INTEROFFICE MEMORANDUM
Date: October 12, 2026
To: The Honorable Mayor and City Council
Through: Ronald Burton, CPM, City Manager
From: Jessie Dehn,P.E., Public Works Director
RE: P.R.25199—Authorizing the City Manager to contract with SCS Engineers of Houston,
Texas,for the installation of a soil vapor extraction system.
Introduction:
The intent of this Agenda Item is to seek the City Council's authorization for the City Manager to contract
with SCS Engineers of Houston,Texas,to install a Soil Vapor Extraction System for the remediation of
methane exceedances in gas probe 9 (GMP-9) and prepare a remediation plan in the amount of
$128,000.00.
Background:
SCS Engineers recently completed a quarterly gas monitoring event and recorded elevated methane levels
in GMP-9. As a result, SCS will submit a Permit Modification to the Texas Commission on
Environmental Quality (TCEQ) and implement a remediation plan in accordance with our Gas
Management Plan.
Budget Impact:
Funds are available from Account No. 403-50-320-5420-00-00-000.
Recommendation:
It is recommended that the City of Port Arthur's City Council approve PR 25199, authorizing the City
Manager to contract with SCS Engineers in the amount of$128,000.00.
"Remember,we are here to serve the Citizens of Port Arthur"
444 4th Street X Port Arthur,Texas 77641-1089 X 409.983.8182 X FAX 409.983.8294
PR 25199
10/06/2026 JAM
Page 1 of 3
RESOLUTION NO.
A RESOLUTION AUTHORIZING THE CITY MANAGER TO
CONTRACT WITH SCS ENGINEERS OF HOUSTON, TEXAS FOR THE
INSTALLATION OF A SOIL EXTRACTION VAPOR SYSTEM FOR THE
REMEDIATION OF METHANE EXCEEDANCES IN GAS PROBE GP-9
AND PREPARE REMEDIATION PLAN IN THE AMOUNT OF$128,000.00.
FUNDS ARE AVAILABLE IN THE PUBLIC WORKS DEPARTMENT
LANDFILL DIVISION — PROFESSIONAL SERVICES ACCOUNT
NUMBER 403-50-320-5420-00-00-000.
WHEREAS, the City of Port Arthur Landfill is required to monitor the landfill gas
quarterly according to the Texas Commission on Environmental Quality(TCEQ); and,
WHEREAS, elevated levels of methane were detected in the most recent quarterly
monitoring event; and,
WHEREAS, SCS will install a soil vapor extraction system to remediate the methane
exceedances in gas probe GP-9 and prepare a remediation plan; and,
WHEREAS, this procurement for professional services is authorized pursuant to Section
252.022(4) of the Local Government Code; and,
WHEREAS, SCS Engineers of Houston, Texas, has performed these services in the past
for the City and can perform these services for a total amount of$128,000.00 (attached hereto as
Exhibit A);
NOW,THEREFORE,BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY
OF PORT ARTHUR, TEXAS:
THAT,the facts and opinions in the preamble are true and correct; and,
THAT,the City Manager of the City of Port Arthur is hereby authorized to contract with
SCS Engineers of Houston, Texas in the amount of$128,000.00, as delineated in Exhibit "A";
and,
THAT, funding for this purchase is available in the Public Works Department Landfill
Division Professional Services Account Number 403-50-320-5420-00-00-000; and,
PR 25199
10/06/2026 JAM
Page 2 of 3
THAT, a copy of the caption of this Resolution be spread upon the Minutes of the City
Council.
READ, ADOPTED AND APPROVED this the day of , A.D.
2026 at a meeting of the City of Port Arthur, Texas,by the following vote:
Ayes: Mayor:
Councilmembers:
Noes:
Charlotte M. Moses
Mayor
ATTEST:
Christe Whitley Ned, TRMC
City Secretary
PR 25199
10/06/2026 JAM
Page 3 of 3
APPROVED AS TO FORM:
Roxann Pais Cotroneo, Esq.
City Attorney
APPROVED FOR ADMINISTRATION:
Ronald Burton, CPM
City Manager
Jessie Dehn, P.E.
Director of Public Works
APPROVED AS TO THE AVAILABILITY OF FUNDS:
ynd oswell, PhD, ICMA-CM
Director of Finance
Clifton . Williams, Jr., CPPB
Purchasing Manager
P. R. 25199
Exhibit
A
SCS ENGINEERS Environmental Consultants & Contractors
October 2, 2026
Mr.Jorge Morales Sent via email
Environmental Operations Manager
City of Port Arthur Landfill
4732 Texas 73
Port Arthur,Texas 77705
Subject: Proposal to Install Soil Vapor Extraction System
City of Port Arthur Landfill
Port Arthur,Jefferson County,Texas
Dear Jorge:
SCS Engineers(SCS) is presenting this scope of services to install a Soil Vapor Extraction (SVE)at the
above-referenced facility. This SVE system is recommended in response to confirmed landfill gas
exceedances associated with gas probe GP-9.
In May of 2025 twenty (20) passive vents (PVs) were installed to address the exceedance in GMP-9.
Following the installation of the PVs, GP-9 achieved compliance in early 2026. Compliance with the
regulatory level of 5% methane had been achieved for several months. However, during the second
May 2026 quarterly monitoring event GP-9 the methane concentration exceeded the regulatory limits
and continues to exceed.
On May 14, 2026, SCS Engineers completed a quarterly landfill gas monitoring event at the City of
Port Arthur Landfill. During this event,a methane level of 62.3%by volume was detected in landfill gas
monitoring probe GP-9 located on the southern boundary of the landfill approximately 1,000 feet east
of the landfill entrance. The methane gas detection equipment was recalibrated according to
manufacturer's recommended procedures and the gas probe was again sampled with a methane level
of 61.4% by volume.
SCS personnel immediately informed the landfill manager, Mr.Justin Thomas,of the results.SCS and
Mr.Thomas determined that there were no buildings or structures within 1,000 feet of GP-9 and that
there were no nearby buildings or structures that were at risk and no evacuations of buildings or
structures were warranted.
On May 15, 2026, SCS again recalibrated the gas detection equipment according to manufacturer's
recommended procedures and the gas probe was again sampled with a recorded methane level of
48.8% by volume.
In accordance with Section 4.1.1.2 Permit Boundary of Part III, Attachment 14, Landfill Gas
Management Plan, the landfill is required to notify the Executive Director through the regional office,
local and county officials, emergency officials, and the public. On May 14, 2026, SCS Engineers
notified the following entities:
12651 Briar Forest Drive, Ste. 205, Houston, TX 77077 1817-358-61621 Fax 281-293-7878
to,
Mr. Jorge Morales
October 2, 2026
Page 2
• TCEQ MSW Permits Section, Austin (via mailed copy to Megan Henson and to
MSWPER@tceq.texas.gov);
• TCEQ Region 10, Beaumont(via telephone and mailed copy to Kathryn Sauceda);
• Port Arthur Police Department(via telephone and mailed copy); and
• Port Arthur Fire Department(via telephone and mailed copy)
Since there were no structures within 1,000 feet of GP-9, no notifications to members of the public
were made.
In accordance with 30 TAC §330.371(c) 3 and Section 5 Remediation Plan of Part III,Attachment 14,
Landfill Gas Management Plan, SCS Engineers investigated the cause of the methane levels at the
area of concern.
A remediation plan was prepared and implemented on July 13, 202026. A copy of the remediation
plan was placed in the operating record and provided to the executive director with a notification that
the plan has been implemented.
On July 2, 2026, SCS conducted a methane delineation around GP-9 and found methane levels
ranging from 8.4 to 72.9 percent by volume. SCS also conducted a vacuum study on MPV 7, near GP-
9. This vacuum study indicated a reduction of methane concentration at GP-9.
As a result of the soil vapor study and vacuum study, it was determined to install a Soil Vapor Extraction
(SVE) System on MPV 6, 7 and 8. This system would be installed with an infrastructure that allows
additional SVE points to be added in the future as necessary.
On July 15, 2026, SCS submitted a July 2026 Remediation Plan to the TCEQ.
On August 10, 2026, a Notice of Deficiency (NOD) regarding the July 2026 Remediation Plan was
received from the TCEQ.
On September 4, 2026, SCS submitted response to the August 10, 2026 NOD including an updated
July 2026, Remediation Plan, Revised September 2026.
On September 22, 2026, the TCEQ issued an approval of the July 2026, Remediation Plan, Revised
September 2026.
Per the July 2026, Remediation Plan, Revised September 2026, existing MVPs (MVP 6, 7, and 8) will
be incorporated into a new SVE System. This system would be installed with an infrastructure that
allows additional SVE points to be added in the future as necessary.
SCOPE OF WORK
Task 1 -Soil Vapor Extraction System Installation
The proposed gas remediation includes conversion of existing gas probes PV-6,-7,and -8 to soil vapor
extraction (SVEs) and the installation of a Soil Vapor Extraction System designed to apply vacuum to
the SVEs.The system would be connected to the existing landfill electrical grid. This remediation plan
Mr. Jorge Morales
October 2, 2026
Page 3
has been developed based on the results of past investigation and monthly monitoring. No air
permitting will be required.
To support gas transport to the new SVE skid location, 4-inch HDPE header piping will be installed.
This includes connection to the existing PVs. The approximate locations of both the skid and the new
header are shown in Figure 1 attached to this proposal. Vacuum will be applied through a 3HP Soil
Vapor Extraction with the following features:
• 3 HP regenerative blower,XP motor
• Moisture separator with automatic level controls
• Integrated particulate inlet filter
• Automatic condensate transfer pump
• Vapor-phase granular activated carbon treatment vessel
• Manual dilution air valve with filter/silencer
• Vacuum monitoring and blower protection instrumentation
• Vapor sampling ports
• NEMA 4 industrial control panel with HOA controls and alarms
All above equipment will be mounted and plumed on a 40"X 48" powder coated steel skid.
To provide power for operation of the skid and SVE system electrical service will be extended from the
existing office building to the skid location. Scope includes trenching and installation of a new
underground electrical feeder,conduit,conductors, required terminations, backfilling,and restoration
of disturbed areas. All electrical work will be completed in accordance with applicable codes and
project requirements.
Task 2 —SVE Maintenance, Evaluation and Maintenance
SCS proposes to monitor, evaluation and maintenance of the SVE system for 8 months. It is
anticipated that the filters on the SVE system will last several years but monthly evaluation is
necessary. If additional monitoring is necessary, SCS will contact the City prior to the additional
activities for approval of additional funds.
SCHEDULE
SCS proposes to initiate work immediately upon receipt of notice to proceed from the City.
FEES
SCS proposes to conduct the Task 1, Soil Vapor Extraction Systeme Installation for $117,000 and
Task 2,SVE Monitoring, Evaluation and Maintenance for$11,000 on a lump sum basis and for a total
of$128,000. As with other recent projects for the City, receipt of a Purchase Order will suffice for our
notice to proceed. Any additional Services that the City may request with regards to this project or
other tasks, will constitute a change order for additional services, or prepared as additional task
orders.
Mr. Jorge Morales
October 2, 2026
Page 4
CLOSING
We appreciate the opportunity to assist the City with this very important project and look forward to
working with the City Staff to ensure the project's success. If you have any questions related to this
proposal, please feel free to contact J. Roy Murray at (817) 358-6156 or Gil Gabaldon at (817) 358-
6162.
Sincerely,
1
Gil Gabaldon, P.G. J. R y Murray, P.E.
Sr. Project Professional Vice President/Houston Office Director
SCS ENGINEERS SCS ENGINEERS
TBPE Registration No. F-3407
FIGURE 1:SVE Extraction System Location
.�*
SVE-7_
r .
+6 SVE-
4�
lik, ,"
,40,
00
/ ,
3HP Soil Vapor " e
Extraction Skid y ` °
with a Vapor Phase
jilt Carbon Filter
�=
t 407 D
� s
.r.
r5 n
t>
` � ,.. - Note:Perform an open-cut N
�`•` < installation across the road A
`" to lay electrical conduit,with
rehabilitation road repairs.
o
2
f,
r m
eC t O
A
o
•A C r d'
a
I
m, GP-9 j_j Permit Boundary Note:
r Tentative Skid Location
ill- Proposed Proposed SVE's For Proposal Purposes Only
1=1 Entrance Road
Approx.Electrical 0 1 80
Approx.4"HDPE Header 1' Feet
Port Arthur Landfill
___— _ PORT ARTHUR GP-9 REMEDIATION Approx.SVE System Location
ENVI AL
APPROX.SVE SKID SYSTEM Jefferson County,TX
Map Revised 08/21/2026 I Protect Number L-I I-I$40 I GIS Anal,st TJW