P.R. 25099 - NEGOTIATE A CONTRACT WITH FORNEY CONSTRUCTION FOR CONSTRUCTION MANAGER-AT-RISK SERVICES FOR THE NATURE/VISITOR CENTER PROJECT ON PLEASURE ISLAND
�r - www.PortArthurTx.gov INTEROFFICE MEMORANDUM Date: October 19, 2026 To: The Honorable Mayor and City Council Through: Ronald Burton, CPM, City Manager From: George Davis, Director of Pleasure Island RE: P.R. No. 25099 — Negotiate a Contract with Forney Construction for the Construction Manager At Risk Services for the Nature Center on Pleasure Island. Introduction: The purpose of this agenda item is to request City Council approval of P.R. No. 25099, authorizing the City Manager to negotiate a contract with Forney Construction of Houston, Texas,for Construction Manager-at-Risk(CMAR)services for the Nature/Visitor Center Project on Pleasure Island. Background: Pursuant to Resolution No. 26-170, the City Council authorized the City Manager to enter into a contract with PBK Architects, Inc., of Houston, Texas, for professional architectural and design services associated with the development of the Nature/Visitor Center on Pleasure Island. Subsequently, the City's Purchasing Division advertised a Request for Proposals (RFP) for Construction Manager-at-Risk services on June 14, 2026, and July 1, 2026. Eight (8) proposals were received and publicly opened on July 29, 2026. A committee comprised of City staff evaluated and scored the proposals in accordance with the evaluation criteria established in the RFP. Following the initial evaluation, four (4) firms were selected for interviews.Upon completion of the evaluation and interview process,the committee ranked Forney Construction of Houston,Texas, as the highest-ranked and most qualified firm to provide the requested services. The committee's evaluation and ranking documentation is attached as Exhibit "B" for City Council review. Budget Impact: There is no immediate budgetary impact associated with this Resolution,as the requested action is limited to authorizing contract negotiations. Any proposed contractual compensation, construction pricing, guaranteed maximum price, and associated funding requirements will be presented to the City Council for consideration as part of the subsequent contract approval process. "Remember,we are here to serve the Citizens of Port Arthur" P.O.Box 1089 X Port Arthur,Texas 77641-1089 X 409.983.8182 X FAX 409.983.8294 Recommendation: It is recommended that the City Council approve P.R. No. 25099, authorizing the City Manager to negotiate a contract with Forney Construction of Houston, Texas, for Construction Manager- at-Risk services for the Nature/Visitor Center Project on Pleasure Island, with the negotiated contract to be returned to the City Council for final consideration and approval. "Remember,we are here to serve the Citizens of Port Arthur" P.O. Box 1089 X Port Arthur,Texas 77641-1089 X 409.983.8182 X FAX 409.983.8294 P. R. #25099 1019/26 GD-tnr RESOLUTION NO. A RESOLUTION AUTHORIZING THE CITY MANAGER TO NEGOTIATE A CONTRACT WITH FORNEY CONSTRUCTION OF HOUSTON, TEXAS, FOR CONSTRUCTION MANAGER-AT-RISK (CMAR) SERVICES FOR THE NATURE/VISITOR CENTER PROJECT ON PLEASURE ISLAND; PROVIDING FOR SUBSEQUENT CITY COUNCIL APPROVAL OF THE NEGOTIATED CONTRACT WHEREAS, pursuant to Resolution No. 26-170, the City Council authorized the City Manager to enter into a contract with PBK Architects, Inc., of Houston, Texas, for professional architectural and design services associated with the development of the Nature/Visitor Center on Pleasure Island; and WHEREAS, the City of Port Arthur, through its Purchasing Division, solicited proposals for Construction Manager-at-Risk (CMAR) services for the Nature/Visitor Center Project on Pleasure Island, with the Request for Proposals (RFP) advertised on June 14, 2026, and July 1, 2026, attached hereto as Exhibit "A"; and WHEREAS, eight (8) proposals were received and publicly opened on July 29, 2026, in response to the City's solicitation; and WHEREAS, a committee comprised of City staff reviewed and evaluated the submitted proposals in accordance with the evaluation criteria established in the RFP, conducted interviews with four (4) firms, and ranked the respondents based upon their respective qualifications and proposed approaches to providing the requested services; and WHEREAS, following the evaluation and interview process, the committee determined that Forney Construction of Houston, Texas, received the highest overall ranking and was the most qualified firm to provide the Construction Manager-at-Risk services for the Nature/Visitor Center Project, as reflected in the evaluation and ranking documentation attached hereto as Exhibit "B"; and WHEREAS, the City Council finds that authorizing the City Manager to enter into negotiations with Forney Construction is in the best interest of the City and will allow the City to proceed with the development of the proposed Nature/Visitor Center Project while reserving final consideration and approval of the negotiated contract to the City Council. NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF PORT ARTHUR,TEXAS: Section 1. That the facts and opinions in the preamble are true and correct. Section 2. The City Manager is hereby authorized to initiate and conduct contract negotiations, on behalf of the City of Port Arthur, with Forney Construction of Houston, Texas, CITY OF PORT ARTHUR Request For Proposal Construction Manager -At- Risk for Nature and Visitor Center at Pleasure Island June 24, 2026 July 1, 2026 PUBLIC NOTICE CITY OF PORT ARTHUR,TEXAS ADVERTISEMENT FOR PROPOSALS IOTICE IS HEREBY GIVEN THAT sealed Proposals,addressed to the City of Port Arthur,will be eceived at the Office of the City Secretary,City Hall 444 4th Street or P.O. Box 1089, Port Arthur, exas 77641 no later than 3:00 P. M., Wednesday, July 29, 2026.Applicant names will be read loud beginning at 3:15 P.M.on Wednesday, July 29,2026 in the City Council Chambers, City fall,5th Floor for certain services briefly described as: REQUEST FOR PROPOSALS CONSTRUCTION MANAGER-AT-RISK FOR NATURE AND VISITOR CENTER AT PLEASURE ISLAND roposals received after the deadline stated above,regardless of method of delivery,will not be msidered and returned unopened. spies of the Specifications and other Contract Documents are on file in the Purchasing Office,444 h Street,City of Port Arthur,and are open for public inspection without charge.They can also be trieved from the City's website at www.portarthurtx.gov/bids.aspx or www.pubiicpurchase.com. )N MANDATORY PRE-BID MEETING FOR iS SCHEDULED FOR WEDNESDAY JULY 8,2026 10:00 A.M. AT THE PLEASURE ISLAND COMMISSION OFFICE LOCATED AT 520 .EASURE ISLAND BLVD.,PORT ARTHUR,TEXAS e City of Port Arthur reserves the right to reject any and all bids and to waive informalities. r Chapter 2 Article VI Sec.2-262(C)of the City's Code of Ordinance,the City Council shall not and a contract to a company that is in arrears in its obligations to the City. /s/Clifton Williams Clifton Williams, Purchasing Manager PUBLIC NOTICE CITY OF PORT ARTHUR,TEXAS ADVERTISEMENT FOR PROPOSALS NOTICE IS HEREBY GIVEN THAT sealed Proposals,addressed to the City of Port Arthur,will t received at the Office of the City Secretary,City Hall 444 4th Street or P.O. Box 1089, Port Arthr Texas 77641 no later than 3:00 P.M.,Wednesday,July 29, 2026.Applicant names will be re aloud beginning at 3:15 P.M.on Wednesday,July 29, 2026 in the City Council Chambers, C Hall,5th Floor for certain services briefly described as: REQUEST FOR PROPOSALS CONSTRUCTION MANAGER-AT-RISK FOR NATURE AND VISITOR CENTER AT PLEASURE ISLAND Proposals received after the deadline stated above, regardless of method of delivery,will not I considered and returned unopened. Copies of the Specifications and other Contract Documents are on file in the Purchasing Office,4 4th Street,City of Port Arthur,and are open for public inspection without charge.They can also retrieved from the City's website at www.portarthurtx.gov/bids.aspx or www.public purchase.Com NON MANDATORY PRE-BID MEETING FOR iS SCHEDULED FOR WEDNESDAY,JULY 8,20 AT 10:00 A.M. AT THE PLEASURE ISLAND COMMISSION OFFICE LQCATED AT 5 PLEASURE ISLAND BLVD.,PORT ARTHUR,TEXAS The City of Port Arthur reserves the right to reject any and all bids and to waive informalitii Per Chapter 2 Article VI Sec.2-262(C)of the City's Code of Ordinance,the City Council shall award a contract to a company that is in arrears in its obligations to the City. /s/Clifton Williams Clifton Williams, Purchasing Manager P. R. #25099 1019/26 GD- tnr Exhibit "B" 1. PROPOSAL TABULATION WORKSHEET Construction Manager at Risk PI { The City of Port Arthur - Nature and Visitor Center at Pleasure Island TOTAL CONSTRUCTION BUDGET: $7,000,000.00 New Nature and Visitor Center OFFERORS Daniels Construction PROPOSAL FORM Spawglass Setex N&T Forney Building And The Signature Managers of G&G Construction Group SouthEast Construction Texas • A. FEE PROPOSAL 1.CM Fee(%) For overhead and profit and all preconstruction services, list your proposed fee as a percentage of the cost of the 3.21% 2.75% 4.50% 0 work. 3.00% 2.00/0 4.00% 2.16% 3.78% 2.General Conditions(%) For all General Conditions,list your proposed cost as a percentage of cost of the work.Refer to Schedule"A"for 6.70% 6.95% 7.50% 13.87% 5.90% 11.80% 6.75% 6.37% all required items to be included in the General Conditions cost. 3.Pre-Construction Services All costs for pre-construction phase services including cost estimating,scheduling,building systems and material cost analysis are included in the FEE,item 1 $13,500.00 $15,000.00 $45,000.00 $15,937.45 $7,500.00 $43,000.00 $0.00 $0.00 above. B. Addenda Acknowledged: YES-1 YES-1 YES-1 YES-1 YES-1 YES-1 YES-1 YES-1 Jose Cardenas PM:Cayden PM Cayne PM:Vince Jabia PM Matt Supt Marc Cody Williford C. CM Personnel Submitted Fahm Demond Supt Darron PM:Matt Morris Kenneth Menino Barrows Casto& Supt:John Supt John Smith/Alton Frank Reynolds Charlie Mecina Supt Joshua Hermann Supt Jace Bush Robinson Anderson Frank Wright Rynolds PM Ueding D. CM Fee(%)+GC(%) 9.91% 9.70% 12.00% 16.87% 7.90% 15.80% 8.91% 10.15% 2. EVALUATION WORKSHEET Construction Manager at Risk City of Port Arthur - Nature and Visitor Center at Pleasure Island Qualifications&Proposals Submittal Date: Wednesday,July 29,2026 @ 3:OOPM OFFERORS(AVG WEIGHT LISTED ABOVE) EVALUATION CRITERIA WEIGHT Daniels Spawglass Setex N&T Forney Signature Group G&G CM of South East Texas 1. The Construction Manager's Fee and General Conditions 25 25.00 21.75 23.00 19.50 19.00 19.00 20.75 24.00 2. The reputation and experience of the Proposer and their services with similar projects and conditions as a Construction 20 19.75 19.50 17.50 13.75 20.00 10.75 15.75 14.00 Manager. 3. The Quality of the Construction Manager's work and services. 10 9.50 10.00 9.50 9.00 10.00 7.00 10.00 9.50 4. The Construction Manager's past relationship with the City.(Criteria will be graded with all proposers starting at 10 10 10.00 12.00 15.00 10.00 10.00 10.00 12.00 11.50 points.Good experience will increase from 10,while bad experience will decrease). 5. The experience and reputation of the Construction Manager's project team that would be assigned. 15 12.75 13.75 12.00 12.75 15.00 10.00 12.75 12.75 6. The Construction Manager's financial capacity appropriate to the size and scope of the project.(Provide the last fiscal year's 5 5.00 5.00 5.00 5.00 5.00 3.25 5.00 4.50 financial report). 7. Safety Record.Provide information regarding EMR(Employee Modifier Rate)or 10 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 OSHA incident rate. 8.The Construction Manager's Presentation of a Management Plan. 5 3.25 5.00 4.00 3.75 4.75 1.25 5.00 4.75 TOTAL POINTS: 100 95.25 97.00 96.00 83.75 93.75 71.25 91.25 91.00 OVERALL RANK>>> 1 3 1 2 7 4 8 5 6 3. EVALUATION INTERVIEW WORKSHEET Construction Manager at Risk City of Port Arthur - Nature and Visitor Center at Pleasure Island Interview Date: Monday August 10, 2026 OFFERORS (AVG WEIGHT LISTED ABOVE) EVALUATION CRITERIA WEIGHT Daniels Spawglass Setex Forney 1. The reputation and experience of the Proposer and their services with similar projects and conditions as a Construction 25 22.00 25.00 22.00 25.00 Manager. 2. The Quality of the Construction Manager's work and services. 25 25.00 24.00 24.00 25.00 4. The experience and reputation of the Construction Manager's project team that 25 23.00 19.00 20.00 25.00 would be assigned. 4. Approach and process to preconstruction services during design and during the 25 23.00 22.00 24.00 20.00 construction of the project. TOTAL POINTS: 100 93.00 90.00 90.00 95.00 \• } `` r. }f JJ��11 i \\.\ x } % i r "� �. _ 'aim.' - '.i'l 4 w.di » 5'- F'+ �� b a ,ram —i. n y ,.1 1! Y P z*. y 111 g K { ���r��. 4 � '..'sue+-' J t y .. n x 7 -. sue, • t^ 111 .'Sid'=.-vr"'+ Proposal Prepared For: Prepared By: ForneyConstruction City of Port Arthur, '` Office of the City Secretary: City Hall , -r -- 8945 Long Point Road 444 4th Street Houston, Texas 77055 Port Arthur, Texas 77641 In Regard To: r _,J- Preconstruction & Construction Services _y., t FORNEY-, U c,". L fr. 4rk! •n. TABLE OF CONTENTS Included: Offeror Information Section 1 Personnel Information Section 2 Projects Section 3 Organization Section 4 Claims and Litigation Section 5 Current Workload Section 6 Financial Information Section 7 Safety Section 8 Pricing Section 9 Other Required Forms Section 10 ..r � pp CO k Pt • ' ` , wv .i r Mrr '',' y '` '� VI'h �yg��_i 0 w 10„ Fr a, rip II j t 1 - u 1 1 I ' -4 10^4 " rryr . , ; r�#r f { z r fi Disc ' I R1. 114, 41 fPili. i i '.a7 4 } 11,✓ 'T.r w .�'+ .$ 4 /,'AA i 4 _ .... IF '400 � , y 'r " > �'� ° fry = , . a' _€. W d ygr i ..v4 `f 4.. 'aC, { 2 t f�4b�' s 1 54 ,+ , - t. --7.7_,;.- 1 ;;',"ItCr, ':;;-;„?.5'''.!'1',!;4::;.'4,;411tel-;:"4,1t ril t- � F \ t f frior 114 i P k fV, ,n t t � f lismommon ,iiiibb\ � a v,� � �i b s ,C a R !y ari � r , . . mic::c • ::„"w k i:::= t. • '"_ yy✓� fir'., r:A 1�. -..' '::,1.1,0;',.• '-'0,....' • yme +a ✓.' ;7r,, Gi r-.m ` : . ,.k�4 4t. 4-,_ r `(a "7 mfi, 'i ,azw... s,. Z f :,,,,p. , �h ..u.i a + ,J .1 .. rt 2 _.Y•'$ � ._ `,,, Ii)M 1 ."v'tl4R` * A '-* µ i ~{S•M@+.rl-r:{.. Lmullii... MO ''''41..t r ,,, , ,,,,,,g,,,,,-7,t, p-4'.,..,414 .4t444t4,;,,o.,-...r--,' A-' 1 bF M ?d a„ �±4 �St �a. fib;" ` Y., T'k .. A K+ 4- , �—�1 "�.W �' •i,.,. d 4 T �rs •fit°j}!--- LC=1) ., ,5n ="4�.`' �,q 'i•,�,,,q e + • v4 _ r.: of s, Offeror Information o '4 Name of Firm � CI; Forney Construction,LLC 4 • • Business Address G 8945 Long Point Road,Suite 200 ��F'ORNv% Houston,Texas 77055 Telephone Number 1 Fax Number 713.224.1900 1713.224.1901 Type of Organization Limited Liability Company Number of Permanent Employees i.Home Office: 50 employees ii. Field: 57 employees iii. Primary Contact:Jason Burt I jason.burt@forneyconstruction.com 1702.913.8212 Describe any substantial changes in ownership of your firm during the past five years. Prior to 2022, Forney Construction was solely owned by Tom Forney,who currently serves as Chairman of the Board. In 2022,the company expanded its ownership structure to include Alberto Garza, Chief Executive Officer,and Ryan Nunn, President& Chief Operating Officer, as equity partners. In 2025,the ownership group further expanded to include Kevin Fogarty,Vice President;Reed Roberts,Vice President;Luke Withers,Vice President;and Scott Linn,Director of Estimating. These partners play an integral role in the company's leadership,strategic planning,and long-term growth initiatives.The expansion of ownership reflects Forney Construction's commitment to leadership continuity, succession planning, and sustainable growth while preserving the values,vision,and operational excellence that have defined the company. How many years has your firm operated under its current form of business organization? 18 years List all professional or industry organizations in which your firm or its principals are members. Forney team members actively serve in board member roles that provide valuable guidance throughout major construction projects,from initial concept development and fundraising to architect and contractor selection and ultimately through project completion. Their expertise in these processes is invaluable to the nonprofits and organizations they support, ensuring successful project execution and long-term impact. Our past and current affiliations include the American Institute of Architects(AIA),the Society for Marketing Professional Services(SMPS),the Houston Arboretum and Nature Center Board of Directors,the Salvation Army Advisory Board,the Trees for Houston Board,and the Memorial Assistance Ministries Advisory Board.These organizations reflect our commitment to professional excellence,industry collaboration, and meaningful community engagement. In order to assist the City in determining whether there exists any conflicts of interest, please describe any business or family relationships between any City Council Member and: i.your firm; ii.any principal of your firm; iii.any subcontractor you are considering using to perform any portion of the project work;or iv.any principal of such subcontractor. There are no business or family relationships between any City Council Member and Forney Construction,any principal of Forney Construction,any subcontractor being considered to perform any portion of the project work, or any principal of such subcontractor. A Brief History of Our Firm Forney Construction is a full-service contractor that tailors delivery and serves our clients as General Contractor and Construction Manager. Local to Houston, Texas, we employ 107 employees within our Houston Headquarters in Spring Branch. With over a decade of Impact under our belt,we are making waves in the Houston Community and serve a variety of market sectors such as Healthcare, Community, Worship, Special Projects, Recreation, and Hospitality. Forney is a construction firm with a purpose.Every project we work on is fueled by the"why."When you select Forney as your partner,we work diligently to understand your business and tailor unique solutions that fit the challenges specific to your project.Tom Forney founded Forney Construction, LLC in 2008 as an organization with strong core values and a priority to maximize our Impact on the communities we serve. Forney Construction is a working vehicle for the company's core values,based on the acronym SERVICE. The experience and leadership of Forney's personnel provide the benefits of a large firm, but with the focused attention to detail that typically can only be found within a smaller firm. Our team of professionals recognizes that your project is more than a concrete foundation and four walls.We understand that of course there's a roof,but there's a lot more inside. Builders talk a lot about integrity. About trust and about value. But those are just the basics. The Forney differentiator is this:We know what's important and it's more than just the building. You get a completed project,yes-but you also get the experience of working with a partner who intimately understands your business and takes those extra steps to ensure you're happy. It is the knowledge that you have someone in your corner that's going to work for you until the job is done,whatever that takes.It is the IMPACT that your dollars have on the causes and people you serve.It is what it means to work with Forney. We Serve with Impact.Our Employees.Our Clients.Our Community. We come back to these values to measure and guide everything that we do. We are good stewards of your resources and operate with complete transparency,because we believe the money you have entrusted us with should be protected.We are reliable and have a proven track record of completing jobs on time and keeping our clients updated throughout every stage of the project. We serve with impact and approach the work we do every day with intention, purpose, and a desire to serve our community. ����� FOR'��o 42. a —t _ - Y TESTaly O ��'FORW' "For the past 20 years,I have been involved in numerous construction projects. Hiring Forney was one of the best FOR N EY BUILDS decisions I made. Not only were they competent and thorough WITH PURPOSE. with their knowledge and job performance,but they were able to put together an amazing team that developed a master We approach every construction site as plan that truly met the needs of our facility. Our budget was a platform to build up and strengthen maintained throughout the project,and Forney was extremely our community. conscious of utilizing existing relationships in our local Together we make a positive impact. community for vendors and subcontractors.' —Kim Brown, Camp Cho-Yeh Our Core Values Respect Others. Respect is something we must earn and give.Work hard to do both. Serve God,Others, Empower People. Then Self. The best investment we can make is in If we serve in this order, Integrity. the person sitting we will receive more than next to us. our share. God is with us;honor Him in all we do. S E R V I C E Commitment. Embrace Challenges. we said we If it's not working,fix would,the way we it.If we can't fix it,ask said we would, for help. when we said we would. Volunteerism. Share work,wealth,and wisdom.A lot.In any way Do what we are able. Forney by the Numbers l 1 Full-Time of our net profits are Employee Years working to Employees given back to the Volunteer Hours positively impact our community community .. •,, ', - ----- . . -... • ,-,) , . . . . ••-• t . ,. . ., ,.. ., . „....,.., ...,- . l,..., ; 1 '4',), "f',i,..,1 q,., -•,. 1 1,,;., i?"-1.,:t, ,•,. ,.., lc......:, .-...,' ., sys, .--- ' .! '"`'1-•:', )4' ; i ---,r ,..: ,* ,,,g 1,7, •.'' ' . ) ,.,,:''' : .k -,,,,..,;',. .,,,,Y.:.,7'i '* '' '''''' ' -'''''',"'" :•";:!'::'•Y'l..: 4400 421 IL'' i .' ' . '-' ,,- -41..1-1W 1., . , .,..- ';,,,,e;-',,#0.,,. , L L '... 'L ''' . '.. '',. ''',' . . . , I, 1 T- I ' [ - '[[ ;',/ -I '''''.'11[.. -;[,,,,'. /', . '--•,-:-.--!?4"-,[''[i[Z[ [2 ..t.„' „ ., . A , - - • -. .... 1 [ . . .. l:' .'''''',';-.'".. -. -,' .'..,..V‘,,',a .• ..„,...,!_ ' ', '',.1--71:` : '11 ,'..:,1 ,1 • :-:-.'.' '' ' ' 1 ', A , :‘* ,',..;,,;::.%:',..) : •, C„ : ' .,, '„,,I,,t, l` ,:.' 4 ... •.,,,,„•• ,,, . ,, ••, ,,,, , 1. v '4',i.;',;.. 1' • — — ' ' ' .. — ' ,b.4' [ -' A '•'' w. .[.' -1,A4 -.• ---: .,;[['sc.41\1 f- . —it, . . ,., 4,V[[[k'. ' ,['.\,',1['['[...-3-[:,['''[. [. • [[[`.ri,•,. - . .. ,,..... 4111=C ... — .,..„, k.,--., ,. - '' ,. ,, . ,„, . ,.. N.N. • .1, ., .. ., ...„ ,. . .,. ,....„ ... .... ,•, e•••• • 1111111 iMMII , , 1 , ••• .. :„., '• . • . . ,‘ t--'..•-,-'.,\ . .T. i,•••-:-, t 4•.. --'...', -' ''\‘, IND (.1,• ,,,,...., C0. , ','.., 4,*. ,A,•;; .-' ,e":-.,... =111111111 Z L.1116.... ...... 1‘/[ii.-.1, :,-,t4",,,J,. ['.',,-, ,[",•-: ,........„ ,. . r ...-_-: ' '- -'''''''.- 1 'i'i7;•J (1) . , • ...- •, .........•E- ....,I . , . . . . . . . Forney Management Team Our team of experienced professionals have been working towards a common goal of Impact for over 18 years. Our strategy, mission,and values have drawn some of Houston's top talent under one roof to deliver projects with SERVICE.With our leadership at the helm,Forney has become a firm that combines both the expertise of experience and the individual,client-focused attention that comes with a smaller firm. � 4 r � Tom Forney Alberto Garza Ryan Nunn CHAIRMAN OF CHIEF EXECUTIVE PRESIDENT & CHIEF THE BOARD OFFICER OPERATING OFFICER o, -a f 4 "'it" Ak 1 P A Erin Peters Tracy Daimler Kevin Fogarty Meredith Epley McWilliams CHIEF FINANCIAL VICE PRESIDENT VICE PRESIDENT VICE PRESIDENT OFFICER a x Reed Roberts Nick Rosinski Luke Withers Scott Linn VICE PRESIDENT VICE PRESIDENT VICE PRESIDENT DIRECTOR OF ESTIMATING Forney Construction,LLC is a full-service general construction firm with decades of combined experience that gets the job done.But we're not your typical construction partner.We listen. We understand your business goals, and we anticipate the challenges ahead to get you the biggest return on investment for your project.Our services and the integrated markets we support are a direct result of hearing what our clients need and taking action to support their continued success.We are the cornerstone for your project's success.Every site,every time. • Alberto Garza, Chief Executive Officer Upon graduation from Texas A&M University in 2001, Alberto began his career as a field superintendent to gain working experience that has served as one of the primary building blocks of his success. Alberto's leadership has proven instrumental in Forney Construction's continued success. As Chief Executive Officer, Alberto continues to invest his time in preconstruction services,an area in which he has consistently excelled.He is a client advocate,ensuring we provide the highest level of service,integrity,and commitment that we promised. EDUCATION: Texas A&M University I B.S.in Construction Science PROJECT EXPERIENCE: Houston Arboretum and Nature Center l H O U S T O N, TEXAS $15.5 million master plan to restore and protect The Houston Arboretum and Nature Center's natural property as well as expand the current education program.Project scope included a new Activator visitor and event pavilion, administration building, extensive landscaping restoration, new trail Turns thoughts into action networks,and new Children's Discovery Garden.This project operated under the sustainable SITES Gold-Certification Standard and encompassed wetland,ponds,boardwalks,and a phased strategic Strategic Decisive and critical thinker approach across the 75 acre development. Learner The Commons at Hermann Park l H O U S T O N, TEXAS Desire to continuously improve $28 million remodel of a 25-acre area in the southwest portion of Hermann Park transformed an Relator underutilized space into a welcoming destination.The park includes play areas,picnic pavilions, Enjoys close relationships with others an art lawn,a fragment of a historic live oak allee,and open areas of trees and lawn,all bordered by Arranger major roads and the back of the Houston Zoo.Designed to attract visitors from the rest of the park, Excellent coordinator and multi-tasker the Texas Medical Center,Rice University,and adjacent neighborhoods,the renovation introduced CLIENT TESTIMONIAL: new food service and expanded picnic areas,improved park entry points,a new destination play "1 have worked with Forney Construction area with water features,and the relocation of the prominent George Hermann statue. on numerous projects and project Bridgestone MUD Park l SPRING, TEXAS evaluations and have found them to $17 million 14-acre park development project for Bridgestone MUD transformed a low-lying forested be very collaborative,responsive and effective communicators.Alberto Garza site by raising the entire area approximately 3 feet above natural grade.The park features a 5-acre has displayed professionalism and has retention pond, drives and parking lots accommodating over 150 vehicles, and two multipurpose proven to be a man of strong character architectural buildings that include restrooms,storage,and covered seating.A 150-foot pedestrian and integrity.I highly recommend Forney bridge spans a portion of the pond,connecting miles of illuminated sidewalks,a custom-designed Construction,under the direction of Alberto Garza." playground,a three-zone splash pad,and two dedicated dog parks.The landscape scope included WESLEY TIDWELL, Memorial full irrigation and the installation of 50 native trees that were carefully relocated or transplanted Hermann Healthcare System across the site. Trees For Houston Headquarters and Tree Nursery I H O U S T O N, TEXAS $5 million ground-up construction of the new Trees For Houston headquarters facility including an outdoor education center and large tree nursery on a one-and-a-half-acre site. The 7,000 square foot office building includes large lobby and reception areas,Trees For Houston Executive offices and workstations,small conference room,multipurpose room,lounge with kitchen,event storage,IT Board & Community Involvement closet,indoor and outdoor restrooms and parking lot.The 1,400 square foot outdoor education space Memorial Assistance Ministries accommodates outdoor classrooms. In addition to these two spaces,the project included a 14,000 Board of Directors I October 2021-Present square foot tree nursery capable of holding thousands of trees to assist in Trees for Houston's goal of distributing and planting 10,000 trees within the next five years. Specialized Skill Sets: • Involved in Forney's most complex and high profile projects • Familiar with multiple building mixed-use development projects • Leads his teams with the end goal in mind Years in the industry I.,,,,.11,.,111,." .,, I.,....1 .. V 101,..1 v...i..�. Ryan Nunn, President & Chief Operating Officer An action-oriented and client-focused leader, Ryan has an extensive and comprehensive background in working with diverse entities.His professionalism,technical expertise,and attention to detail make him an excellent leader and has earned him glowing recommendations from some of Houston's most notable hospitality organizations.Ryan is a knowledgeable experienced leader who - mentors up-and-coming Forney staff,ensures that each project team has the resources required to complete each project and is ultimately responsible for the success of your project. PROJECT EXPERIENCE: Hotel Daphne HOUSTON, TEXAS $28 million new construction of a European-style boutique hotel to the heart of Houston Heights, ' ? offering a unique blend of charm and modern comfort.The hotel features a total of 51 thoughtfully Achiever designed rooms,along with a pool,restaurant,indoor lounge,outdoor cabana areas,and ground-floor Leads by example retail space.Designed to complement the vibrant character of the Heights neighborhood,the property Positivity offers guests a welcoming,walkable experience surrounded by local shops and dining.With a focus on Generous with praise refined finishes and a warm,community-oriented atmosphere,this hotel aims to become a destination for both travelers and locals alike. Woo People-oriented,rapport-builder The Houstonian Hotel,Club&Spa I HOUSTON, TEXAS Communication Multiple projects totaling$79.5 million,the largest being a four-phase renovation of an occupied Easily puts thoughts into words 3-story 467,000 square foot fitness club.The project scope included infill of existing racquetball Arranger and basketball courts,a new atrium which will be the Club's interior focal point and gathering space, Excellent coordinator and multi-tasker relocation and expansion of dining and kitchen space to include new exterior dining deck with CLIENT TESTIMONIAL: Avadek canopy.Additional major scope included a relocated guest check-in,skylight replacement "Ryan's creative approach and focus over the new atrium,relocated retail space and sales offices,high-end finishes throughout,new turf on the vision have proved essential in workout area and monumental structural steel stair at the atrium to the upper level fitness areas. navigating the complexities of our project. His attention to detail and professionalism Other projects include The Houstonian Hotel which was a renovation of 285 guest rooms,Concierge made my job easy.River Oaks Country Suite,Tribute restaurant as well as interior and exterior renovations to the Trellis Spa and extension Club couldn't be more pleased with Ryan's of The Houstonian-Solaya Spa and Salon. work,as well as the work of all other Forney team members assigned to the River Oaks Country Club I HOUSTON, TEXAS ROCC renovation and expansion." $66.6 million worth of renovations at River Oaks Country Club consisting of a series of separate 1 o E s EN DY,River Oaks Country projects,the largest being a complete renovation of the east end pool area.This project included the Club demolition of the existing east side of the fully operational club house that was built in the 1950's, along with the removal of the existing pools and structure.This made room for the renovation of four new water attractions,a 4,000 square foot basement and two-story facility.The new building houses a new bar,kitchen and dining,kids'area, poolside cabanas,a playground and basketball court. Other projects for the club included new construction of a 2-story Pro Shop and halfway house on the golf course, renovations to the member's entry and lobby area,parking lot expansions, pickleball courts,and new landscape and hardscape. Specialized Skill Sets: • Experience phasing,scheduling,and coordinating teams on large scale projects • Specializes in hospitality projects • Leverages experience in a variety of roles to serve as a mentor and leader to project teams Years in the industry I'UL d II lel I luel ul II le I'dlUIC 01 V IJI WI%.el'lel di riedbule IJldlIU IJIuielA Kevin Fogarty, Vice President With 20 years of experience,Kevin Fogarty is a seasoned professional with a comprehensive background of construction experience both as a project manager and superintendent. His extensive portfolio of work is evidence of his attention to detail,hands-on problem solving mindset, and ability to communicate with clients in real time.As Vice President,Kevin is responsible for ( overseeing all healthcare projects and works closely with his project teams while constantly measuring the performance of schedule,budget,quality,project control and safety throughout the duration of his projects. F a i( PROJECT EXPERIENCE: + Shriners Hospitals for Children-Housing and Garage I GALVESTON, TEXAS At ! E $37.5 million new construction of a 4-level 320 stall cast-in-place parking garage consisting of 140,700 square feet as well as a new 2-story 31,000 square foot housing building that will include 40 Strategic units,with elevated vestibule connection,into the existing Shriners Hospital.Both new structures Decisive and critical thinker were built to better serve patients and their families going to the Galveston facility for care.The Futuristic site posed complex logistics as the active hospital and residential area directly border the project. Inspired by what is yet to come Shriners Hospitals for Children-Renovation&Consolidation I G A LV E S T O N, TEXAS Self-Assurance $32 million renovation of 80,000 square feet to accommodate relocation of the orthopedic function Strong inner compass of the Houston facility to Galveston operations. This scope includes the renovation of operating Achiever rooms,construction of new pre-operation and post-operation areas, renovation of patient rooms, Leads by example new clinical areas,new imaging centers,lobby renovations,along with ancillary spaces to support Maximizer patient care areas.All mechanical,electrical,plumbing and life safety systems were updated in all Stimulate personal and group excellence areas.The design team incorporated high-end custom finishes and fixtures throughout the hospital CLIENT TESTIMONIAL: to create a cutting-edge and breath-taking facility to serve children and their families.Many of these "I have thoroughly enjoyed my time working with the Forney team specifically fixtures and finishes had extensive lead times and shipping transit durations as they were European- Paul Keating,Kevin Fogarty and Joanna manufactured.Heavily-detailed scheduling and coordination was required as the hospital remained in Wojcik.They have been a valuable full operation throughout the course of construction. asset to the project teams they have been associated with.They are honest, Baylor St.Luke's Hospital-Network IT Refresh I H 0 US TO N, TEXAS dependable,and incredibly hard-working. $27 million design-build project which included the relocation and remodel of(66)IDF rooms in the They always have the owner's best interest hospital and(4)MDF rooms in order to bring these areas up to the CommonSpirit Health standards, at heart and assist to bring solutions to issues,along with identifying risk,scope all while IT services will remain operational.This turn-key planning required coordination and design gaps&cost savings.They will often go of all low voltage raceway systems, including backbone fiber installation and wireless access above and beyond what is called for in points for the entire hospital.Also included were design and construction upgrades for required the base scope of work to help make a successful project." power,grounding,HVAC needs as well as required wall and ceiling bracing,backing and mounting materials to support installation of the Owner's IT equipment. Memorial Hermann League City Convenient Care Center I LEAGUE CITY, TEXAS - RYAN HERR,CHI St.Luke's Health $13 million ground-up construction of Memorial Hermann's satellite center and subsequent build-out of the 41,000 square foot healthcare interior,surrounding parking lot paving and exterior landscaping. This comprehensive healthcare facility provides 24 Hour Emergency Care,Primary Care, Advanced Imaging, Breast Care Center,Sports Medicine & Rehabilitation, Diagnostic Lab and Occupational Medicine to families in the League City Community. Specialized Skill Sets: • Consistent and reliable communicator • • Experience managing and overseeing complex projects • Excellent ability to coordinate moving pieces Years in the industry IYV\a,,,C„I..C, WI ,,,G, ka V 1.,1,,,3 .,..,,C,, ,,,, ,,,,,,,,,,,,,,,,,,,,,,r,.,�..... . fritgrit_ Reed Roberts, Vice President } Reed is a dedicated client advocate and strategic problem solver with a proven ability to employ meticulous coordination within his teams. His ability to adapt helps him effortlessly manage multiple projects,priorities and people.Reed's devotion to his clients motivates him to uphold and escalate performance standards in pursuit of personal and team excellence. w, • EDUCATION: Texas A&M University I B.S.in Construction Science \ PROJECT EXPERIENCE: Christ the King I HOUSTON, TEXAS $35 million comprehensive campus master plan that includes both new construction and interior renovations to support the parish's long-term growth and ministry needs. The scope includes construction of a new 23,000 square foot Sanctuary and social hall,a new 17,000 square foot youth building and gym,approximately 15,000 square feet of interior classroom and office renovations, Adaptabilit and 13,500 square feet of interior renovation within an existing structure,including the addition of Comfortable in times of change a second mezzanine level to create twelve new classrooms and eight new restrooms.The project Relator will be delivered through a phased construction approach coordinated around church services, Enjoys close relationships with others school activities, and parishioner schedules to ensure the campus remains fully operational Restorative throughout construction. Finds improvements and solutions Bridgestone MUD Park I SPRING, TEXAS Positivity $17 million 14-acre park development project for Bridgestone MUD transformed a low-lying forested Generous with praise site by raising the entire area approximately 3 feet above natural grade.The park features a 5-acre Competition retention pond,drives and parking lots accommodating over 150 vehicles, and two multipurpose Motivated and measurement oriented architectural buildings that include restrooms,storage,and covered seating.A 150-foot pedestrian CLIENT TESTIMONIAL: bridge spans a portion of the pond,connecting miles of illuminated sidewalks,a custom-designed 'Like many church owners,we are not the playground,a three-zone splash pad,and two dedicated dog parks.The landscape scope included easiest client to work for.Our parishes are represented by diverse committees, full irrigation and the installation of 50 native trees that were carefully relocated or transplanted and each pastor brings forth a unique across the site. personality.All the while,as the governing body,the archdiocese has standards that Citizens Medical Center-Emergency Department I VICTORIA, TEXAS need to be met.Reed has proven to be a trustworthy partner and an advocate who $11 million addition and renovation of the existing Emergency Department at the Citizens understands our needs.I have seen Reed Medical Center in Victoria,Texas. The project scope consisted of a 17,983 square foot single take on responsibility to make the project a story addition and a 6,576 square foot renovation giving the hospital two new trauma rooms, success.Many of our projects are heavily budget driven and our designs demand high twenty-three private patient rooms and two decontamination showers/patient care rooms.The quality.Reed is involved from the beginning structure is unique in the fact that it is a solid concrete,two-way structure,with a crawl space. of preconstruction to the end of closeout to Construction of this project was completed in three phases.The scope of work completed during ensure that these needs are met.We are in constant communication throughout,and phase one consisted of the demolition of the existing Emergency Room entry,construction of a he knows his projects.Lastly,I would like new temporary entry and site utilities as well as earth and site work. Phase two consisted of a to recommend Forney Construction as a company.Their culture of servant leadership new base building structure as well as the medical interior build out,while the renovation of the aligns perfectly with our mission:to serve existing Emergency Room Department,converting this space into the new trauma department, God and bring the faithful to Him.' was completed during phase three of construction. -PABLO HERNANDEZ The Archdiocese of Galveston-Houston Specialized Skill Sets: NMI • Experienced in constructing projects within occupied facilities • Regularly manages projects with complex phasing • Fosters efficient and effective coordination and communication Years in the industry throughout projects mit a II ICI I lUal VI ti lc Natal a VIpItUI Ral at rl00Julc Ia Ia,1U FAujct t Luke Withers, Vice President Luke Withers has been working in the Houston construction industry since his graduation from Texas A&M University.He works closely with his project teams and consistently measures performance • 7 of schedule,budget,quality,project control,and safety.With an expansive portfolio of construction that is highly technical,phased,and within operating campuses,Luke is a seasoned leader who represents Forney's commitment to serve clients with transparency,reliability,and excellence. EDUCATION: Texas A&M University I B.S.in Construction Science,Minors in Architecture&Leadership PROJECT EXPERIENCE: Hotel Saint Augustine I HOUSTON, TEXAS $36.5 million construction to build Hotel Saint Augustine,a new boutique hotel adjacent to The Menil Collection. Featuring seven separate two-story buildings totaling approximately 63,000 square feet. Spanning two acres,the property includes 71 rooms and suites anchored by a courtyard pool, an Relator intimate lobby bar, private event space, and the brand-new restaurant, Perseid. The buildings are Enjoys close relationships with others thoughtfully connected by open-air bridges and walkways,creating a seamless flow throughout the Achiever site while reflecting the character of the surrounding arts district. Leads by example The Houstonian Hotel,Club&Spa I HOUSTON, TEXAS Activator Multiple projects totaling $79.5 million,the largest being a four-phase renovation of an occupied Turns thoughts into actions 3-story 467,000 square foot fitness club.The project scope included infill of existing racquetball Responsibility and basketball courts,a new atrium which will be the Club's interior focal point and gathering space, Committed to following through relocation and expansion of dining and kitchen space to include new exterior dining deck with Harmony Avadek canopy.Additional major scope included a relocated guest check-in,skylight replacement Seeks areas or agreement over the new atrium,relocated retail space and sales offices,high-end finishes throughout,new turf workout area and monumental structural steel stair at the atrium to the upper level fitness areas. Other projects include The Houstonian Hotel which was a renovation of 285 guest rooms,Concierge CLIENT TESTIMONIAL: Suite,Tribute restaurant as well as interior and exterior renovations to the Trellis Spa and extension "It was definitely a pleasure to work with of The Houstonian-Solaya Spa and Salon. Luke and his crew on a daily basis.Forney was able to complete this job in time and Kirkwood Restaurant I HOUSTON, TEXAS satisfy all the criteria needed...This project $7.1 million renovation transforming the ground-floor lobby of a commercial office tower into a was a complete success.It is clear Forney vibrant,7,000+square foot restaurant that brings together Gulf Coast flavors and global influences. takes pride,ownership and responsibility in The scope includes reworking the structure, installing all-new MEP systems, building out a full the projects they construct.Further,Forney has proven they can meet any construction commercial kitchen, custom bar, sound-treated dining areas, and high-end finishes throughout. challenge and achieve a successful Designed with flexibility in mind,the space will cater to everything from business lunches to evening outcome." dinners,and will also feature outdoor patio seating and modern A/V setups.The goal is to create a -JUL I E B LU M,Memorial Park Driving stylish but welcoming restaurant within a busy,mixed-use office tower environment. Range Terry Black's BBQ l HOUSTON, TEXAS $5.9 million,7,000 sq ft new restaurant marks the first Houston site for Austin-based Black Family Hospitality's Terry Black's BBQ. It includes a pit house,outdoor courtyard,parking,service areas, and a 600 sq ft elevated mezzanine for dining.The restaurant offers a beer garden with a large pergola,custom pits,reclaimed barn wood,antique barn metal ceilings from Smithville,and a brick exterior with burnt cedar boards.It blends durable construction with Terry Black's authentic Texas barbecue style. Specialized Skill Sets: • Established experience in the hospitality sector • Excellent ability to coordinate moving pieces and identify efficiencies • Leverages having held multiple roles throughout Forney to the benefit of each client Years in the industry oy``vFoR' Project Management Q. �a Forney Construction understands that a nature center requires seasoned professionals who recognize • a ~ that the project is more than a building-it is an educational and community resource designed to connect • visitors with the surrounding environment.Our proposed team brings extensive experience delivering parks, recreation,public facility,and site-intensive projects that require thoughtful planning,close coordination, yFORN� careful stewardship of natural resources.Their depth of experience enables them to anticipate challenges,protect sensitive site features, coordinate complex building and site components, and maintain clear communication with the owner, design team, stakeholders, and trade partners throughout construction. PROJECT EXECUTIVE DID Jason g' _ Burt DIRECTOR OF ESTIMATING f VICE PRESIDENT OF FIELD © y OPERATIONS ,r11 1 Scott SENIOR PROJECT MANAGER V Linn Nick Rosinski i Morris . �r l GENERAL SUPERINTENDENT 1 SENIOR PROJECT SUPERINTENDENT Steve Mounts .I4. Frank Runnels i ) SAFETY& QUALITY TEAM 1- 2 Safety By Design As part of our on-boarding process,each staff member-regardless of position-is asked to take a StrengthsFinder assessment. Not only does this help us learn about our teammates and how to communicate with each other more effectively,it also helps us determine project teams.We look for teams whose strengths complement the others to maximize your client experience. In the resumes that follow,you will get an intimate glimpse into this team,their strengths and get a feel for what really makes them tick. Jason Burt, Project Executive Throughout his 30+ years of construction and site work experience, Jason has amassed an expansive portfolio of projects,including an impressive collection of renowned golf courses around the world.His vast experience,coupled with his problem-solving ability and desire to do things the ..,1 c..' right way,makes him an indispensable member of a project. Jason is a reliable team player who confidently and calmly manages people,plans and complex projects. PROJECT EXPERIENCE: ° I Houston Arboretum and Nature Center I HOUSTON TEXAS $15.5 million master plan to restore and protect The Houston Arboretum and Nature Center's natural property as well as expand the current education program.The project scope included a t new visitor and event pavilion,administration building,extensive landscaping restoration,new trail Strategic networks,and new Children's Discovery Garden.This project operated under the sustainable SITES Decisive and critical thinker Gold-Certification Standard and encompassed wetland,ponds,boardwalks,and a phased strategic approach across the 75 acre development. Arranger Excellent coordinator and multi-tasker The Commons at Hermann Park I H O U S T 0 N, TEXAS Responsibility $28 million remodel of a 25-acre area in the southwest portion of Hermann Park transformed an Committed to following though underutilized space into a welcoming destination.The park includes play areas,picnic pavilions,an Futuristic art lawn,a fragment of a historic live oak allee,and open areas of trees and lawn,all bordered by Inspired by what is yet to come major roads and the back of the Houston Zoo.Designed to attract visitors from the rest of the park, Ideation the Texas Medical Center,Rice University,and adjacent neighborhoods,the renovation introduced Improves on the existing new food service and expanded picnic areas,improved park entry points,a new destination play area with water features,and the relocation of the prominent George Hermann statue. CLIENT TESTIMONIAL: Eagle Pointe Recreation Center-Fitness Addition M O N T B E LV I E U, TEXAS Jason is an excellent site development manager who has proven himself for many $9 million addition and renovation to the Eagle Pointe Recreation Center expanding fitness,wellness, years.Jason is not afraid to get into the and community recreation amenities while enhancing the existing facility. The project includes trenches with his crew and is extremely construction of a new two-story fitness addition featuring open fitness areas,aerobic and dance resourceful when it comes to overseeing studio, fitness room, indoor turf training area, conference spaces, locker rooms, and supporting projects.I can attest to Jason's character, integrity,honesty,responsibility,and administrative areas. Renovations to the existing recreation center reconfigure portions of the excellence." facility to create improved circulation, expanded child watch areas, updated locker rooms, a new s R I a N B ow E R s, Fazio Design sprinkler system through the entire building and enhanced support spaces while maintaining ongoing operations. Site improvements include expanded parking, accessible routes, new sidewalks, fire access improvements as well as landscaping. Shadow Creek Ranch Parks PEARLAND, TEXAS $5 million expansion of the existing sports complex including the addition of an artificial turf multi-purpose field,which features a dedicated cricket field as well as a miracle field designed for Board & Community Involvement accessibility, along with enhanced sidewalks for improved pedestrian access. In addition to the Trees For Houston installation of fencing around the entire complex, there are two newly constructed parking lots, Board of Directors I June 2026-Present upgraded sidewalks, and fresh landscaping to beautify the area. Furthermore, the project will Houston Arboretum&Nature Center include a new maintenance facility building and a new concessions building that will house public Board of Directors I January 2023 Present restrooms,training rooms,and locker rooms for athletes and visitors. Specialized Skill Sets: • Ensures clear,consistent updates and alignment with client and team expectations • Guides teams through evolving project needs while maintaining momentum • Analyzes complex situations,identifies solutions,and makes effective decisions Years in the industry Scott Linn, Director of Estimating Since joining the Forney Construction team,Scott has participated in virtually every bid that the company has submitted,giving him a wide-range of experience with different project types.Since Scott joined the team, Forney's average contract value jumped from $200K to$2.6 million, and the company's volume has consistently grown each year.Scott knows the Houston subcontractor market well,including subcontractor work loads,and uses historical data to select the best possible R subcontractors for each bid we submit. EDUCATION: ./ Texas A&M University I B.S.in Construction Science PROJECT EXPERIENCE: Houston Arboretum and Nature Center I H O U S T O N, TEXAS $15.5 million master plan to restore and protect The Houston Arboretum and Nature Center's natural property as well as expand the current education program.Project scope included a new Responsibility visitor and event pavilion, administration building, extensive landscaping restoration, new trail Committed to following through networks,and new Children's Discovery Garden.This project operated under the sustainable SITES Restorative Gold-Certification Standard and encompassed wetland,ponds,boardwalks,and a phased strategic Finds improvements and solutions approach across the 75 acre development. Achiever The Commons at Hermann Park I H O U S T O N, TEXAS Leads by example $28 million remodel of a 25-acre area in the southwest portion of Hermann Park transformed an Analytical underutilized space into a welcoming destination.The park includes play areas,picnic pavilions,an Thinks things through art lawn,a fragment of a historic live oak allee,and open areas of trees and lawn,all bordered by Intellection major roads and the back of the Houston Zoo.Designed to attract visitors from the rest of the park, Capable of deep and philosophical thought the Texas Medical Center,Rice University,and adjacent neighborhoods,the renovation introduced new food service and expanded picnic areas,improved park entry points,a new destination play CLIENT TESTIMONIAL: area with water features,and the relocation of the prominent George Hermann statue. "We engaged Forney early on in our design Bridgestone MUD Park I SPRING, TEXAS and documentation schedule in order to $17 million 14-acre park development project for Bridgestone MUD transformed a low-lying forested make sure that the projects were designed within our target budget and help the design site by raising the entire area approximately 3 feet above natural grade.The park features a 5-acre team execute their visions with no impact retention pond, drives and parking lots accommodating over 150 vehicles, and two multipurpose on the overall schedule...Their contributions architectural buildings that include restrooms,storage,and covered seating.A 150-foot pedestrian in creative value engineering,their high bridge spans a portion of the pond,connecting miles of illuminated sidewalks,a custom-designed quality sub-contractors and their clear communication to all parties has ensured playground,a three-zone splash pad,and two dedicated dog parks.The landscape scope included Forney a spot on our preferred contractor list full irrigation and the installation of 50 native trees that were carefully relocated or transplanted for all future endeavors.With their guidance across the site. during the pre-construction phase,lam Pat Hallisey Park I LEAGUE CITY, TEXAS positive that we have avoided significant delays during the on site construction Forney Construction participated in the design process as a consultant to the landscape architect. portion for both our hotels.l highly Our team has provided preliminary pricing through each stage of design,totaling five budgets since recommend Forney Construction and believe 2022. Using a mix of historical data and subcontractor feedback,we have continuously verified they will be an asset to any project team.' costs at each design stage.We also worked to identify changes in scope,track cost impacts,and -SOPHIE AURELIO,Bunkhouse Hotels develop potential cost-saving solutions. The project encompassed a park totaling approximately 100 acres and includes several athletic fields for baseball,softball,soccer,and tennis/pickleball, along with support spaces for maintenance,restrooms,concessions,parking,and the associated utilities and detention. Specialized Skill Sets: • Extensive knowledge of the Houston Subcontractor Market • Precise and detail-focused • Routinely coordinates phasing and logistic plans for large scale projects Years in the industry Project Manager's Roles and Responsibilities r Project Manager44 Our project manager will be responsible for overseeing all aspects of planningand execution �° the projects are completed successfully.With a strong focus on budget,schedule,quality,and safety,they will coordinate with all stakeholders to deliver a meaningful and to ensure Fa�E1 '' in maintaining clear communication, managing risks, and ensuring that every detail is handledy well-executed project. Their leadership will be instrumental They will serve as the driving force behind project delivery, ensuring that team efforts are aligned and consistently achieved. Below are our project manager's key responsibilities: with precision and care. project goals are Project Planning&Execution - Oversee the overall planning and execution of the project, ensuring the ej ro on schedule and within budget. p ct remains Scheduling & Procurement - Develop project schedules, procurement plans, and cost controls while managing compliance and any necessary change orders. Stakeholder Communication - Serve as the primary liaison between the owner, design team, and subcontractors, fostering strong relationships through regular updates and addressing concerns as they arise. Financial Oversight - Approve invoices, track expenses, and implement cost-saving measures to maintai stability throughout the project. n financial Risk Management- Identify potential project risks and develop mitigation strategies to minimize disruptions a smooth execution. P nd ensure Quality Assurance - Ensure all work aligns with contract documents and specifications, overseein ualit efforts throughout the project. 9 q y control Project Documentation - Ensure maintenance of all project records, including RFIs, submittals, meeting minutes, and progress reports,ensuring thorough documentation and compliance- Project Closeout- Facilitate the final stages of the project,including inspections,punch lists,warranty docum and turnover to the client. entation, Through their leadership and proactive management, our project managers will ensure that every phase of executed with precision,efficiency,and professionalism. By fostering collaboration among all stakeholders and maintaining a clear focus on project objectives, they will drive successful outcomes that meet or exceed client expectationsatiProject upholding Forney's commitment to excellence. while la t '. v J ✓ •,:.„.....„ ._ 2."`-'-,--.-. ' .,,e,. .,..,::•:.:,_.: .• . • •• .„........i. ;.•.„,, , ,f s ,„ _ - '" t, 4 - �*" A ., '+^ _- ..p'. 2 • err f�� !'. ��J�= O ' �' 'R l�., r t c.„.,. .....0.K.....„.. ]I !- x y.,�r� `h Y�d`(:'` fi*' -.:. ... - f F -?et' YY �R �if 13 1 � '� }.. "S.,S r' w y r'TC' 'S t+; - '. ., • - 'T :.:elS t 4,.-` `- ` dit-. r r i, _..3_+ ..jai .- -' f � �L , ,, "The Forney Project Team has played a pivotal role in helping ouri. ` ��''* .�y, v ` .t om organization transform into our master plans guiding R:,_= � -, , " i, i I e.... team was knowledgeable,and deeply committed to our construction h # :-� '-'Y'7� ;'_ �j�,^'' i, / success.They were a lea ` ' '-1 ' allowed us to accomplish our rgoals staying in budget and fullyhavee to work with and their efforts _ - _�_� operational throughout the entire construction process." ----�_ .-..a �' .1 '`� ___ Debbie Markey,Executive Director,Houston Arboretum&Nature Center Superintendent's Roles and Responsibilitiesdi ` Superintendent Our Superintendent 1 _ , will take on the critical role of on-site leader, responsible for managing day-to-day . s V construction activities, maintaining the project schedule, and upholding high standards of quality and safety. They will coordinate all field operations, ensuring clear communication, smooth execution, and successful project delivery. Their expertise in field management will be essential to driving productivity, resolving challenges in real time, and ensuring the project progresses efficiently and safely. Below are their key responsibilities: Daily Construction Management - Oversee daily construction activities, ensuring all work progresses according to the project schedule. Project Schedule Maintenance- Maintain and update the project schedule,making necessary adjustments to keep the project on track and aligned with deadlines. Subcontractor Coordination - Coordinate subcontractors, ensuring each trade performs efficiently and meets project milestones while fostering effective communication. Quality Control - Implement quality control measures, regularly inspecting work to confirm compliance with project specifications and industry standards. Safety Enforcement-Prioritize safety by implementing OSHA regulations,enforcing jobsite safety plans,and conducting regular safety meetings to promote a safe work environment. Material Management - Manage material deliveries, ensuring that materials arrive on time and are properly stored to prevent delays in construction. Site Logistics Oversight - Oversee site logistics, including jobsite security, equipment management, and overall site organization to ensure efficient operations. Daily Activity Documentation-Document daily activities through detailed reports,tracking manpower,progress,delays, and incidents for accurate project records. Final Inspections & Closeout - Take charge of final inspections, punch list resolution, and site demobilization as the project nears completion,ensuring a seamless transition to project turnover. Through their hands-on leadership and deep understanding of field operations, our Superintendents will ensure that construction activities run seamlessly from start to finish. By fostering collaboration among all trades,maintaining rigorous safety and quality standards, and proactively addressing challenges on site,they will be key to delivering projects on time, within budget,and to the highest level of craftsmanship.Their commitment and expertise are essential to transforming plans into successful,well-executed projects. v. - - .�s r _ .y... -.g --.1; a �/ - _ yr' �,.% w _. . :, ...„....„I . , ,, w. ,„.„..._.. . . ,...,...„.„.....-. „--.„.z . _ . ,-., _.,44.=. 4`'..-7 t•-siz -4, # -� i� - + i jt .-.ter >>. r�> "= 1 "Fomey's construction experience was obvious from the ver b in- 'sti «;`= nin Their project team was assembled,and we were off.Forney's y .. as tR construction expertise was invaluable throughout the project.Their - - ;,,�: .' on-site superintendent• > .., , , r .,+`xr• p rintendent could not have been more qualified.He .r. - : ; brought site experience and sub-contractor management experi- A.-' .r - ,..4, X,. ence that kept the project moving forward:' _.- . Clark Cur1-41.7c fe ,�'+ Curry,Discovery Green • 1 _ yI .• ! -/ L•.. . 'y`r- j1 L 7. lai 1iar yI. , e r r � a tLljf 64,4 p C Z �" P d '' 1.r r CIO C g Cthlietro. 01` ! r f 1 �vIle :;', t 3, 'I'*;''' kJr� yq�f • > ! ▪r .4 ! V ,,' J + ,y+' �j��, �h.�. .k'{\ �.j�i!'P'tA• h } ' 'x'4�yY , lri CO i ,Cs qiF141 ,.} A q 1. +�y � it 1 tr de °4.+s"h' rz -_ vt y r, 4��a p37 y t ��r r -� < b . ,. .c • 4 i 1 f'' / �� �' .�..� .>.w.ytbse..4*xx N >''".' +^" -`E� _� ?, �w'r"y �5 � t` • t, Jr G • r h s fi R ,. 14, 4 /$E • - r'i't,. ;s�'' r- r '�£*.r y x _ j !I� Ak - rli �6 e > • at v ,- M ,'t as '1 y d Yh ♦sue. A, t i s "ak' �Y P •^., a r 4L f ; ,.' 'w. .d .1 1 • �h v g 4- sW 1i1711 • fittv • � 1 Y t .. age t 'y ., 11 ©1+ •4 S{"t / \4i, f. � \it '-r, , / , r' + °', Y ip ; � � �rj �uS� ,z � s ; y r k k ''4 #''� `,.,4`r ,i, Z1Fvt". I {{d Tft �,{ IIhh ri .�,°i n - •'S 4 rY n t "fr�l y .:�b: ;U+ 7ili� 'I ` � a S .. ... 3^,,� ssar d•� t•,..f. 1Pi a- �,s ; tx 7 A44akl) i1 _ ,r k I w'. ( c�Y �`� "Z. y�1 r ,�� } t* ' 1 QED ? a ; , - r rpm�� fwl� �� r:14,'' �� r �� 1,f \ '�: �At ,.q i, , ,. �x }i 1 .u.. 1r Z y�tr,f 1pttr, S - �ly V i\� •I ft 1, s / �`1• r t g„" O r;,✓- 's •� j VI ,: ,w : 4 �11� i `�,` - r�1' �' :,:::;::-,:;ri:;!:4:! 'li '', :''''''. 1,;14:! -... 41 t, }: {_� `yam t +, .K �'y ,',' L t , r. � a � #jt 1�I. 'L-" 1} ,.i/r -�..� +` [i\\\'\\ yittl,„ - ,.. •S � _ 1S . ..`,,, . : a _ i •r i'Qq rrl*. �`Yi.4' M f 7. i 4-,''''Ai°' ..Ar•‘," ' ' 41;•'•f'A—, '-''-'111110 '4:-.*, .„ :-,, ; ,..- ,- EiE • � !t ...,. �%► s\*,..., .:,us r i.!` , ,,4 ^Ir vs -7 n g r v x ... a ski „_ Ct r t l t ry' ��t i.--tt - k - - � •cr... :'. u -'4 F/}? , s:•'' N. `,i, T^., .,, _, . ; °j•CSS. ; d.?',�1. i \ tby ` r.� v Houston Arboretum Master Plan HOUSTON, TEXAS Construction Manager at Risk y M , r - .... ' '. c ' 1 , , ,,, .• , 70, ..,,, - ', .., , . , Li3 , .,„ ,_ _ ,,, E . ' ' '-.41 -r1,;,-- ..--.1, ::--(4 4 ---;• --- - 5 'oa, ,, _ _ 1 , , Nature Center n ` �. . : tMw17�i y -_p ' �. F-ip., ,• a» ta• - -,-: ter •'A ° _q ---- e �4 r Oa _ / _,' , .< . .rt: I i q i. • Scope Forney Project Team S15.5 million master plan to restore and protect the natural property and expand current education Alberto Garza,Scott Linn,Drake program at the Houston Arboretum. The project included a new visitor and event pavilion, Forney,Jason Burt administrative building,maintenance facility, extensive landscaping restoration,new trail networks, Owner children's discovery garden and nature center. This project operated under the sustainable SITES Houston Arboretum& Gold-Certification Standard and encompassed wetland,ponds,boardwalks,and a phased strategic Nature Center approach across the 75 acre development. Debbie Markey 713.681.8433 I f. © FOR Original Contract Amount OI'li $14,489,648.00 Completion Date te, July 24,2020 kt. Final Contract Amount Q 11 $15,498,315.00 Managing Principal • • Alberto Garza (9f fy Number of Change Orders FORK 24 Change Orders Architect/Engineer Design Workshop Jason Burt,our proposed Project Executive,currently serves on the Board of Directors for the Houston Nature and Science Center,further strengthening his understanding of the planning,stewardship,and educational goals that are essential to projects of this nature. Houston Zoo Elephant Barn and Yard Expansion HOUST0N, TEXAS General Contractor a'‘" % I•J ❑ - y >r _ _ • of ',� • s h•' r a 1 _ --Cy.;iii% ` ;� F� ct t „ .z z� ? a ti — • Y��y y C ` . 5... a tea - l < t L. • ilk ..:: ..,46.! t Ij Scope Forney Project Team $8 million construction of a 6,500 square foot bull elephant barn,expansion of existing yard and a Alberto Garza,Scott Linn 130,000 gallon lagoon pool for the Houston Zoo's elephants.Doubling the size of the previous habitat, the project included a new boardwalk with unobstructed views of the yards.This exhibit featured high- Owner Houston Zoo end and unique finishes for a consumer facing hospitality project with a focus on sustainability.With Gene Eldridge a conscious emphasis on durable and natural materials,this project was designed and constructed to 713.533.6623 last for many years with very low maintenance. Completion Date May 24,2017 40 FOR Original Contract Amount Managing Principal �J /�� $7,143,032.00 Alberto Garza GL CL 0 Final Contract Amount Architect/Engineer • 4 y $7,892.567.91 House+Partners • •Op. A. Number of Change Orders PORN 5 Change Orders Washington on the Brazos „ ASH i`; c, TO `1 7 EA ' SR General Contractor • A ,t ✓3C r -* 3 L.s I Ir IE31 i11 y -- r r DRUG STOR a • ...e.g.-- ill i ��8 Y Ct liii! ■ ��0 it T - - „--t =s- • — , - - _ e -- t; a L11 � , if r .". 1QIIIIIIII . ,,....._,_, . .,,,,,,,,„ .„,-;,. r: _,-,.. g ....i Ire' Li W .may .�, i �� � •i,l ./ Scope Forney Project Team S5 million historically accurate restoration and reconstruction at the Washington-on-the-Brazos State Luke Withers,Jaci Autry,Coy Historic Site.The work included restoration of 13 historic buildings,construction of the Hall and Lott Koehl,Michael Stevenson Tavern,and recreation of a historically representative ferry boat. Improvements incorporated period- appropriate masonry, timber framing, carpentry, finishes, fireplaces, and porches, while discreetly Owner integrating modern structural systems, including helical pile foundations, to protect archaeological Texas Historical Commission resources.All work was completed in coordination with preservation stakeholders and in accordance Dan Valenzuela with Texas Historical Commission and Secretary of the Interior standards while maintaining public 512.463.7947 access and ongoing site operations. Completion Date February 27,2026 Original Contract Amount 0.r E�'1 $4,597,450.00 Managing Principal ��. Luke Withers Final Contract Amount Q .., $4,582,442.00 Architect/Engineer • • Texas Historical Commission dby *� Number of Change Orders PORN 6 Change Order San Felipe de Austin SAN FELIPE, TEXAS Construction Manager at Risk ., iiiiw .. ., „ow ,f. . -f. / ,° �./ 12!A-:,1"5 `: - Ir .r111r `'s,,��Y f1S Y- , s J i.. -L} .w.. 1- v y -.7r 61.7 ys -{ 1ir'.-r'*#4:md >-ems.__:„ 4 -'`,a r «s .; 4c-.` ....`- --.. -aJ.y 4 ' . „_ I'l: ` ..-. _ .-n.±..*f`7 • ..':. . i tar 4s4, r4 1'1:,r 4 kf4 t '' iY 0r.•.1.,.: y i. a&et'•dt . '4 '"Yt•,.. i.z .r 4 $$ 7r f{ , y •v T Ia_','� '4 - �C..._. '„ _ .r yt `_ • 4 � t 1" t 2_ 24.... NJ L Li a 4. L h ,`gig=i mwe Tiff K �_-�� � Y } sue?' - ,.-• E --� vim_ -i�ro » a. -, .—_ ice-- ,, 1 I t � r - a .�- *-ia fit . r'_s- °��• ,. Scope Forney Project Team The $1,949,738 townsite at San Felipe de Austin State Historic Site is an outdoor exhibit of eight Luke Withers,Scott Linn,Jason custom log cabins and three structures representing the 1830s village of San Felipe de Austin. All Burt cabins were constructed using the same hand techniques as the original cabins.Utilities were brought to the site as to allow modern conveniences for visitors.The construction of this one block historical Owner's Rep Moore Consulting&Contracting replica required a state of Texas Archaeologist to be onsite daily as the building sites and pathways Michael R. Moore were developed. 281.342.0375 Completion Date December 18,2020 �D FOR Original Contract Amount OJ /� $1,863,522.00 Managing Principal a Luke Withers Final Contract Amount 4 y $1,949,738.00 Architect/Engineer • • Texas Historical Commission— e y Number of Change Orders Historic Site Division Of,. 1 change order The Commons at Hermann Park HOUSTON, TEXAS Construction Manager at Risk t :r ' tig., t ` r at¢may r r. Af r" , " V.F. " / ���.•, a^' - n ,: ; ; -if �om `d`y t* g k 9tA+ors , J �I6� R I l 4 JR y�/�• •-�T ti °'r i ter _ � ...a,l,.r- � SJ '4 f-S _ { < ; 71yy,�,, . 41 ti B ;s .-r t:,1tl tkPY •/"�v�P . t �t4 t \�4 - 4. f64 ,- .r for tt ', 7y t 5 R Y V +1 ps---Nc l i = - 7. ' _ ' •3 + fir; "�i ` r� " @ 4'_':y,e-s'`'-�`- t _ 1�� ➢� if'r�.� ,, "«� GIs ,� > ,Xt�l , irivt07. Scope Forney Project Team $28 million transformation of The Commons,a 25-acre area in Hermann Park,revitalized an underutilized Tom Forney,Alberto Garza,Jason space into a welcoming destination. Improvements included new play areas with water features, Burt,Jaci Autry,Nicholas Salley, expanded picnic spaces,pavilions,an art lawn,enhanced park entrances,landscaped open areas,and Austin Geveshausen,Scott Linn, Natalie Pettis,Adrian Fernandez relocation of the George Hermann statue.The project also included an 847-square-foot food kiosk within the renovated historic pavilion,featuring a commercial kitchen,custom millwork,new utilities,service Owner and prep areas,and a customer-facing counter,all coordinated with historic preservation requirements. Hermann Park Conservancy Doreen Stoller 713.524.5876 *,Q FOA Original Contract Amount Completion Date OJ /4 $27,613.184.00 October 24,2024 c ' Final Contract Amount Managing Principal 4 y $28,535,836.23 Tom Forney • •may �A Number of Change Orders Architect/Engineer FORK 19 Change Orders Michael Van Valkenburgh Associates Bridgestone MUD Park General Contractor � - <. % - ,.. r r , ` i' ,' : y w _a*4. f ffi" r , ' - - ' --- . - ; _ , f ..-: - „„..,_ ..;s,. _ �.t �,�" S ly. • -,7�. fi_ ' t 4 _i 3.:..¢ ..r1 ;: j `* �� i '� -� 1 � ` �`-'� i�E:+� r fir__ c�-� f r 4-r• 4 s';;/ AI Ii5,4 -7- ' ••-•-r. ....:,' ..N '/.1:: i;; ;+ kid _':�as � J { ;: � -,"`_ _,ram • ! ? ,, s Scope Forney Project Team A 14-acre park development for Bridgestone MUD featuring a 5-acre retention pond,driveways,and Alberto Garza,Reed Roberts,Mat parking lots accommodating over 150 vehicles.The project included two multipurpose architectural Morris,Clay Seime,Monica Waller buildings with restrooms, storage, and covered seating, along with a 150-foot pedestrian bridge spanning a portion of the pond. Additional amenities consisted of miles of illuminated sidewalks, Owner custom playground equipment,a three-zone splash pad,two dog parks,various fitness stations,site Bridgestone Municipality Utility furnishings,and recreational gaming elements such as cornhole boards,foosball tables,and chess/ District checkers tables.Landscaping efforts involved irrigation,planting,and the relocation or transplanting Ron Schkade 713.929.6756 of 50 native trees. Completion Date Original Contract Amount January 24,2025 0 4 �ORz,1i $17,455,462.30 O. C� Reed Managing rincipal Final Contract Amount Robertsrt 4 y $17,589,554.58 Architect/Engineer 4gt. et Number of Change Orders Four and One Landscape FQRN 18 Change Orders Architecture Trees For Houston HOUS T ON, TEXAS Construction Manager at Risk r t ¢ a t r k✓ r. i :44. J': , �� , -- 3 -I -1 jti .2 - t, .t r51 • • Nib, �r r P 4r3 .fi • �, �_P / � w �",:"+-r,�'z' 'tea.-^ - - .. -ram` 'f`' $. t ' ,- `` i.- lir ,. fll �llluxQ . _ a I s"�a -rr.i f (I ff'llfflt , . 7rr tt HH''[[� �� ii; # _yam 1f�t!1It1tt1 ° t' / ---.•.d y 'Ok..}% ›"`A trr '4' r -t :/''t.i .�r:ff ,..Ni �i' tv1c ,•i=`r� t y;' - y .r- {:... 4 ,7"ear -. AF. --AC` :1'. Scope Forney Project Team $5 million ground-up construction of the new Trees For Houston headquarters facility including an Alberto Garza,Mat Morris,Turner outdoor education center and large tree nursery on a one-and-a-half-acre site.The 7,000 square foot Routh office building includes large lobby and reception areas,Trees For Houston Executive offices and workstations, small conference room, multipurpose room, lounge with kitchen, event storage, IT Owner closet,indoor and outdoor restrooms and parking lot.The 1,400 square foot outdoor education space Trees For Houston Randi Koenig accommodates outdoor classrooms.In addition to these two spaces,the project included a 14,000 713.840.8733 square foot tree nursery capable of holding thousands of trees to assist in Trees for Houston's goal of distributing and planting 10,000 trees within the next five years. Completion Date June 1,2023 �,O FO4b-. Original Contract Amount do / $4,418,185.00 Managing Principal 0 n Alberto Garza Final Contract Amount O.4 -,,,g $5,003,040.00 Architect/Engineer • • Kirksey Architecture O� Number of Change Orders lPORr1 8 Change Orders Discovery Green Northwest Corner Improvements _ <;Aj Y •• R Construction Manager at Risk t r M 1. ; etu, .e Y 1,` . r��.•,- yam... /� • Q Y 1 2` ,,. .:-.2 ,:7_,. I -.:-11";.,, -;%, ti,#:' -zia'r..Z-SZA- ' `f • .i .s -. ..w y � _ i'7�y r.LL' - 7 a{ .- a • a1;. a .. _ __ _____ ___ ,, ._ . _ . , _,.. _ ,.. ..... , . ::..,,J, , ___. ._ . ,_ . _ ,____._ „.. ,, .,, 4,.. . _ ... . ,: _ ,.. ,,„:„,„,._„ _,.„44,,i,.......,...,.„ , , .... , _ _ . . . x _. , . , ".,.„,......,..,. ;_,,..... .„.„.„....,,,,,,.„.___„.„,,,,,.. ,...e., i. ,... ..r. . . .,i,.. , . i� .. ..,,.rl.. . ... .. gg.' -.�� �mbistrattr- ., �'.i�{fir Nq (� �: � z: '} � ._.. EM ,eitj , Sc .. a ' 1L,' _---`dam, -/ r_ -t �,, ,{+'�� r - ' •_'- Ira `( - I 4H - 1 .= .e �----- -0w .. Scope Forney Project Team $3.3 million in extensive renovations to Discovery Green in Downtown Houston include a striking 50- Garza,Steve Mounts foot signage feature that leads visitors directly into the main promenade entrance,complemented by a custom-designed playground area,elegant granite pavers,and precast bench seating intricately Owner carved into the shape of a snake and surrounded by artistic lights that resemble the form of trees. Discovery Green Conservancy Clark Curry Thoughtful landscaping enhancements feature newly planted large trees,ornamental grasses,and 713.400.7336 carefully designed hardscape elements that work together to create a welcoming,lush green space in the heart of the bustling city. Completion Date August 10,2020 v©FO9 Original Contract Amount Managing Principal QO'1 / $3,403,254.00 Alberto Garza � Final Contract Amount Architect/Engineer ...# $3,317,475.00 Hargreaves Associates 41). *y Number of Change Orders PORtS 46 Change Orders Hermann Park Lott Hall H O U S T O N, TEXAS Construction Manager at Risk :t! ,tom t ! { tK` �F \����` € �_ Lam` u _s._s_._ ____Nattjmit„.., 4.,,t, ., , „._ 1 ;. . '.. r R , _ems 11 ®�F9 r .cam. i1! lF:'1:1.-1--4.i:-"L'-'41:"11---.:14. �� a _::l::-7-'::- ---.---:7- ------11— o :- - gyp— irk;14:0 t' . -- ,. — • l� ` III i f — ., I , i — i - II iiirriki ' utt A 41 I • A ,,,, II _,..,,___,...., . . . . . 1 1 .„ ,,,,,_„,--- ii --:' -- . _ owl ox..„„ 43,404v _.,\_ iiytiviiiL___±---._: __-_____ :,.,, ,,,„:„..,- i —4 „ 1,cr. ., e. e,,�' fi 't.�1 - , -- - = — i em . ,� v _ Scope Forney Project Team Forney Construction served as the Construction Manager at Risk for the comprehensive renovation of Alberto Garza,Drake Forney,Steve this historic clubhouse,which was originally constructed back in 1922.This extensive 10,200-square- Mounts foot project involved the addition of a beautifully designed upscale garden,a completely redesigned and modernized lobby area, updated event rooms to enhance functionality and aesthetics, and a Owner brand-new main entrance that prominently features an elegant Porte Cochere.The project scope also Hermann Park Conservancy Fani Qano included a full site civil package spanning approximately 72,424 square feet,aimed at expanding the 713.306.3674 parking capacity significantly and upgrading the site's drainage infrastructure to improve overall site performance and sustainability. Completion Date September 17,2025 �0 FOR Original Contract Amount �� f� $3,771,010.00 Managing Principal � n Alberto Garza Final Contract Amount 4 --I $3,802,274.00 Architect/Engineer • • Curtis&Windham Number of Change Orders yPORN� 8 Change Order Shadow Creek Ranch Park Phase II HOUS T ON, TEXAS Construction Manager at Risk � - L - r 'iiL Layic�r + . :as F "�+ • _ _pp�� � i� _ 4 _ x _ -s-- !F - •'' + I - - ' • '. ;: �"-v.. - •"_____—. y_ cv- -d-y4- t 1 -- - ",4 H-(I -_LLL L� -" _tip - .� _ = j .r 1 - 41111111 }_ r a J r 4 - - r i" j / r"tsr z t A _ V.l- . �� '1^ tr`nt I-i sf.r a a •-.-"_ _ 4,1..t a3 '_�� -•,di.W • � 1= .____ . _._ "' 1� ��....... ,_,,. ,____,_ _:„..... ___...„.,,,, . + pp , � ,lito, , _04 . .. ,. ,, .. „...; _:„...:.... - ; 'fir d[- '�, CF - E ` 2?.i 2+z. _ ♦5[I" {_ Scope Forney Project Team $5 million expansion of the existing sports complex including the addition of an artificial turf Alberto Garza,Jason Burt,Zinai multi-purpose field, which features a dedicated cricket field as well as a miracle field designed Castleberry for accessibility, along with enhanced sidewalks for improved pedestrian access. In addition to Owner the installation of fencing around the entire complex, there are two newly constructed parking City of Pearland lots,upgraded sidewalks,and fresh landscaping to beautify the area.Furthermore,the project will Morgan Early include a new maintenance facility building and a new concessions building that will house public 281.652.1734 restrooms,training rooms,and locker rooms for athletes and visitors. Completion Date February 15,2022 F Original Contract Amount �� ♦ $4,552,384.78 Managing Principal �� Alberto Garza Final Contract Amount Q ® rt $5,012,677.77 Architect/Engineer • • Kimley Horn&Associates,Inc. 041' Number of Change Orders PORtt10 Change Orders Bridgeland Lakeland Activity Center & Prairieland North Lake Edge 0 (PRESS, TEXAS g General Contractor r a` 11. r`n, 1, 1 it s d P fi: ^ 1 _ • 1 ... ...: .... ------r.„. ... \ l moot'_..,r-z:--,!...: i , .._ ii\,..,..„. yr_ . .,4,..„0,. _„„,,, 4a,.„ ,. 7 k f C�.t Scope Forney Project Team The phased construction of the fitness and activity center in the Bridgeland development included the Alberto Garza,Reed Roberts,Mat ground-up construction of a 4,260 square foot fitness center featuring a large exercise room with sports Morris,Jesse Moreno,Will Fuentes flooring,an open ceiling concept,and numerous exterior windows overlooking the lake.The building has a brick exterior, standing seam roof, and access hardware for seamless resident entry. This project also Owner included a 6,675 square foot remodel of the existing amenity center as well as a new covered patio and The Howard Hughes Corporation/ refreshed parking lot.Additionally,there was a$3.1 million site development on the north side of Bridgeland Bridgeland Development,LLC Lake spanning 16 acres,incorporating 38,000 square feet of paving for walking trails,fishing pier entrances, Tricia Brasseaux(No longer with and special paving with exposed aggregate and inlaid stainless steel butterflies at the pavilion structure. Howard Hughes) 281.330.0929 J*.o FOR Original Contract Amount Completion Date a�0 �If' $5,528,977.00 January 30,2023 4 Final Contract Amount y $6,007,605.54 Managing Principal • . Alberto Garza th. to Number of Change Orders SRN 50 Change Orders Architect/Engineer SWA Group Miller Outdoor Theatre Entry Gateway „__ __ HOUSTON TEXAS Construction Manager at Risk 4 ; • Z %'e p!Vol rt , -r - ii�.40,1 w'',ems--',.,pt.-w ' .: KI. e� ") -.r. t^_. ' \ s •,y. -r' �• k ..may, •,` V ` % a i . _,' i 1 .p/. • -'}: r.yl.c . � jt Y• . f.1 3 t .;3 t;•,.v ` •mil 0 •.f s._ •'.:. L; •.,t dk '{3. _ t = , ., _ .f- to } • Fice ' �l ._, i = :-45 a- -• - -" - -.-•11 "..-s---ti44:41 4\lt ttt }} �� tip ..ja,. _✓. i♦ !It �4¢� - .. - S f 4.c Y'yawr• •' «,.tom * _ z , N L -.r . y Scope Forney Project Team Site improvements designed to enhance accessibility,comfort,and the overall visitor experience at Miller Alberto Garza,Reed Roberts, Outdoor Theatre.The work included upgraded pedestrian pathways featuring an intricate combination of Jason Burt,Jaci Autry,Coy Kohel, decomposed granite,four distinct paver types,and concrete to create a cohesive and visually engaging Clay Selma hardscape throughout the site. Three custom steel "bird" canopy structures served as signature architectural features while providing shaded gathering areas,complemented by refreshed landscaping, Owner Miller Outdoor Theatre Advisory upgraded irrigation controls,new site furnishings,and enhanced lighting.Improvements to the dining cafe Board included new benches,decomposed granite surfacing,and landscape enhancements,creating an inviting Claudia de Vasco outdoor environment that seamlessly blended functionality with the theatre's iconic park setting. 323.810.7847 i0 FOlik /A Original Contract Amount Completion Date ��J � $3,101,767.00 June 8,2026 Cl. n Final Contract Amount Managing Principal id. T -I $3,215,050.30 Alberto Garza • • 461.y 44 Number of Change Orders Architect/Engineer PORN 28 Change Orders DLR Group,Inc. Memorial Park Driving Range and Maintenance Facility - Construction Manager at Risk r � 41► iw ' - --.. yy 3-. yG - f --� z� ,L�r� '\� �.C" .. ipriumft, xi1 f !' .t% AZ' e � n 1 1 . ' .s. s ` - i •' 7iTj r • ,em s 0. �•• ,. �{{ _ a -r y� -r.) -' 7 p _ Scope Forney Project Team Ground up construction of a two story driving range for the Houston Astros Golf Foundation. Alberto Garza,Luke Withers,Zinai Construction consisted of a 2-story steel hitting structure-455ft long x 25ft wide. The structure Castleberry,Brett Fisher increased golfer hitting stations from 57 to 84 potential stations. The project also included construction of three pre-engineered metal buildings including a new 13,500 square foot equipment Owner and storage facility,5,000 square foot office and crew building to support staff,11,000 square foot Memorial Park Golf Course cart barn pavilion to house golf carts. All site utilities(power,water,sanitary)were brought to site Julie Blum and distribution installed to new maintenance area.The Forney team assisted in the design process, 713.515.0696 development of budget,completing the permit process,build and completing project by November 1st to ensure that the course aligned with the PGA rules to host the Houston Open. Completion Date November 1,2019 0 FO/Q Original Contract Amount OJ ! $5,477,428.00 Managing Principal CI. Alberto Garza j) 37 Final Contract Amount Q -4 S5,767,900.00 Architect/Engineer • • EYP BJ, �A Number of Change Orders FORK 2 Change Orders Jubilee Amenity Center Housroly, TEXAS ;�/� General Contractor .\\ �\ / I- ; �. ,„,im . f , H-linn - ili it i1 • v ,,....., _,,,,..,, i . MIIWJ j . J i ;iii!, _L--,.,k .-, .-- •:. -i,,.•- -'-'-''' .1..-.:- r: :::!, ..„ .... -,...z,! _.,.. : .. ..1„, .,..., ,_ _I,i .11 —47,14: .,— 'l';''' t y • It A e U Willa Ill' . i.1-41 ,zear*Ii;4- Scope Set within the Jubilee subdivision,this recreational destination brings a refined,resort-inspired experience Forney Project Team pReed Ro ,Dan to the community. Thoughtfully designed gathering spaces,warm architectural details,and a striking Fisher,Arriiauna DavMullins,Brett is pool environment come together to create an inviting place for residents to relax,connect,and enjoy.Two complementary buildings,a custom concession stand,and a signature canopy with skylights establish a p Owner's Re cohesive architectural character,enhanced by a blend of stone,stucco,Thermory wood,and custom- Johnson Development colored metal accents.At the heart of the space,the resort style pool creates a vibrant focal point that Nick Deacon elevates the overall amenity experience. 281.949.6401 Completion Date o40) FQ4)' Original Contract Amount September 17,2025 $5,361,917.00 aQ�'y �•Q Managing Princi hitecpal P` Final Contract Amount Reed Roberts -1 $5,344,749.00 • • Architect/REDEngineA rc ;tars r �J Number of Change Orders Studio FURN 1 Change Order Sienna Sawmill Lake Event Pavilion & Beach Lake Front MISSOUPI CITY, TEXAS _ ...� .._....s. w-._____„. _.... _ ..._...-T.... __. Construction Manager at Risk > - r .--- - - 4 a .' y.__ • ' - __ 4 - R .- ram, •, _ _ 1 s I.. '�---"------..is-,.-,-_r - ice t + !�i 1 s fl+�rr � i 'r 1 iIH1' ( „ ..a" - ? d »c �'� am - - ..•t4: • •." L . , � x '�J.1 - -- __-- s..e;'-'- .�_ _ _ ,j- 1;11�1a.� 1_:_1. -_A _.�M� � ._' '1K�= ..s _ ._ _`.. ..lY_ 2..M+4r"fl ,-_- z --igatP7 . , 4. 4. ; : . i'!, .iltipsial x. -- . ak, - •- . -- ,t• 1.,A4'4..;. '' 1. "4-', 41,, .,„;,.; •, a, Scope Forney Project Team $5.9 million expansion project for the Sawmill Lake Club,encompassing a new 3,841 square foot event Ryan Nunn,Zinai Castleberry,Judy pavilion building and a new beach lake front.The new event pavilion includes a large event space,office Miranda,Ken Benoit,Scott Linn, Robert Villarreal,Will Fuentes and storage areas,kitchen,restroom facilities,and a large outdoor patio.Adjacent to the event pavilion, a new parking lot and food truck space was added as well. A new beach lake front was also created Owner along the side of the lake.This addition includes beach sand areas,pavilion,cabana,wood decking,and Toll Brothers new beach volleyball court with shaded viewing space.The scope of work included all landscaping and Kim Tiger sidewalks surrounding both the event pavilion and beach lake front. 610.312.6062 Completion Date � F©R Original Contract Amount May 24,2024 CT'J � $5,936,934.96 Managing Principal 4DI—flip) Final Contract Amount Ryan Nunn 4 —J $6,286,783.74 • • Architect/Engineer <Pk f,,k Number of Change Orders GSB,Inc. PORO 6 change orders Toll Brothers - Sienna Oaks Clubhouse and Pool i';iIS3OURI CITY, TEXAS House General Contractor Ia i 1 -� -la Wit] I i4 - -a---------5* 4-431_: ' r 3"....---.-"'l 7 .„____,_ _r , . §r _.. 1_ , ,„,„,...L.. it 1 - _ , ________. ,i_______ _ g to__ ...--------------4/ _ _ ,f t ,. i „t„, _,....,,,,.,t„..,.,,,,:.,..,.*i.,. _ __ : „ ,__,,,:.,... _...__ ....... _ , _itevogg ,., „.. .„. .„ i.\,... ,. _____ _ ,_,,,,,,_ . _ :.„, ---- i _ — ,,,.‘_._ .s.,:..r.):,-.,_,_ 14---i- 1-11--i-, , , ; . __ __ ___..i. 1 1 iriimoestics____ „.„4„,...... _ .:. i...., , r xt, �/_ ✓ z \!I _ s'.. "/111111/11/ ope New construction of a new community amenity complexSC featuring a 6,802 square foot clubhouse,1,363 Ryan ` Forney Nunn,ProjectbTeam square foot pool house,competition swimming3 Robert Villarreal,Judy pool,and two basketball courts.The clubhouse includes Miranda,Ken Benoit,Scott Linn a tween room, multi-purpose room,café,full kitchen,office,reception area,and men's and women's restrooms, all designed for community gatherings and recreational use. The pool house includes Owner lifeguard storage,a pool equipment room,men's and women's restrooms,and chemical and pool storage Toll Brothers to support daily pool operations. Exterior improvements feature a large competition swimming pool, Kim Tiger colored concrete pool deck with Sundek coating,custom sun shades,and comprehensive landscaping and hardscape work surrounding all buildings to create a cohesive and welcoming outdoor environment. 610.312.6062 Completion Date 4 FO4 Original Contract Amount February 26,2026Q 4; $8,461,876.00 :' Managing Principal aFinal Contract Amount Ryan Nunn $8,860,466.59 Architect/Engineer O�'FottN Number of Change Orders GSB,Inc. 5 Change Orders s ash ' � � • _ ca fi , ; , 1, L. - " � �`• � fit: ,p h '�a � P• �t •• °A "'�.t\ y k q ��� Or . t''''''''' ''''''' 01 f ,, h b;`1 4 4 +,.— ypt 6', X� lt... f " +aa`�'4: ti. r 3-!Aft; ,[t F x" { mew ',•Fr} . /G�) is*v*i r- ..,,:. � I �, t C 1 ed 13"�.> . ' a< a *. '' ',s- ki 0 CI }} RjY y .,,,,,,,,,, r y,(i; t ! r t 2 4 ,'� d' �►I €, .ail I l #+ Ito; !`.'. r ? �e a'' 24 it CO�..t.,:., . ,:..„, \-,,„„ , ,.„.. :, 247.11,i‘, ,„ ,, ,..,..v„.„,_,.. .,,,,„*;;,:4, '' 'rt t y f. vs°r F 1 { , li ,4Y lin' ,f12 �l9 • - 4_'4 t Y r r # yj # i. ` may} *� �� * , : 3,. tNe k} t'., P t a 2#'r-r 4 �i y �3. c+.e., y �... a-4...;*,+a1+r/ �x. .�.;. },,g�$ ,� fit. '� .��Ye �� e a3 r er s ,P t 'x f� }I � us :fir Common Challenges in Visitor/Nature Cente r Construction One of the most important considerations when constructing a visitor or nature center is understanding the mission.To support the City of Port Arthur,as well as their future staff and goals,we feel like it's critically important to have a work session to fully understand their needs.Those priorities shape our plan and focus when looking at all aspects of the project,like schedule,cost, and quality control. By understanding the most important pieces of the project, eare n a position member of the project team, ensuring that the facility supports the City of Port Arthur's mission. This collaboration frompful start provides a better,more holistic experience for the City of Port Arthur and their Nature&Visitor Center team.Our approach stems from The Law of the Letter "P"- Proper-Prior-Planning-Prevents-Poor-Performance. This forward-thinking approach enables more effective results with each of the of the Key Challenges spelled out below,thus ensuring the project is delivered safely,responsibly,and in alignment with the owner's vision. Addressing Key Challenges Maintaining Clear and Consistent Communication Successful construction requires close coordination among the owner, design team, consultants, regulatory agencies, subcontractors,and other project stakeholders.Our team will establish clear lines of communication,conduct regular progress meetings, and provide timely updates regarding schedule, site conditions, upcoming activities, and potential challenges. Questions and concerns will be addressed proactively,allowing decisions to be made efficiently and helping the project remain aligned with the owner's goals. Protecting Environmental and Natural Resources Whether it's a brand-new construction or a renovation of an existing nature center, the land is sacred & we treat it as such. Construction near sensitive landscapes, wildlife habitats, waterways, or protected vegetation requires careful planning and responsible execution. Our team will work closely with the owner,design consultants,and environmental specialists to identify sensitive areas and implement appropriate protection measures, including clearly defined limits of construction, erosion and sediment controls,tree and vegetation protection,and responsible material handling.Environmental controls and site conditions will be monitored throughout construction to help preserve the surrounding natural resources and minimize unnecessary disturbance. Our team completed the first SITES certified project in the City of Houston while working with the Houston Arboretum on their master plan. From the careful planning during preconstruction to meet that criteria to assisting with gathering seeds and pine cones to preserve some of the unique species in the area,we understand what it takes to be a responsible partner in minimizing our impact on the environment. Managing Site Logistics and Access Visitor and nature centers are often constructed on sites with limited access, unique terrain,or proximity to protected natural features. Our team will develop a detailed site logistics plan addressing construction access, material deliveries, equipment movement,temporary utilities,staging areas,and emergency access.Careful coordination of these activities will help maintain an organized and efficient site while reducing impacts to surrounding land, neighboring properties, and environmentally sensitive areas. Coordinating Specialized Building Elements Visitor and nature centers may include specialized exhibits, interpretive displays, educational spaces, observation areas, and building systems designed to support the facility's environmental mission. Our team will coordinate closely with the design team, exhibit consultants, specialty subcontractors, and vendors to ensure that infrastructure, dimensions, finishes, utilities, and installation requirements are fully integrated into the construction process. Early coordination and detailed quality control reviews will help prevent conflicts and support a cohesive final product. Supporting the Center's Educational and Community Mission A visitor or nature center is more than a building; it is a resource that connects people to the surrounding environment, history, and community. Our team will approach the project with an � understanding of its broader purpose,ensuring that construction decisions support the intended visitor experience,long-term functionality,and educational mission of the facility. By maintaining open communication,protecting environmental resources,and carefully coordinating site logistics "l and specialized project elements, we will deliver a safe and efficient construction process that supports the center's mission and preserves the qualities that make the site meaningful. • Team Relationships with the Owner and Architect At Forney Construction, we believe that a successful project is built on a foundation of collaboration, transparency, and proactive communication. Our approach to working in a team relationship with the Owner and Architect throughout both the design and construction phases is rooted in collaboration. Our Collaborative Approach Early and Continuous Engagement • We integrate our expertise early in the design phase, working alongside the Owner and Architect to provide cost, constructability, and schedule insights. This ensures that design decisions are aligned with budgetary and operational goals,reducing costly redesigns and improving efficiency. Open Communication and Transparency • We facilitate regular meetings with all stakeholders, ensuring that expectations, challenges, and solutions are addressed in real time. By leveraging collaborative tools such as Procore, we enhance coordination and keep all team members informed. e A Y csams.(,..: Ash . •.Q - C.�e...__ - . -.. • • .. ...r.w.•a.. '� — - 1 1 — Sli amb"tryout �, - _ _'4. . - iffIl : ! :1 - s. Procore is a project management tool provides our Owners,Architects,Subcontractors and the Forney Team with the most up to date information at all times,all in one place.Organizing Submittals,RFIs,Pay Applications,Drawings and other documents in Procore allows for a smooth and efficient process throughout all phases of the project. Procore allows everyone to create tasks,set due dates, and notifies the team when these dates are not met, resulting in on-going timely efficiencies. Its user- friendly interface makes Procore an excellent tool for any job that requires effective project management and collaboration. "The Forney Project Team played a pivotal role in helping our organization transform into our master plan's guiding They were professional, knowledgeable and deeply committed to our construction success. They were a pleasure/to work with and their efforts allowed us to accomplish our goal of staying in budget, on time and fully operational throughout the entire construction process." -Deborah Markey-Houston Arboretum&Nature Center Value Engineering and Cost Management • Our team actively participates in value engineering discussions to identify opportunities for cost savings without compromising design intent or quality. We provide cost analysis, alternative material recommendations, and schedule evaluations to optimize project outcomes. Problem-Solving and Conflict Resolution • Construction projects inevitably face challenges, but our team takes a proactive approach foster a solutions-oriented mindset,working with the Owner and Architect to address design,logistical, r boludgetaWe ry issues collaboratively and efficiently. Quality Control and Schedule Adherence • Throughout construction,we implement rigorous quality assurance measures to maintain design integrity and meet project milestones. Our team prioritizes coordination with design professionals to quickly resolve field conditions and ensure smooth project progression. Commitment to Shared Success • We recognize that the success of a project is a reflection of the entire team. By fostering a culture of respect, accountability, and teamwork, we ensure that the Owner's vision is realized while maintaining a positive and productive working relationship with the Architect. This approach has allowed us to successfully deliver complex projects on time and within budget,while strengthening our partnerships with Owners and Architects. m The Commons at Hermann Park > ,o w 1 3 ♦ f f r • -•1 ,Y s rC4, r '� - �. .: •y+ „ +, .rF• w.. 'V;�g-ti�i .. '"k ', .. *". '� r _ `. `*-r L ,`!,f +vr .,Xw �' •j�,A• : ,fib' s �C+� _ F+ ,, T - 'i; a+``�..6. 'k*�a+... �Y t It ! ...y �y�. 4 • -• "S:-' ugs �0�-.'; v--.r ' '",..3, 1.� Y` r+- ii* '�`':'� ► t sic.',2- • - '.l « .siy+-. , ^( -Y'; 1.. tr _ •.t .'►• 1 ` "r w ~ a r. .L 3 y 1}� - {-` y ' 9 0 1- ' i�i mil'-�4._ iy -'4 i_` i 4y� . r • "`- ., ' !,. :s' - < a 't Z�^t 4" R During the construction of The Commons at Hermann Park, the George H. Hermann statue was temporarily relocated to ensure its preservation. This bronze statue was created in honor of Hermann's significant contribution to the City of Houston. Warranty During the one-year warranty period,Forney Construction would be committed to providing attentive,proactive support to ensure your satisfaction and the optimal performance of your new facility. Our management team conducts a detailed weekly review of all warranty items on all projects, allowing us to promptly address issues and ensure resolution. This structured approach ensures that no item is overlooked and that any concerns are handled efficiently. As part of our commitment to long-term quality,we would also conduct an 11-month walk-through before the warranty period concludes. During this walk-through, we will thoroughly review the building with you to identify any items needing attention, allowing for timely resolution within the warranty period. Our team is dedicated to managing all warranty items proactively and to providing you with responsive, high-quality service throughout the warranty period and beyond. It is commonplace for Clients to reach out with items requiring attention past the warranty period. In this situation it is our intention to minimize costs for correction or eliminate them altogether. Below you will find some past client references. We encourage you to reach out to them and discuss their experience with our warranty process. . ..,: Trees For Houston � . r'- Barry Ward Trees For Houston ,. .t., Executive Director •,,,.1- I 1 - .,- y. - -', '.• . 832.715.6062 barry@treesforhouston.org + 4" — The Commons at Hermann Park '~-J< a e : Fani Qano-Hermann Park Conservancy x. 4. . T • ? e , .: -. Project Manager '` ` re i ,c. 713.524.5876 fgano@hermannpark.org '''-, . { 5 1. - _ �•� L: � .k`.�'! to� 1�,,, y... _ h.: 72i . Houston Arboretum and Nature Center j► Debbie Markey-Houston Arboretum and Nature Center r x1 Executive Director ' 4 El _ := 713.681.8433 dmarkey@houstonarboretum.org 111. _� ,i i _4 '� ,' V � T 0 Self-Performing Work We can confirm that no work will be directly performed by Forney Construction.All tasks and activities will be subcontracted to qualified subcontractors through out bidding process. Experience is one of the most helpful teachers in our industry.We have the luxury and EXPERIENCE benefit of having completed a wide array of similar projects.This experience allows us MATTERS. to anticipate challenges,making informed decisions,ensuring compliance with safety and building codes,and delivering high-quality work on time and within budget. s • j 'I ' ',Icloa ri• et' jT ' iiA -. -- ''.. .iit--4: ''.. . _ {, Discovery Green --�'" --._ Innovation and excellence don't happen by accident. Our firm is driven 45`k- PaRe ** QUALITY WORK by values that make anything other than getting it right, wrong. We believe we have been recognized for our work throughout the years EVERY TIME. because of these beliefs and values! { ; ; -‘,41. . `x,, ..,:.... c;'=:[` •=atil.•.1 ' - �1=,.Inc l - ` -, , 4`-.I,.. _ . _ fir. „_. _ _ t 0 'Y+x. 1 i The Commons at Hermann Park ` ; -Nk, �.Za Camp Strake ,-t+F. AMCH Golden Trowel Award ►' i� Landmark Award -Special Projects , 1 x w !P -a r < .. t -:-", '''--,.. .-Alc.:,.*: q..-=.40 los,v, n. '.'V .•g• '7:017*.iyi'-:S-,;-. ...i',A=0:`:÷•'';:-,-2:---,--57..-,7*...••. *.--:..... ...e.W. *--- - Chrysalis Lake-Bridgeland ' Houston Arboretum and Nature Center l .;;t ,'x; f-r,,''{3 i - Urban Land Institute-Trailblazer Award Green Leaf Award X,• -"I • r 'd ��� �k' .'fib A • �, � 1 wn e w ♦ .. - xi ' � � A\� ; � " • ,4„1: t,L.r.."4!,^1,,,,t;,':,,,x4t!:ttt::::,,,I',:t:r$,, , '\\\\\A\ `� "�,{✓ '� ` �`.' .J:f A,� ^b �A 11 tea � . ,,*W" ,I'" 1 ' 9'1` r 4 �' k ate''+'`e.� • ,•,: 5*°w ', 3 >�.' r . 'i: ' r s +� �� \ a _ n ! r :ril:::':‘: „,..,...,,_. ,,,,, \ ,\\ x x, "§ a • w.rw W w id ya i s a :: p.''S:L.. Y j I. f ! t� I ` y t (Ao iA I;Ir Ih gC t s• w � ,t r ,,, rN�ffrl M f"4. L 'Y j y r��j �l 'i, f( f"4 7 •T I IF , \ \ .1, • ).',i , , ,, . , , ' ti ••,••, �.g It 4,- p i t ' �� 3 a l i, }e% • tip ,k4,\\ t, , ti*,t,:„.,,,,..,-,,,,,,,,, t - " J7,--„__,..' ''''''',' . I I I I I I I I I I I I I I I II I I I 11.I I 1 i= r > I,-4],k**: 'i'1: :1;1;11 \ \ �, 1 r � 111111111111111111111111. I ?w _ xF ti i ��jl 4 .'.:<> .: 1 ICI ,I��CiiNSZ .ar>a iii }} Claims and Litigation 1. Identify any claims or suits,if any,brought against your firm within the last five(5)years. Year Claim Resolution Creditor 2025 Forney Construction, LLC is contracted with the Foundation for Jesse Valma(Individual Proceedings Jones Hall to provide Construction Manager as Adviser services Resolved on the renovation of Jones Hall.Jesse Valma was injured on the job on or about June 14,2022 while working for Houston Produc- tion Services, a vendor contracted by the Foundation for Jones Hall, as a stagehand assisting with preparations in anticipation of the Jones Hall project. Mr. Valma has retained the services of a law firm, Tilton & Tilton LLP to represent him in his claim against Forney Construction, LLC. The claim was resolved and does not impact Forney Construction in any manner. 2.Describe all instances in which your firm was unable to complete the work under a contract. Forney Construction has successfully completed all work performed under contract and has never been unable to fulfill its contractual obligations. 3.Identify any judgments,claims,arbitration,proceedings or suits pending or outstanding against your firm or its officers. Forney Construction has no judgments,claims,arbitration,proceedings or suits pending our outstanding against our firm or its officers. 4. Identify any lawsuits filed or arbitration requested by your firm with respect to construction contracts of your firm. Forney Construction has not filed any lawsuits or requested arbitration related to its construction contracts. WE DO CONSTRUCTION Proven Experience I Quality work every time A partnership The stronger the people,the I Innovation and excellence don't you'll enjoy better the job.Your Forney l happen by accident. Our firm Team has decades cumulative is driven by values that make We're good stewards of your experience,knows your industry anything other than getting it resources and approach the work and arrives with ready-to-go right,wrong. we do with intention.We believe in knowledge for your project. g building the relationship while we're building the project. I I i yddd J r. • " i= I' 4 C Illl1 t 6v4` ' 4 ' • u. F ti max' .�," oE N— v 4CD A4 S :':s1::: '+-I', C.) — `s t t ri „ . . C::::1 11111:=IL. ,,.t,,,,..i ,r,;,. :4-„,, yy k ti 4� ,lam�V r • to, ,-,;•';-',•1. liming.... (i1=) . ,: 7}. 1 S 1 t%1, y .. N `' 1 ki h t 179 1 V,' 1::= C:::= , ., , . .„./:•"',.Iiikft4i‘Se--'''. C:::=11 C=M 0 . r,,it-:;,;-.)..,',' '_,Nt, : = C.) tea ; , . . W r NINIII �3 � ' meM y , !1 A Current Workload The following information describes our(5)largest projects currently under contract. ,/ , River Oaks Country Club-Level 1 Expansion Houston,Texas -.-„,_.-- :fie. L.' -- ' Owner: River Oaks Country Club i•.T, 1. r` Architect: Gensler Current Contract Amount: $22,847,034 =v Percentage Complete: 14% Specified Contract Completion Date: 02.13.27 Citizens Medical Center ICU Additions and Renovations Victoria,Texas , _ _, Owner: Citizens Medical Center Architect: Downing Ferguson Peebles, LLC _ Ia .4_ _ - 4 �, y `; a... Current Contract Amount: $18,814,693 -,; _T �- - �.`,.__ Percentage Complete: 98% - -"--- Specified Contract Completion Date: 01.04.26 $f X` CHI BSLMC Cosmetic Refresh Houston,Texas _ _ �, Owner: Common Spirit Health _ __ Architect: Devenney Group ilk Current Contract Amount: $11,709,348 Percentage Complete: 72% Specified Contract Completion Date: 03.17.27 Woodson's Reserve East Amenity Center Spring,Texas Owner: Toll Brothers I, I Architect: GSB, Inc. Current Contract Amount: $10,956,436 Percentage Complete: 61% Specified Contract Completion Date: 10.09.26 Eagle Pointe Recreational Center Mont Belvieu,Texas Owner: City of Mont Belvieu Architect: Barker Rinker Seacat Architecture i lit I d . Current Contract Amount: $8,986,935 ' Percentage Complete: 28% Specified Contract Completion Date: 02.01.27 . ,,::r t: = - , ---.• , ,. *.,.4,y-'::1, ,,4,.''' ':".,-21,4.4.22f , 2 , ,i . ,. , .1.11;1.,,;;';',..,;.;:'.1:.14:.,,iii.',.','",:,-.1/114'''-'''''',::',,i:',:,,-:!..". ,,. .. ` ' .:,1.$'W- '''4''''' ,.. I' ....- ,''', .!. ' :' Ur 0 ll lit ''. ''''td.',e.' 11:'''..CiKtl (k''..'-lit;S''' 14. Zs', . .7*.•'., . •,. .4 r, ,,,„:„.,•„•,,,-1,-„,;‘,•••,to,,:t C4 .-____,_,.... , , • : .....,„0 011i[':-::• .,•-.'„!,.i.•4,-7,••• • rt.t.,,,y,.,. .1,,:,:„.. .',k•. ..'- 'i,v, ','•'1,.--"-4:4,.").-+:-:''', T-4.40: CD ,._ • ,r •,-1,,,.• , „i'f,t—',:,-,4c' -' 0 A , OS •..."-h• • .. .,... ;-Ati* -',‘.„',-,,t4,03*r.. Of .,.:•&:,..."4,,,, .t•c,1, ,, ..;,. •,.,,,,,,-.;:,„:0,*,t.', ' .":''''''':, *4----A'',,'..., •...t-.it, i ( 10110 •' ,-;ir,t., `4. , •,tlio','•_kl% :,..•'.• ‘,-;.''- - r' ' ' .. '';':'5".11',;:'-,-...,;:itt,:tV ..„, • ., II' 4.4. . --, . 0,p___,:mill . , •,,,o, ,9,-„!..i,,•':,-,,,--• . .,,,, ,,,,,, :,:,,,,,,:,,,•,-;-,,,--:--:-,,,.",-,*vc ,.A, ''''''''''' ' i, ,y"k:.-',.. :' ',:N'' . • _.-' ;'...i.rt43;C:/,-:A*:. ;-;,Lt,,,,y, :.i, ,,4,411V! •:, • .,..._-_,...--,..,..,,, , .. ,.., ,,,.. V" - - -• 1. . . ' - ,- i .. , - ' •.' ' ;.., , :,.....„, .,,...: ..,,k,,' . - , 5;,, .piE.i,..i,,-i44`.i... t .. fiji:i., ' P.,,,,,„,, , ,0,ii;•Aliiiiii,-,1,1"',-,5",,,V, :';'; ' '•' 'i'',.• •'i[ i • ' • '- u milt : ,. . scum .,, lb. . '..,„a,,,..„.,4,-,:: .;:,.f.11,.'..ttkt,-4:°•;i'i.''*,041".'c ,,,,,,,,i. . 1/2 r..,'-'' :- ' i ! i'il°,'' . •-i', •,.`i Ito!,...-° ,'''''*"":4-' ,.,4.4.:1.-i,•,...;' .,-`vAi.". MI:1111 °,,, tti ," •,,,,,..,;,,7,,,..44:::,..,. ' .4.•k': •1' ''..'1 Nt-...,Vri tR*44,4' ,"‘"": .-.11,- '''';..''.4:, ' i'•- FV'. .,'•'...,',V.,?-i„-..P.,.,. .„:0-7,' .-4J4itt,'4';'.''', ,• I ,,} :VI:UAW. 1 L)ggir4. '''''',,`,`'e'v::. `;,•,.':..''•,..'. '1';';',4',,..;:..,4it.,i; •;f:,..','''."is',•7... ..,.',,'n:'.i4- _ i''.11 'III' ! t'Fill'INI-is • 4 .?-,,,I.,..,.#'-'m,,(:,, ..,A.,. •;„,...-'":„,,K,r,,-..-;,*-v*ri %,•,. . . ,. . .. -1'.--•- . ''''''... ' '5,1",it 'iiii4'.''litA',..tt.f.i'i •;.14if,". , 1' 1:.,;tt -• • ' Am ill r . le •4'-'' .„,-, , ',. min1111111.....1 . t .. . . . ,,,,,,-11 14•:,t-:i.:),-• 4.,:ii,-.‘,0,- r,:t(,,t,...ti;.4i'•: 114171,1,0741:',,,:,,vio:, !--i.' .,i'kl.t--.-.T-.'•';-•,. •,,',1,-,-. , ,-,-r ii 'v---1 .,N.,,--.:1111 14 , • , • 1 . , :- inomenommill torniumminni it ,,,i,..,„ , -, , 2--:-.,7,' .-'j,4,•'.•",:::.-e,;"'r'''', ,, OW- - .•-• . ,,,,,, . , , - 4'r." , „ • ., „.„•, , • - ' .-t*- -1 '‘-.' '.-.;,if,,,,.',.,..,.4-‘14,,,,i,k----,• •,,,, •, .::': itf ."1.' ' .."'Ll.X.• '541''''.1-I''''' '..71, ar,,,,,,',,...: ,,,,,,, .. , •',...,-, .. ', ,•:.: ::: '''' '"),1 -'H;4' •,-- IIIMIllmegii . f....,:I . ,, ' *'...4'. -''Y''.---: '-i ' I , .. "' . . (CiiiiiiiM •- - . , '.''1,147'.'• '..,- i:ii ., .. ', oi-, ..i .,, , ..., 'ii:`, illil MINI - •-. ‘ . - •',. NW' ' il .. .. . .0: --:„',- • —' '.'..,,' ..„..,,..; " • '1' .''' :,t'„,'...''''.:'...i,''''' • ,.... '''' ,,,- Pf.i'4.14 44'1'1 ' AIS la "'''''''',4' V.,..f•;143;!ii-,.., ‘:::'• ,• , ,•,!.;,:.•.;, 1 Iii 0 '-*.t.'',4••:..: ,fr.i 't 'ql•rf-,,'';-::-,-. ' pi 1 Li 1 j is„ow 1.11111.11111111111. A : iii, '..,:.'",' '.' •,'...•,',,, ' 'I'T.':'''''''..:;• ' ', :.c,•,.'1,;'`..;:.'' atil. ... .,44.%, 4111.7,, ,,i' ,,,• .4.):4...,;-,•,. •.- :tli'^;-,1' ."• ., .•;,,, '..,,t , . •. . ., .. • . ' • . . . . . . • Financial Information `otal amount of ork Performed as a rneral contra� 2025 $158,200,000 2024 $149,400,000 2023 $125,100,000 2022 $134,900,000 2021 $85,700,000 Per project $100,000,000 Aggregate $200,000,000 ontrimerne Bank Gokinos Bond Agency Mallory Idelman Vice President Kyle Cokinos 713.300.2691 President 1900 W. Loo Sa 713.940.6522 p uth 1337 W. 43rd St. Suite 1800 Houston, TX 77027 Suite 105 Houston, TX 77018 Dun & Bradstreet Number 015443093 • \ :,...;i, ..,'.. 1 -:,..',I. ,' 1 ‘•-•, :', :,-. . , :, .. , , R :44: t=1';,-',,''''',1;it 1:,..a:*'.:i. .,-i=t, G rM1 Y ('' y. V� 1 t 11 S ly't^y�) I ;.,4r."l'?0,.A,I%',.:g,).-,‘,,..1, ..41/4-,i, 7 t ' Mi. rPsnly '1 � 11, .fir . „ ' : 17c T R E � • - f.` 4Ez r 71 i �9 , _ • y vii ,,, e _ �/ . dt � 1; .: , .....5::;.4).010,,, $14, ' Y i•a. 1 ` # I 0 1 e� Y'. I I j 'I ''t: • t t N t f.' «MYY .' 7 E� Illlillllll Ilfltl(itll 11111 A (gip • 1 IIIIIIIIIIIIIIIIIIIIIIIIBi4 + ! i y 1s a s ll ' I. fi ITV b �> , • r FiE�.M1+ � ." ".r 'I �. I i I "" _� A y ,'• ' 'ra'� ire 9 �" ! I • •t Y., ri t 1:,,i''''',' '''' i''': ,,-.1:1, :`,i1-1-.; l';:,-i i '_ • ,-;,, i� 1jj,:,,,,,,,,,,,:,,,t4,,A-:: .z,:. �� " 'i �€i..l ..?K.14 w^Y9 to a,'. L +`t. I'1 fan. f'>r „ •1` "'.3Ft.* qr fir sz ai, f ri'• d o • +� + wEtik` v; {{ "4 '`'Y fit t !�.Y r +(�r� =�raytit' y�'�1 i Y� �RS� {s..t .',tir `.: J /�,�I j •1 5 1'4.,, Y4 .'�4 O .( y(�ii� � x 'F ryi -1rb s 3�i 'f, < w -re';',,-,It ;lf,� •,v- �j,r Y 4 ,y��. 'H.I' 3 .+'.. �>{ �;.,.Y.l{r�° f, i is I}1 r r t �t'r�^ ' iSg Td*. }r ' 1 I I i �'2,i la . a ah ,ay",� t 1r L` Y 2 ° 1 P,r r:S K+ 6 l T ..: 11V M'S`'3 V� 'k iti, 1. •, 4 ( ._:t � ✓ S ' i ' x. K 1 . 1. .1 1 ii t‘.." ' Safety INVESTING INTO OUR COMPETITIVE ADVANTAGE: OUP, PEOPLE Our team has established a company-wide, aggressive Safety Program that is the basis of every project-specific safety plan developed. These requirements exceed OSHA's minimum guidelines. While Forney maintains a company-wide safety program, the Forney team evaluates the individual needs of each client and project and develops a project-specific safety Primary responsibility for the development of the program safety program award. with the assigned Project Superintendent;however, our Vice President of Field program lies Operations, Steve Mounts, and our General Superintendent, Nick Rosinski, are 2024 Worker'sn Rate also heavily involved in the process. Compensation Experience Modification Rate Safety By Design Forney Construction has commissioned Safety by Design, a third-party safety consulting unannounced safety audits at our job sites. The audit results are shared with our field operations team and members of the executive management team. Any items of concern firm, to provide weekly, quickly evaluated and resolved. We use these job site audits to keep track of long-term prations management quickly ly and y. If any subcontractoretheejob has audit to k site safetyng-ter discovered during sg the audit are our database and we will not enlist them on future projects. g m safety statistics of our infractions they are removed from Forney Safety Committee Leadership at Forney Construction takes responsibility for the safety of our employees, our subcontractors and the general public on or near our project sites very seriously. p We are continuously looking for opportunities to improve safe working practices on our project sites and to learn from all incidents or site-specific conditions that could have possibly contributed to Our operations leaders and our project managers meet regularly for the purpose of In injury or accident. all our projects. Our entire operations group including management is continuously focused on creating a safe working environment o pleveryanning the safe completion project managers, fieldsuperintendents e Forney and executive project. Forney Construction Some highlights of our Safety Management program include: A. Executive Safety Committee's Primary Objectives 1. Causation investigations 2. Site safety plan approvals 3. Monitoring key safety performance indicators for all projects 4. Frequent re-evaluation of processes B. On-site safety program management by Safety by Design, a third-party safetyconsulting C. Successful completion of OSHA 30-hour training tmg firm program — required of all Superintendents D. Site-specific safety plans 1.Job hazard analysis 2. Hazard inspections 3. Safety pre-planning for all construction activities 4. Lift plans 5. Site safety orientation a.All new Forney Construction projects b. All new on-site Forney Construction hires c.All subcontractors E. Proactive incident case management by Axiom Medical Consulting, LLC f �y1 x K{{t ", ' 1 "� e r1T: .,'..1P a-lei 1,. [+i h aF >p t t +4fii :2ii) if ipl0$1 --:-i:, i,r_, ' '4 i:itc--‘'4' '' it f'i 1 l'.. ''.'- t'41:''' ',.. "7..,$;.1:',,,t,''''', ',„ id slt t'l ' • I,' t:A.',‘Z-1:::-Ti'!' - i' 4 It til.;.•AY;i;,,,4-:;-0'ii,'';'1;:''''-‘1.17:.'—e;,''' J C � i ti, . , irr e Q 1 y�/P +' is ¢.fr i i ,. A, r a_., .2, d ! iS .., a. l .re'.3 ,u, "'#' i}k}( li i A. r .., v f% 1>e s r } + +F? y p ,o k1 .a i g4 .. a Yv fi s mr its J., k d /m p p� # 45 4i 1 -"' ' }E f ,,, 3' k r' itirmi, �Ii d r# fs� D }° 3M�p,€i` + Mgr {i mi.$ x 9 j:�X�i � ' ��t'11�������" tea ;` a�;I "14;iiol rr',,! 1,1a€adil r,t,d, tntyattaat1i10191e!liAAA111 4{,,t,,I 1# t lF� �` ,i.y;l` ''' i ++ y 1'f-,,:,44 a . *� Ewa. k 'tj _ _ I py� et "i � � � t , . , '',,,,, -; /it* 110113144i0' '.4'- 4 .;,,I,P,. , -"fr'. '- ' 4 R� •� 7!� 11414 '``;. f ti 4 .. o s t114 aj`��d r \It #' I, � t�rli, p #@W �� 1 �. dot PI: s 4:i l:' 1 j:4t'w x. r, *.=q,�■N ib �r v.T+ 1 r; 7 °k OT_�ti sxpl E d ..," " ��ri !' r r r 4.7,1 4',,-'','' 4.7.1.4i: ,s,,,o,4,,, . i „IT, GIt it K 4 ), y _ y..� y,wr ter a` `-. ,t 0�1 1 1 * 1 ;' J;g'. j k. • ` e @ y f '. � i'%' ' -ter,. .�1 r { ` u•. , i �� war !{ ° r'p i ; d°t �iCC �r t4 .� r a F s� #44: k. M T ,, ' i i ' x� iSx Y P ka7 i # 1 x f 1. ei era r r, r yyy '�' s m y �' b �T �i 3 �,,y,�la]p1,,,�}}}.i _ f� {i!�4 ' 4 ? ro 1 ,ir 71[y w; +1: tlFayh- �' r 21 vvs� d !ii //�� i) IT ((' e{� t', + h k�l� k ��;�(��M!�l;i/ i ad• . ..� ,y l8 x. �: V = ,� 4r' �'r�,�'+,r � milim i , 1;t 'i ' ,_ 4 ale+d r s I , i� ` s� rd f c r`�. P n *F { m• •i • } r , 1IIII t iki1tG11 ,fix. J { ` t yr t a d:f1! "ft�7 1{ �' k 3, fr PROPOSAL FORM Company Name: Forney Construction Address: 8945 Long Point Road, Suite 200 Houston, TX 77055 Phone: 713-224-1900 Fax: 713-224-1901 Having examined the Request for Proposal, the following is a breakdown ofall fees and costs. proposed A. FEE PROPOSAL 1. FEE For overhead and profit and all preconstruction services, list your proposed fee as a percentage of the cost of the work. 3.00 % 2. GENERAL CONDITIONS COST (Percent) For all General Conditions, list your proposed cost as a percentage of cost of the work. Refer to Schedule "A" for all required items to be included in the General Conditions cost. See attached breakdown for further detail. Based on 13 month duration. 13.87% (Percent) 3. PRECONSTRUCTION SERVICES NOT-TO-EXCEED COST All costs for pre-construction phase services including cost estimating, scheduling, building systems and material cost analysis are included in the FEE, item 1 above. However, if the construction phase does not commence for any reason, payment to the Construction Manager for preconstruction services shall be the necessary and reasonable cost of such services, not to exceed the lump sum of: Dollars $ 15,937.45 (Amount in figures) If the amount is "zero", enter"0"; do not enter"no bid" June 19, 2026 RFP for Construction Manager at Risk E-1 B. ADDENDA Undersigned acknowledges receipt of Addenda Numbers : 1 ( ) C. CONSTRUCTION MANAGER'S PERSONNEL The Offeror agrees to employe Work at the the following individuals for the entire duration of positions indicated, and agrees not to remove them from the Work nor replace them with others except as otherwise allo Documents or approved in writing by the Owner: wed in the Contract Project Manager: Mat Morris Superintendent: Frank Runnels D. REPRESENTATIONS By execution and submission of this Proposal, the Offer represents and warrants to the Owner as follows: °r hereby agrees, 1. Offeror will hold Proposal open for acceptance for ninety 2. Offer accepts the Owner's right to rejecta (90) days. formalities and to accept the Proposal which the Ownerpconsiders most waive advantageous. 3. By signing this Proposal Form, the undersigned on behalf affirms that, to the best of his knowledge, the information concerning Proposal has been arrived at independently of the Offeror collusion with anyone to obtain information or and is being submitted without this gain ny would in any way limit competition or give an unfair advanta9over favoritismeother that respondents in the award of this Proposal. 4. All contingencies and savings shall be returned one (100%) to the Owner. hundred percent 5. Offeror has read and understands the Proposal Documents Documents, and this Proposal is made in accordance wit and thee Contract Documents. he Proposal 6. Offeror has carefully inspected the Project site, and that own investigation, the Offeror has satisfied itself as to the nature and Off location anon of the Work within the scope of the Project and the character , June 19, 2026 RFP for Construction Manager at Risk E-2 7. Quality, quantities, materials and difficulties to be encountered; the kind and extent of equipment and other facilities needed for the performance of the Work; the general and local conditions and other items which may in any way affect the Work or its performance; and the Offeror has correlated the Offeror's site observations with the requirements of the Contract Documents. The Offeror understands and accepts the difficulties and costs associated with the Work and the Project site and the potential delays, disruptions in work and costs associated therewith and has included such considerations in its construction schedule and the Proposal amount. 8. All information submitted by the Offeror to the Owner in response to this Request for Proposals is true and correct. The City, or any authorized representative of the City, is authorized by the undersigned to contact any firm, institution, or person to obtain information about our firm's services, financial condition, and any other information which the City might determine as being desirable. 9. To the fullest extent permitted by applicable law, the Offeror waives any claim it has or may have against the Owner, the Architect, and their respective trustees, officers, shareholders, directors, partners, agents, contractors, consultants and employees arising out of or in connection with the administration, evaluation or recommendation of any offers; waiver of any requirements under the Proposal Documents or the Contract Documents; acceptance or rejection of any proposals; and the award of a Contract. 10. The Project will be undertaken in accordance with the applicable provisions of Chapter 2269, Subchapter F of the Texas Government Code. 1/6,r_y By: (Signature) Alberto Garza (Printed Name) CEO (Title) June 19, 2026 RFP for Construction Manager at Risk E-3 Nature and Visitor Center at Pleasure Island 1111 Port Arthur,TX 77640 Proposal Date:7/29/2026 Total Work Area: 10,000 sf FORNE Duration: Fee Proposal 97 Weeks Fee Preconstruction Services Fee 3.00% $ 203,883.50 Preconstruction Services 41 wks $ 15,937.45 General Conditions General Conditions 56 wks Insurance 2.74% $ Overhead 163,731.00 3.84% $ 229,035.41 Total General Conditions 7'29% $ 434,840.00 Total Costs 13.87/ 827,606 Alt#01 Allowance for Additional Week of Preconstruction Services 1,047,427 Alt#02 Credit to Preconstruction Services upon Successful Commencement of Project ADD $ 540 Alt#03 Allowance for One Additional Week of Overhead&General Conditions DEDUCT $ (15,937) Alt#04 Credit if Building Permit Cost Waived/By Owner ADD $ 5,168 Alt#05 Credit if Plan Check Fee Waived/By Owner or Design Team DEDUCT $ 23 220)( DEDUCT $ (15,208) Nature and Visitor Center at Pleasure Island Port Arthur,TX 77640ig„, Total Work Area: 10,000 sf Proposal Date:7/29/2026 FORNE Duration: 41 Weeks 1 General Requirements Mileage Subcontractor Drawings FC 41 Unit Unit Rate Subtotal Totals FC 431 wks 34.64 1,420 ea 150.00 450 Cost of Work Direct Overhead 1,870 %of Time 1,870 1,870 Estimating Director Qty Unit Unit Rate 3.0% 41.00 wks Subtotal Totals Vice President/Preconstruction Manager Estimator 2.0% 2,885 3,548 Labor Burden 41.00 wks 2,885 2.5% 41.00 wks2,957 2,308 2,365 8,870.19 Is 40% Insurance 3,548 General Liability Insurance&Umbrella Policy $ 12,418 Builders Risk Insurance Q� Unit Unit Rate Subtotal Totals Payment&Performance Bond Group 1 14,289 Is 0.50% 14,389 Is 100 Not Required 0.021% 100 Excluded Total Cost $ 200 Contingency $ 14,489 $ 14,489 Fee Qty Unit Unit Rate 14,489 $ 0.00% Totals State Sales Tax 14,489 $ 10.00% 0 Total Proposal Tax Exempt 1,449 15,937 $ 0 0 Alt#01 Allowance for Additional Week of Preconstruction Services ADD $ 540 Alt#02 Credit to Preconstruction Services upon Successful Commencement of Project $ 15,937 DEDUCT $ (15,937) 40% 56.29 wks 2,596 58,455 Project Coordinator 56.29 wks 1,731 48,713 Labor Burden 50% Field Operations&Safety 303,100.00 Is 40% 121,240 7,000,000.00 % 0.15% 10,500 Insurance General Liability Insurance&Umbrella Policy QLY Unit $ 434,8 Builders Risk Insurance 32,835 Unit Rate Subtotal 6,567,081 Is 0.50% Totals Payment&Performance Bond Group 3 6,599,917 Is Required 1.00 Is 112,200 0.098% 84,000 112,200 Total Cost $ 229,03 Contingency Qty Unit $ 6,796,117 $ 6,796,11' Fee Unit Rate 6,796,117 $ 0.00% Totals 6,796,117 $ 3.00% Sales Tax Tax Exempt 0 7,000,000 $ 203,883 Total Proposal 0 0 $ 7,000,000 Alt#01 Allowance for One Additional Week of Overhead&General Conditions Alt#02 Credit if Building Permit Cost Waived/By Owner ADD $ 5,168 DEDUCT $ (23,220) Alt#03 Credit if Plan Check Fee Waived/By Owner or Design Team DEDUCT $ (15,208) r , �h r� �� tYt � • yak Nf j G ,„..,,. 4',--' ; �+ sit l; r � �y ,. w di /{{ Kt ^���y{y 1'' rn, y.Yr ry.Y a ,� '. ; d �� ,if !fir +.e *�.e x #x I ciI f 004:4t° !3 4.14t1 `0 ' CD I C:::::1) ,' ' t 3sr �.bp- ,+ ' Y "w^,; I 1I "` ' r l S ,-.vv .r. r , a.., A '.' - s.', cil k fix; f'^ pndg7 ♦�' *^' ' k. f: (s CU • w .. r Mg ( ,111.'.',t-,` ';'„, ,", ,. 111Milimmill C:=I - ry z. r e `" "' 2 1 C°1° fir- ii . C:= 1474,,,'..•i I .ikr r ''). " �, X�ahb:.r«fit WA*. i�ccyY s ,. -.F NI • CO r t �9 s= 64 { t NON-COLLUSION AFFIDAVIT CITY OF PORT ARTHUR § STATE OF TEXAS By the signature below, the signatory for the bidder certifies that neither he nor the firm, corporation, partnership or institution represented by the signatory or anyone acting for the firm bidding on this project has violated the antitrust laws of this State, codified in Section 15.01, et seq., Texas Business and Commerce Code, or the Federal antitrust laws, nor communicated directly or indirectly the bid made to any competitor or any other person engaged in the same line of business, nor has the signatory or anyone acting for the firm, corporation or institution submitting a bid committed any other act of collusion related to the development and submission of this bid proposal. Signature: Printed Name: Alberto Garza Printed Name: Alberto Garza Title: Chief Executive Officer Company: Forney Construction Date: 07.29.26 SUBSCRIBED and sworn to before me the undersigned authority by July the 29th of, 2026 on behalf of the said bidder. �11,,(A,,���U✓U� Notary Public in and for the State of Texas TRACY R DAIMLER 1 My commission expires: 12.03.28 I r . `}�Y� jl Notary Public,State of Taos mi ' ry �� � My Commission on Expires I ,,� t December 03,2028 `4....o1.<, NOTARY ID 3988.183 AFFIDAVIT All pages in Offeror's Responses containing statements, letters, etc., shall be signed by a duly authorized officer of the company whose signature is binding. The undersigned offers and agrees to one of the following: X I hereby certify that I do not have outstanding debts with the City of Port Arthur. I further agree to pay succeeding debts as they become due. I hereby certify that I do have outstanding debts with the City of Port Arthur and agree to pay said debts prior to the execution of this agreement. I further agree to pay succeeding debts as they become due. I hereby certify that I do have outstanding debts with the City of Port Arthur and agree to enter into an agreement for the payment of said debts. I further agree to pay succeeding debts as they become due. Forney Construction 07.29.26 Firm Name Date Chief Executive Officer Authorised Signature Title Alberto Garza 713.224.1700 Name (please print) Telephone alberto.garza@forneyconstruction.com Email STATE: TX COUNTY: Harris SUBSCRIBED AND SWORN to before me by the above-named_ Alberto Garza on this the 29th day of July , 20 26 TRAGYRDNMLER Notary Pudk,ST.of T.xu �.1 WO✓�ll-✓-, MDiimborO3 220028� Notary Public NOTARY iD3cee4ea RETURN THIS AFFIDAVIT AS PART OF THE BID PROPOSAL CONFLICT OF INTEREST QUESTIONNAIRE FORM CIQ For Vendor or other person doing business with local governmental entity This questionnaire reflects changes made to the law by H.B. 1491,80th Leg.,Regular Session. This questionnaire is being filed in accordance with Chapter 176,Local Government Code by a person who has a business relationship as defined by Section 176.001 (1-a)with a local governmental entity and the person meets requirements under Section 176.006 (a). By law this questionnaire must be filed with the records administrator of the local governmental entity not later than the 7th business day after the date the person becomes aware of facts that require the statement to be filed. See Section 176.006,Local Government Code. A person commits an offense if the person knowingly violates Section 176.006,Local Government Code.An offense under this section is a Class C misdemeanor. 1.Name of person who has a business relationship with local governmental entity. 2. Check this box if you are filing an update to a previously filed questionnaire. (The law requires that you file an updated completed questionnaire with the appropriate filing authority not later than 7th business da after the date the originall filed •uestionnaire becomes incom•lete or inaccurate.) Confirming that Forney Construction does not have any conflicts of interest to 3.Name of a local gove disclose. Name of Officer This section(item 3 including subparts A,B,C,&D)must be completed for each officer with whom the filer has an employment or other business relationship as defined by Section 176.001 (1-a),Local Government Code.Attach additional pages to this Form CIQ as necessary. A. Is the local government officer named in this section receiving or likely to receive taxable income,other than investment income,from the filer of the questionnaire? Yes No B. Is the filer of the questionnaire receiving or likely to receive taxable income,other than investment income,from or at the direction of the local government officer named in this section AND the taxable income is not received from the local governmental entity? Yes No C. Is the filer of this questionnaire employed by a corporation or other business entity with respect to which the local government Officer serves as an officer or director,or holds an ownership of 10 percent or more? Yes No D. Describe each employment or business relationship with the local government officer named in this section. 4. Signature of person doing business with the governmental entity Date SB 252 CHAPTER 2252 CERTIFICATION Alberto Garza ,the undersigned and representative of Forney Construction (Company or Business Name) being an adult over the age of eighteen (18) years of age, pursuant to Texas Government Code, Chapter 2252,Section 2252.152 and Section 2252.153,certify that the company named above is not listed on the website of the Comptroller of the State of Texas concerning the listing of companies that are identified under Section 806.051,Section 807.051 or Section 2253.153.I further certify that should the above-named company enter into a contract that is on said listing of companies on the website of the Comptroller of the State of Texas which do business with Iran, Sudan or any Foreign Terrorist Organization, I will immediately notify the City of Port Arthur Purchasing Department. Alberto Garza Name of Company Representative (Print) Signatui'e of Company Representative 07.29.26 Date House Bill 89 Verification Alberto Garza (Person name), the undersigned representative (hereafter referred to as "Representative") of Forney Construction (company or business name, hereafter referred to as "Business Entity"), being an adult over the age of eighteen (18) years of age, after being duly sworn by the undersigned notary, do hereby depose and affirm the following: 1. That Representative is authorized to execute this verification on behalf of Business Entity; 2. That Business Entity does not boycott Israel and will not boycott Israel during the term of any contract that will be entered into between Business Entity and the City of Port Arthur; and 3. That Representative understands that the term "boycott Israel" is defined by Texas Government Code Section 2270.001 to mean refusing to deal with, terminating business activities with, or otherwise taking any action that is intended to penalize, inflict economic harm on, or limit commercial relations specifically with Israel, or with a person or entity doing business in Israel or in an Israeli-controlled territory, but does not include an action made for ordinary business purposes. c, SIGNATURE-OF REPRESENTATIVE SUBSCRIBED AND SWORN TO BEFORE ME, the undersigned authority, on this 29th day of July , 2026 . 4,,,:.; TRACY R DAIMLER /�� Noterryy Pudic,Stitt•of Tutu tPl; My Commis+ nExpiraa 0..41h UU+1y✓L Decamber03,2°28 NOTARY ID 39984$3 Notary Public a y • • yFaRt% Forney Construction iorneyconstruction.com 8945 Long Point Road,Suite 200 Houston, TX 77055 713.224.1900 © O