RE: P.R. 25275 —Rose Hill Park Prefabricated Restroom Facilities-Restroom
Facilities LTD
Introduction:
The intent of this Agenda Item is to request the City Council's approval of P.R. No. 25275
authorizing the City Manager to enter into a contract with Restroom Facilities LTD of Marble
Falls, Texas through Buyboard Cooperative Purchasing Contract No. 781-25 for a turnkey
installation of a prefabricated restroom building at Rose Hill Park in the amount of
$508,905.00.
Background:
Pursuant to Resolution No. 24-176, the City Council approved and adopted the Rose Hill Park
Master Plan,establishing the vision and improvements necessary to revitalize and enhance Rose
Hill Park. The Rose Hill Park Hardscape and Landscape Improvements project is intended to
implement the approved Master Plan and enhance the park through the construction and
installation of planned hardscape, landscape and related site improvements.
The Rose Hill Park improvements are designed to transform the park into a premier recreational
and community gathering destination for the City of Port Arthur, consistent with the City
Council-adopted Rose Hill Park Master Plan. Part of the approved and adopted plan included a
prefabricated restroom facility on the park. Restroom Facilities Ltd of Marble Falls, Texas
submitted a bid for a turnkey installation of a prefabricated restroom building at Rose Hill Park.
The installation of prefabricated restroom facilities will enhance visitor convenience and
accessibility while providing improved accommodations for residents and visitors participating
in recreational activities, community events, and other gatherings.
Budget Impact:
Funding in the amount of$508,905.00 is available in Capital Improvement Account Number
307-25-067-8525-00-10-000; Project Number PR0018
"Remember,we are here to serve the Citizens of Port Arthur"
P.O.Box 1089 X Port Arthur,Texas 77641-1089 X 409.983.8182 X FAX 409.983.8294
Recommendation:
It is recommended that the City Council approve P.R.No.25275 authorizing the City Manager
to enter into a contract with Restroom Facilities LTD of Marble Falls,Texas through Buyboard
Cooperative Purchasing Contract No. 781-25 for a turnkey installation of a prefabricated
restroom building at Rose Hill Park in the amount of$508,905.00.
"Remember,we are here to serve the Citizens of Port Arthur"
P.O.Box 1089 X Port Arthur,Texas 77641-1089 X 409.983.8182 X FAX 409.983.8294
P. R. #25275
11/8/2026 ca
RESOLUTION NO.
A RESOLUTION AUTHORIZING THE CITY MANAGER TO ENTER
INTO A CONTRACT WITH RESTROOM FACILITIES LTD OF
MARBLE FALLS, TEXAS THROUGH BUYBOARD COOPERATIVE
PURCHASING CONTRACT NO. 781-25 FOR A TURNKEY
INSTALLATION OF A PREFABRICATED RESTROOM BUILDING AT
ROSE HILL PARK IN THE AMOUNT OF $508,905.00. FUNDS ARE
AVAILABLE IN THE PARKS AND RECREATION CAPITAL
IMPROVEMENT ACCOUNT NUMBER 307-25-067-8525-00-10-000
PROJECT CODE PR0018
WHEREAS, pursuant to Resolution No. 24-176, the City Council approved and adopted
the Rose Hill Park Master Plan for the City of Port Arthur; and
WHEREAS, the Rose Hill Park Improvements are designed to transform the park into a
premier recreational and community gathering destination for the City of Port Arthur, consistent
with the City Council-adopted Rose Hill Park Master Plan; and,
WHEREAS, part of the approved and adopted Rose Hill Park Master Plan included a
prefabricated restroom on the park; and,
WHEREAS, Chapter 271 of the Texas Government Code allows a city, by resolution of
its governing body, to participate in cooperative purchasing programs, such as Texas BuyBoard
as an alternative to formal bid process; and,
WHEREAS, pursuant to Resolution No. 02-341, the City of Port Arthur entered into an
interlocal agreement for cooperative purchasing with Texas BuyBoard; and,
WHEREAS, Restroom Facilities Ltd. of Marble Falls, Texas, is part of the BuyBoard
Cooperative Purchasing Program under Contract No. 781-25 and submitted a bid for a turnkey
installation of a prefabricated restroom building at Rose Hill Park in the amount of$508,905.00
(attached hereto as Exhibit"A").
NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE
CITY OF PORT ARTHUR, TEXAS:
Section 1. That the facts and opinions in the preamble are true and correct.
Section 2. That the City Council hereby authorizes the City Manager to enter into a
contract with Restroom Facilities LTD of Marble Falls, Texas, through BuyBoard Contract No.
781-25, for a turnkey installation of a prefabricated restroom building at Rose Hill Park in the
amount of$508,905.00 (attached hereto as Exhibit"A").
Section 3. Funds are available in the Parks and Recreation Capital Improvement
Account, account number 307-25-067-8525-00-10-000, Project Code PR0018.
Section 4. That a copy of the caption of this Resolution be spread upon the Minutes
of the City Council.
READ, ADOPTED AND APPROVED THIS day of , A.D.,
2026, at a Regular Meeting of the City Council of the City of Port Arthur,by the following vote:
AYES: (Mayor)
Councilmembers:
NOES:
Charlotte M. Moses
Mayor
ATTEST:
Christe Whitley Ned, TRMC
City Secretary
P. R. #
11/8/2026 ca
APPROVED AS TO FORM:
Roxann Pais Cotroneo, Esq.
City Attorney
VED AS TO ADMIN TRATION:
•
Ron Burton, CPM
City Manager
j11,01OtA('
Chandra Alpough, CPM
Director of Parks and Recreation
APPRO AS TO AVAILABILITY OF FUNDS:
Boswell, PhD
Director of Finance
/I
Clifton Williams, CPPB
Purchasing Manager
Exhibit "A"
R F L Restroom
Facilities Ltd
A corworth Company
TURNKEY QUOTATION
PROJECT NAME: ROSE HILL PARK - PREFABRICATED RESTROOM BUILDING
OWNER: THE CITY OF PORT ARTHUR, TEXAS
DATE: NOVEMBER 5, 2026
Restroom Facilities Limited (RFL), the Nation's leading specialized restroom design/build firm
since 1988, offers to furnish and install, per plans and specifications, subject to our attached
Scope of Work, and the Standard Terms and Conditions of Sale, which become part of our offer
to sell.
BUYBOARD CONTRACT# 781-25
TOTAL PURCHASE PRICE
MODEL# B424CEDFST @ $ 508,905.00
This amount includes freight, crane and installation.
Payment terms: 50% installment with order; 45% in progress billings during construction; and
balance of 5% upon completion of delivery and installation, no retention. Payment of 95% must
be received by RFL prior to scheduling of delivery and installation. Thank you for considering
RFL as your restroom specialist for this project.
HOW WE WORK
Once plans have been approved and engineer stamped, the manufacturing process begins.
The manufacturing process begins with execution of sales order and receipt of approved
submittals, color selections and progress payments. It is the responsibility of the Client to
respond to color selections in 1-3 days, if this condition is not met it will delay the construction
process and the Client may incur additional charges. In-plant inspection reports and
certifications will be provided by an independent inspection agency.
The client must prepare the site in accordance with the "Scope of Work by Client" attached and
coordinate any required on site inspections. Client is required to provide verification that the site
is ready for delivery in accordance of Client's scope of work.
Exclusions:
A. Sidewalks beyond building slab.
B. Site issues beyond the control of RFL.
Initial Initial Page 1 of 9
1707 Colt Circle, Marble Falls,Texas 78654 • Phone: 512.222.5454 • www.restroomfacilities.com
C. Damage to existing improvements.
D. Protection of existing utilities, landscaping, and improvements.
E. If required per geotech report, footing, piers, and/or select fill labor and materials to be
provided by others.
F. Excavation and backfill of trenches
G. Any components not explicitly listed or written in the specification section of the bid
documents
CLIENT'S SCOPE OF WORK
TURNKEY INSTALLATION OF RESTROOM BUILDING WITH ATTACHED SLAB
1. SURVEY STAKES:
Provide ten foot offset stakes and locate front corners of building, existing utilities, and
inverts within the area of construction. Locate and mark final slab elevation.
2. SUBGRADE PAD:
Detailed instructions to prepare the building site are as follows:
2.1. Excavate down ten inches below the finish floor elevation (the slab is eight inches
thick on top of a two inch sand bed).
2.2. Import six inches of - road base rock, and pour for a footing and/or piers.
2.3. Compact to 95%, or to local code requirement. If RFL installer questions 95%
compaction Client will be required to sign off on approval of setting of the
building.
2.4. Compact one foot over in all directions (over build).
2.5. Supply approximately enough clean sand to develop a 2" bed on compacted soil,
on side of site, for fine grading.
2.6. Excavate and backfill trenches up to and within building pad for RFL supplied
underground utility service kits.
2.7. Provide water and inspection for RFL supplied underground sewer kit.
2.8. All irrigation should be turned off prior to delivery to allow the surrounding soils to
dry and bear the weight of the truck and crane. Any damage to area after
verification of path in is the responsibility of the Client.
2.9. Check corner locations against plans for proper sizing.
2.10. Verify finish floor elevation for concrete slab (shipped fully attached to the
building.)
2.11. Excavate one foot perimeter footing if required by local code to specified depth.
2.12. Verify that pad is level and flat and at correct elevation.
3. SITE ACCESS AND STORAGE:
Provide suitable safe clear access to allow a crane (minimum 110 tons), and the building
on a semi-trailer (up to 40 tons) to reach site (14' width, 70' length, and 14' in height). If
path to site is over existing utilities, sidewalks, or other damageable areas, proper
Initial Initial Page 2 of 9
1707 Colt Circle, Marble Falls,Texas 78654 • Phone: 512.222.5454 • www.restroomfacilities.com
marking, plating or other appropriate protection must be provided by and paid for by
CLIENT. CLIENT is responsible for removing any overhead obstructions (i.e. power
lines, trees). CLIENT is responsible for scheduling and paying for the de-energizing of
any power lines, if powerlines are not de-energized in a timely manner any additional
truck and / or crane cost will be the responsibility of the Client. CLIENT is responsible for
rerouting or blocking of traffic to ensure safe and clear access, or if required by local or
State jurisdiction. to delivery site and will be responsible for associated costs. Upon
agreed delivery schedule client will be responsible for additional crane and trucking
charges if any delays are incurred due to weather, lack of inspections, lack of pad being
prepared, or any other cause for delay.. This proposal provides for a 110 ton crane with
access to within 25' of the building pad. The proposal is based on four (4) hours of
crane time. If access is limited a larger crane may be required. All additional crane
costs shall be borne by the CLIENT. A direct route to the project site is assumed.
Should routes be altered due to road closures or restrictions, additional fees may apply.
4. UTILITIES:
Bring water, sewer, and power (if applicable) utilities into point of connection Christy
boxes (supplied by RFL), within six feet of the building line at the location shown on our
plan.
4.1. Water: RFL will furnish a water point of connection (isolation valve), from
mechanical chase to a Christy box six feet from the building line. CLIENT must
have a licensed plumber connect the water supply line inside of the building
plumbing chase room, and connect service to the valve located outside of the
building.
4.2. Sewer: RFL will furnish a sewer point of connection from mechanical chase to a
Christy box six feet from the building line. CLIENT must have a licensed plumber
install sewer vent stack (provided by RFL) inside of the plumbing chase room,
and connect service outside of the building. Depth of sewer line (below finished
floor elevation) will be approximately 30" at bottom of sewer line at a distance of
6' from building. It is the responsibility of the Client to meet up with RFL's
supplied sewer line at this depth. Client will be responsible for the hiring of a
licensed plumber to acquire appropriate plumbing permit, to install prefabricated
underground plumbing kit into pre dug trench, and to make connections between
underground stubups and internal building plumbing located in the plumbing
chase room within the building. RFL installer will be on site to answer any
questions or give direction as to proper installation of said plumbing kit as
requested by licensed plumber or client.
4.3. Electrical: (when this option is chosen) RFL will furnish and install a PVC conduit
to the point of connection six feet from the building line. CLIENT to pull the
electrical service line through the conduit and connect to the main panel lugs
inside the building. All electrical inside the building will be furnished and installed
by RFL, except as noted above in exclusions.
Initial Initial Page 3 of 9
1707 Colt Circle, Marble Falls,Texas 78654 • Phone: 512.222.5454 • www.restroomfacilities.com
R„.
4.4. If the utilities are not available and connected to building when we depart the site,
an additional charge will be billed to the CLIENT in the amount of 1,500 per day
to 2,800 per day (dependent on location) to send an installation crew back to site
to flush out plumbing lines, pressurize building plumbing, test for leaks, test all
other components of the building (plumbing, sewer, electrical), and conduct a
final walk through of the building.
4.5. A minimum 11/2" line with 50 gpm at 60 psi pressure minimum is required to
ensure that water closets will operate as designed. If this is not available an
auxiliary holding tank may be required.
5. SPECIAL CONDITIONS AND COSTS:
If specifications and / or local ordinances by owner and /or local jurisdiction require any
testing, work by licensed plumbers, work by licensed electricians, or special inspections,
costs, if any, shall be borne by CLIENT.
6. PERMITS AND FEES:
All building permits and fees shall be borne by CLIENT.
7. INSPECTIONS:
We require that all inspections be scheduled with adequate notice to ensure that the
underground plumbing and electrical work is approved prior to placement of building.
We require that final inspection and acceptance by owner and building officials be
performed immediately following RFL's completion of installation. If any conditions exist
in which RFL cannot conduct a final walkthrough (no utilities / partial utilities available
during install, or other circumstances beyond our control) there will be an additional
charge of 1,500 to 2,800 (dependent on location) per day to send an RFL install crew or
crew member back out to site at a later date to complete the installation. We also
require final inspection and acceptance immediately following RFL's conclusion of any
correction items.
8. SITE CLEANUP AND DEBRIS REMOVAL:
CLIENT shall provide an on-site trash bin for disposal of one pick up load of debris. All
excess spoils shall be the responsibility of the CLIENT. All rough and final grading shall
be by CLIENT.
9. VERIFICATION OF PREPARED PAD:
Client must verify elevation, compaction of pad as well as the pad being flat and level
prior to delivery of building(s).
Initial Initial Page 4 of 9
1707 Colt Circle, Marble Falls, Texas 78654 • Phone: 512.222.5454 • www.restroomfacilities.com
STANDARD TERMS AND CONDITIONS OF SALE
1. LINKAGE:
These Terms and Conditions of Sale shall apply and form a part of the Company's Offer
to Sell and supersede all other expressed or implied terms and be linked to our
Agreement for work whether or not signed by the Purchaser.
2. ACCEPTANCE:
Unless otherwise expressly stated herein, the Company's Offer supersedes all previous
quotations and expires, unless accepted by purchaser, within ten (10) days from date of
Offer. None of the Terms and Conditions contained in this quotation may be added to,
modified, superseded or otherwise altered except by a written instrument signed by the
President of the Company. Each shipment to buyer from the Company shall be deemed
to be only under these Terms and Conditions of Sale, which shall become part of our
Offer to Sell, notwithstanding any Terms and Conditions that may be contained in any
purchase order or other form of the buyer, notwithstanding the shipment, acceptance of
payment or similar act of the Company. All Purchase Orders when accepted by the
Company at 1707 Colt Circle, Marble Falls, Texas 78654, will be in accordance with the
Laws of the State of Texas. All orders are subject to review by the Company in
accordance with the Company's Offer to Sell before final acceptance is authorized. All
disputes shall be governed by applicable Texas Law and all claims shall be filed and
litigated in Burnet County, Texas, with the prevailing party recovering attorney's fees.
3. PRICES:
Initial payment is due no later than 30 days from receipt of invoice. All subsequent
progress payments are due no later than 30 days from receipt of invoice. If payment is
not made by client in accordance with the Contract Terms, interest will be charged at the
rate of 1 -1/2% (one and one/half percent) per month until paid. If an order is accepted
by the Company, and a delivery date is accepted by the Client, and delivery is delayed
by the Client, payment of all but 5% is due upon completion at the Point of Manufacture.
A 2-1/2% (two and one/half percent) per month added fee shall be due for each month
the shipment is delayed. Client shall approve Phase 1 plans and have color selections
chosen and back to RFL no later than 15 days of receiving Phase 1 plans for review and
color selection. If Phase 1 plans are not approved and / or color selections are not
submitted to RFL within 15 days Client will incur a 1.5% fee of total project amount per
month commencing at the 16 day mark. Fee shall continue on a monthly basis until
Phase 1 approvals and /or color selections are received by RFL. If, during the
performance of this contract, the price of construction materials increases, through no
fault of RFL, the price of the contracted building shall be equitably adjusted by an
amount reasonably necessary to cover any such price increase. Such price increases to
the client shall be documented through change orders or invoices. Where the delivery of
contracted buildings is delayed, through no fault of RFL, as a result of material shortage,
Initial Initial Page 5 of 9
1707 Colt Circle, Marble Falls, Texas 78654 • Phone: 512.222.5454 • www.restroomfacilities.com
material unavailability, or shipping regulation changes, RFL shall not be liable for any
additional costs or damages associated with such delays.
4. TERMINATION:
Purchaser shall be responsible for costs of work performed which will include overhead
and profit. Contract may not be canceled once production has commenced.
5. TITLE AND LIEN RIGHTS:
All Products remain the personal property of the Company, whether or not affixed to any
other real property or structure, until the total amount of the contract including any
change orders has been fully paid. The Company shall, in the event of the purchaser's
default, have the right to enter upon any premises and repossess such structures and
equipment wherever it may be located.
6. LACHES:
Failure of the Company to exercise any right or remedy under this contract shall not be
deemed a waiver of such right, nor shall any lien or other right of the Company be lost or
impaired by laches or in any manner or by any act or failure to act.
7. LIMITATION OF LIABILITY:
Under no circumstances, unless stated in our Offer to Sell or bid, shall the Company
have any liability for liquidated damages, for collateral, consequential special damages,
loss of profits, loss of production, delay in the progress of construction, whether resulting
from delays in delivery, performance, breach of warranty, due to lack of timely
performance in reviewing and approving shop drawings, completing site preparation or
lack of payment in accordance with the terms set forth herein. The aggregate total
liability of the Company under the contract, whether for breach of warranty or otherwise
shall in no event exceed the contract price. Buyer agrees to indemnity and holds
harmless the Company from all claims by third parties which extend beyond the
foregoing limitations on the Company's liability.
8. DELIVERY:
Except as may be otherwise specified in the attached Offer, delivery will be F.O.B. point
of manufacture. "The City of Port Arthur shall contact the Vendor when it is ready to
request delivery of the restroom facilities. Upon receipt of the City's request, the Vendor
shall provide the City with an estimated delivery date and time. The delivery date and
time shall be coordinated between the City and the Vendor and confirmed prior to
delivery. No specific delivery date is established or guaranteed under this Proposal unless
and until mutually confirmed by the parties." The Company shall in no event be liable
for delays caused by fires, acts of God, strikes, labor difficulties, acts of Government or
military, delays in transportation or procurement of materials or causes of any kind
beyond the Company's immediate control. If building is ready for shipment and
Initial Initial Page 6 of 9
1707 Colt Circle, Marble Falls,Texas 78654 • Phone: 512.222.5454 • www.restroomfacilities.com
Customer delays said shipment, Company shall store the facility at the point of
manufacturing and charge 2-1/2% (two and one/half percent) per month as a storage
charge. If shipment arrives and site is not ready, Owner shall pay any off-site storage
fees as applicable.
9. WARRANTY:
All structural elements produced by the company are warranted to the purchaser to be
free from defects in material, workmanship and title. The Company will replace or repair,
at its option, defects in workmanship or any part which is proven defective within Twenty
(20) years from delivery. This warranty applies only where the Company has been
notified in writing of the defect within the warranty period and where any equipment has
been properly operated and maintained in accordance with the Company's instructions:
the Company having no responsibility for abuse, neglect, minor leaks in plumbing, or
improper storage. Company shall have no responsibility for improper grading of
concrete or soil around the building that does not allow for proper drainage of water
away from the building. Example: improper drainage of water could cause cracking of
brick, cultured stone, natural stone, cmu, hardie materials, or other types of exterior
finishes, as well as swelling, rot, mold, or mildew of any type of lumber that has
prolonged exposure to water. Typically the final grade must be sloped away from the
foundation by 1/2 inch per foot over a minimum distance of 10 feet (site plans, civil
engineer, or others can and may override the above recommendation, as it is a typical
recommendation and site conditions vary). Keeping the proper slope allows water to
drain away from the foundation. Should any issues arise where additional work must be
performed RFL retains the right to perform this work at the earliest opportunity. Should it
be necessary to have this work performed by others due to the nature of the work or a
conflict in scheduling, RFL must be notified 48 hours in advance in writing and given the
opportunity to perform said work. Should it be necessary to have this work performed by
others a written estimate must be approved by RFL in advance of any work being
undertaken. The Company assigns any and all warranties for fixtures, appliances, and
other equipment manufactured by others to said other manufacturer. Due to its nature,
concrete is prone to settling and cracking. Minor cracking in the concrete is normal and
is not the responsibility of RFL. Checking, warping, twisting, or splits in timbers are
natural occurrences and are not the responsibility of RFL. We use high quality 304
stainless steel in our products and under certain conditions and/or improper
maintenance stainless steel may rust. Minor rust spots or discoloration are not the
responsibility of RFL. The foregoing shall constitute the said liability of the Company and
the sole remedy to the purchaser. Company's warranties as set forth in this paragraph
are exclusive and are in lieu of, and purchaser hereby waives all other warranties,
expressed or implied, including without limitation, any implied warranties or
merchantability and fitness. This warranty shall be void if payment in full for the project
is not received by the Company in accordance with these Terms and Conditions of Sale.
Initial Initial Page 7 of 9
1707 Colt Circle, Marble Falls,Texas 78654 • Phone: 512.222.5454 • www.restroomfacilities.com
10. CREDIT:
(Deposit and Progress Payments)
11. MUNICIPAL AND FEDERAL GOVERNMENT AGENCIES:
Orders may require deposits or progress payments. If buyer's financial situation justifies
such action, the Company may at its election require payment in advance or cancel the
order as to any unshipped item and require payment of its reasonable cancellation
charges. If the buyer delays completion of manufacture or a delay in shipment, the
Company shall require payment according to the percentage of completion. In the event
of the default of the buyer, the Company is entitled to the full amount due including
reasonable attorneys fees, costs, storage, expenses of physical recovery, and interest at
1-1/2% (one and one/half percent) per month.
12. CLIENTS AND NON-GOVERNMENT AGENCIES:
Orders may require deposits or advance payment as well as progress payments subject
to the buyer's creditworthiness in accordance with the Company's applicable credit
policies. Breach of any payment terms shall accelerate full payment which shall be due
the balance of the contract amount including change orders.
Initial Initial Page 8 of 9
1707 Colt Circle, Marble Falls,Texas 78654 • Phone: 512.222.5454 • www.restroomfacilities.com
Restroom Facilities Limited
John Putman, President Date
Client Name
Name and Title Date
Initial Initial Page 9 of 9
1707 Colt Circle, Marble Falls,Texas 78654 • Phone: 512.222.5454 • www.restroomfacilities.com