval of Change Order No.2 to the construction agreement
with Elite Contractors&Equipment,LTD,of Kirbyville,Texas(Elite),for the 7th Street Improvements Project—Stadium
Road to Duff Drive,for a sixty-three(63)calendar day time extension.Project No. ST3047.CON.
Background:
The City of Port Arthur's Engineering Division,based on historical data,identified streets that were in poor condition and
recommended them for Reconstruction,Remediation,and Rehabilitation. The 7th Street Improvements Project: Stadium
Road to Duff Drive has been identified as in need of reconstruction.
Pursuant to Resolution No. 25-296, City Council awarded the construction contract to Elite for a contract amount of
$2,828,270.00 with an estimated completion date of October 30,2026.
Change Order No. 1
The 7th Street Improvement Project discovered that a previously unknown sanitary sewer line conflicts with the proposal
storm sewer system and a conflict box is required to protect the sanitary line from the storm water system. Field Order
No. 1 informed the City Manager of the work that was required with the understanding that it would go to the Port Arthur
City Council in the form of Change Order No. 1.
Pursuant to Resolution No.29-080,City Council approved Change Order No. 1 for a conflict box,water line casing,point
repair,and removal of bid line item regarding sewer construction that will not be performed from the contract; Sewer line
installation—bid item 1B,&post-construction TV inspection—bid item 3B.These changes decreased the contract amount
by a total of$123,257.00.
"Remember,we are here to serve the Citizens of Port Arthur"
444 4th Street X Port Arthur,Texas 77641-1089 X 409.983.8182 X FAX 409.983.8294
Change Order No. 2
Elite is requesting sixty-three(63)additional calendar days due to the following reasons: 1.)Hurricane Edouard,
declared a natural disaster by Jefferson County, caused a five(5) calendar day delay due to the natural disaster.
2.)During construction, a natural gas pipeline owned by Texas Gas was discovered, causing an additional three
(3) days delay. 3.) Proposed additional work on Imhoff Avenue, with no budgetary impact, for an additional
fifty-five (55) calendar days. This request changes the original completion date of October 30, 2026 to a new
completion date of January 1, 2027.
Budget Impact:
Funding not impacted. Project No. ST3047.CON.
Recommendation:
It is recommended that the City of Port Arthur's City Council approve PR No. 25176 for Change Order No. 2 to the
construction agreement with Elite,for the 7th Street Improvements Project—Stadium Road to Duff Drive,for a sixty-three
(63)calendar day time extension.Project No. ST3047.CON.
"Remember,we are here to serve the Citizens of Port Arthur"
P.O.Box 1089 X Port Arthur,Texas 77641-1089 X 409.983.8101 X FAX 409.982.6743
IFF
PR 25176
10/01/2026 RLD
Page 1 of 4
RESOLUTION NO.
A RESOLUTION AUTHORIZING THE CITY MANAGER TO EXECUTE
CHANGE ORDER NO. 2 TO THE CONSTRUCTION CONTRACT WITH ELITE
CONTRACTORS & EQUIPMENT, LTD, OF KIRBYVILLE, TEXAS FOR THE
7TH STREET IMPROVEMENTS PROJECT-STADIUM ROAD TO DUFF DRIVE
FOR AN ADDITIONAL SIXTY-THREE (63) CALENDAR DAY EXTENTION.
FUNDING IS NOT IMPACTED. PROJECT NO. ST3047.CON.
WHEREAS, a street rehabilitation plan has been developed by the Public Works Engineering
Division to address streets that are in immediate need of reconstruction, remediation, and rehabilitation;
and,
WHEREAS, the Engineering Division has selected the 7th Street Improvements Project —
Stadium Road to Duff Drive because it met the criteria; and,
WHEREAS,the City of Port Arthur's Purchasing Department publicized its Invitation to Bid for
interested parties to bid on the project on April 30, 2025 and May 7, 2025 under Bid No. P25-051; and,
WHEREAS, a total of four(4)bids were received and opened on June 4, 2025 from Allco, LLC,
of Beaumont, Texas; Brystar Contracting, Inc. of Beaumont, Texas; Eastex Utility Construction, LLC,
of Beaumont, Texas; and Elite Contractors & Equipment, LTD, of Kirbyville, Texas; and,
WHEREAS, pursuant to Resolution No. 25-296, the City entered into an agreement with Elite
Contractors & Equipment, LTD, of Kirbyville, Texas for the 7th Street Improvements Project— Stadium
Road to Duff Drive for the amount of$2,828,270.000; and,
WHEREAS, the 7th Street Improvement Project contractors discovered that a previously
unknown sanitary sewer line conflicts with the proposal storm sewer system and a conflict box is
required to protect the sanitary line from the storm water system. Field Order No. 1 informed the City
Pir
PR 25176
10/01/2026 RLD
Page 2 of 4
Manager of the work that was required with the understanding that it would go to the Port Arthur City
Council in the form of Change Order No. 1; and,
WHEREAS,pursuant to Resolution No. 29-080, City Council approved Change Order No. 1 for
the Field Authorization approved on January 16, 2026 for the conflict box, water line casing, point
repair, and the removal of bid items regarding sewer construction that will not be performed from the
contract; Sewer line installation —bid item 1B, & post-construction TV inspection—bid item 3B. These
changes decreased the contract amount by $123,257.00, changing the previous contract amount of
$2,828,270.00 to the new contract amount of$2,705,013.00; and,
WHEREAS, Change Order No. 2 is being submitted by Elite Contractors & Equipment, LTD
requesting sixty-three (63) additional calendar days due to the following reasons: 1) Hurricane Edouard,
declared a natural disaster by Jefferson County, caused a five (5) calendar day delay due to the natural
disaster. 2) During construction, a natural gas pipeline owned by Texas Gas was discovered, causing an
additional three (3) days delay. 3) Proposed additional work on Imhoff Avenue, with no budgetary
impact, for an additional fifty-five (55) calendar days. This request changes the original completion date
of October 30, 2026 to a new completion date of January 1, 2027, see Exhibit A; and,
WHEREAS, approval of PR No. 25176 for Change Order No. 2 is herein deemed an appropriate
action.
NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF PORT
ARTHUR,TEXAS:
THAT,the facts and opinions in the preamble are true and correct; and,
THAT, the City Council herein approves Change Order No. 2 and authorizes the City Manager
to execute said Change Order to the contract with Elite Contractors & Equipment, LTD, of Kirbyville,
PR 25176
10/01/2026 RLD
Page 3 of 4
Texas requesting sixty-three (63) additional calendar days due to the following reasons: 1) Hurricane
Edouard, declared a natural disaster by Jefferson County, caused a five (5) calendar day delay due to the
natural disaster. 2) During construction, a natural gas pipeline owned by Texas Gas was discovered,
causing an additional three (3) days delay. 3) Proposed additional work on Imhoff Avenue, with no
budgetary impact, for an additional fifty-five (55) calendar days. This request changes the original
completion date of October 30, 2026 to a new completion date of January 1, 2027., see Exhibit A; and,
THAT, the City Manager is authorized to execute Change Order No. 2 with Elite Contractors &
Equipment, LTD, of Kirbyville, Texas, in substantially the same form, attached hereto as Exhibit B; and,
THAT, a copy of the Resolution shall be spread upon the Minutes of the City Council.
READ, ADOPTED AND APPROVED this the day of , A.D., 2026, at a
of the City Council of the City of Port Arthur, Texas,by the following vote:
Ayes:_ Mayor:
Councilmembers:
Noes:
Charlotte M. Moses
Mayor
ATTEST:
Christe Whitley Ned, TRMC, City Secretary
Pr
PR 25176
10/01/2026 RLD
Page 4 of 4
APPROVED AS TO FORM:
•
Roxanne Pais Cotroneo,Esq.
City Attorney
APPROVED FOR ADMINISTRATION:
Ron B
City - •ger
Suhail Kanwar,PE
Director of Public Services/City Engineer
APPROVED AS TO IABILITY OF FUNDS:
yn)B w ,M A-
ance Direct
(.4_,A04
Clifton Williams,CPPB
Purchasing Manager
EXHIBIT A
eere
e & Sg
To Whom it may concern:
Elite Contractors & Equipment LTD is requesting an additional 55 Calendar days to be
added to the contract for the additional work on Imahoff. Proposal is attached separate.
Elite Contractors& Equipment also requests an additional 8 Calendar days to be added
due to two separate events that took place.
1. Hurricane Edouard made land fall on September 1, 2026 were Jefferson County
issued a disaster declaration, we are requesting an additional 5 calendar days due
to the natural disaster. The Hurricane made landfall directly in Port Arthur Texas.
2. We ran into conflict with a natural gas pipeline owned by Texas Gas; this gas line
caused an additional 3 days of delays.This gas line depth did not meet standard as
it was only approximately 8"deep.
Elite is requesting a total of 63 calendar days to be added to contract.
Thank you,
Cody Ellis
���r
EXHIBIT B
CITY OF PORT ARTHUR
Public Works Engineering
DATE: October 1,2026
PROJECT: 7TH STREET IMPROVEMENT PROJECT
OWNER: CITY OF PORT ARTHUR
CONTRACTOR: ELITE CONTRACTORS&EQUIPMENT,LTD
CHANGE ORDER NO.:2
THE FOLLOWING CHANGES IN THE PLANS AND/OR SPECIFICATIONS ARE HEREBY MADE:
Adjust the Estimated Quantities to reflect the Actual Quantities used in the completion of the project:
Item Original
Description Unit quantity Unit Price Original Amount Total Quantity New Amount
No.
SCOPE
63 ADDITIONAL CALENDAR DAY EXTENSION
TOTAL CHANGE ORDER $ -
NEW CONTRACT
ORIGINAL CONTRACT AMOUNT $ 2,828,270.00 AMOUNT $ 2,705,013.00
ORIGINAL CONTRACT AMOUNT:1$ 2,828,270.00
TOTAL AMOUNT OF CHANGE ORDER NO.1: $ (123,257.00)
TOTAL AMOUNT OF CHANGE ORDER NO.2: $ -
NEW CONTRACT AMOUNT: $ 2,705,013.00
PREPARED BY APPROVED BY:
2-A-I.e /,ea-..,-wH
Roeisha L Diaz,Engineering Administration Suhail Kanwar,PE,City Engineer
APPROVED BY: APPROVED BY: 6e41)*1
`,'V QiL,
Clifton Williams,CPPB,Purchasing Manager
Elite Contractors&Equipment,LTD
APPROVED BY: APPROVED BY:
Gregory Casmire,Roadway Design-Engineering Ron Burton,CP ,Ci Manager
S:\Engineering\PUBLIC WORKS\PW-ENGINEERING\C.I.P.PROJECTS\Year 2025\7th ST.Stadium Rd to Duff Dr\Change Orders\Change Order 2\7th Street_CO 2_Elite