HomeMy WebLinkAboutPR 15764: AAR INC. CHANGE ORDER 01 FOR ASBESTOS ABATEMENT & DEMOLITION OF 2 BUILDINGS IN SABINE PASS~, ~
To: ' Mayor, City Council, and City Manager
From: Adam J. Saunders
CC:
Date: 2126110
Re: P. R. No. 15764, Council Meeting March 9.2010
Attached is P. R. No. 15764 authorizing the City Manager to execute Change Order 01 to the
contract between the City of Part Arthur and AAR Incorporated .for asbestos abatement and
demolition of two buildings in Sabine Pass, along with the removal of two dead trees. This
change order will increase the contract amount by $3,550.00 to a new total of $17,800.00, said
costs to be paid by Port Arthur for Positive Action.
r
1
P. R. NO. 15764
03/03/10 as/ts
RESOLUTION NO:
A RESOLUTION AUTHORIZING THE CITY MANAGER TO EXECUTE
CHANGE ORDER 01 TO THE CONTRACT BETWEEN THE CITY OF
PORT ARTHUR AND AAR INCORPORATED INCREASING THE
SCOPE AND WORK CONTRACT AMOUNT BY $3,550.00 TO A NEW
TOTAL OF $17,800.00, SAID COSTS TO BE PAID BY-.PORT ARTHUR
FOR POSITIVE ACTION
WHEREAS, on January 26, 2010, the City entered into a contract with AAR
Incorporated for asbestos abatement and demolition of two buildings. in Sabine Pass, along with
the removal of two dead trees, for the amount of $14,250.00; and,
WHEREAS, AAR Incorporated has requested Change Order OI , as delineated in Exhibit
"A" attached hereto, in the amount of $3,550.00; and,
WHEREAS, Pursuant to Section 252.048 (A) of the Local Government Code, Change
Order.No. 1 is being requested to increase the quantity of work to be preformed in order to allow
for the removal of slabs on the site, which was not included in'the original Scope of Work; and
WHEREAS, approval of Change Order No. O1, as delineated in Exhibit "B" attached
hereto, in the amount of $3,550.00, increasing the contract to a new amount of $17,800.00, is'
herein deemed an appropriate action.
NOW THERFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY
OF PORT ARTHUR:
Section 1. THAT, the facts and opinions in the preamble are true and correct.
Section 2. THAT; Change Ordet0l, as delineated in Exhibit"B" attached hereto, is
herein approved and the City Manager is herein authorized to execute said Change Order.
s.pr15764
Section 3. THAT, a copy of the caption of this Resolution be spread upon the
Minutes of the City Council.
READ, ADOPTED, AND APPROVED, this day of
2010, A.D., at a Regular Meeting of the City Council of the City of Port Arthur, Texas by the
following Vote: AYES: Mayor:
Council members:
NOES:
Mayor
ATTEST:
Terri Hanks, City Secretary
A\P~PROVED AS TO FORM:
`~ ~_ .~~
Val Tizeno, rty A to y
APPROVED FOR ADMINISTRATIONr
Steve Fitzgibbons, City Manager
APPROVED AS TO FUND AVAILABILITY
1 ~.,
x
Deborah Echols, Director of Finance
~ ; 1 ~ ,,
Shawna Tubbs, Purchasing Manager
s.pr15764 _
EXIII~IT 6`99
S.pr15764
6640 Signat
kouston, Texas. 77041
Phone (71.3) 466 6800
Fax (713) 466 4234
vwvw.aarinc.net
February 19, 2010
Mr. Adam J. Saunders
Robert A. "Bob° Bowers Civic Center
3401 Cultural Center Dr.
Port Arthur, Texas 77642
Phone (409) 985-8801 •• Email: asaunders a~.oortarthur.net
Re: Demolition of Slabs at Community Building and Vacant Building in Sabine Pass
Change Order # 1
Dear Mr. Saunders:
We are pleased to submit pricing as requested for demolition of slabs on the
above referenced project as follows:
Price Demolition of Slabs - $ 3,550
Scope of work for the Demolition of Slabs includes:
Demolition and proper off-site disposal. of the buildtng'slabs totaling 3,700 sq. ft.
on the above referenced project
Demolition of building slabs, grade beams and building foundations to 2' below
grade
Building site will be graded to drain (if possible) using existing on site materials
Demolition of concrete driveways and sidewalks totaling 1,660 sq. ft.
Demolition of and proper off site disposal of Concrete up to 5": thick
All debris generated will be transported off site and disposed, of properly
All work in compliance with all federal, state and local regulations
Assumptions:
Grading will be accomplished using existing on site materials unless directed by
owner to provide backfill
Electrical, gas and telecommunications service disconnects to be called in by the
owner and performed. by the utility companies
Unencumbered access to the site
Demo Contractor has all salvage rights
Sabine Pass Slabs CO # 1 Page 1 of 2
°Our Business Cleans Up"
Our quotation is based on the following:
NESHAPS and' OSHA approved Demolition Methods ,
$1,000,000 CSL general liability policy
Complete Closeout Documentation
Exclusions:
Electrical, gas, and telecommunications service disconnects
Payment and Performance bonds
Any concealed conditions `
Replacement of materials removed
Specifications, project management orconsultant
Site work or any restoration work except as noted above
Importing any backfill unless directed by owner
If you have any questions regarding this quote, feel free td call me at (713) 466
6800 or by mobile (713) 702-2004.
r
Sincerely .
• Gerardo Alejandro
Gerardo Alejandro
' Project Manager
F '
i
d
Sabine Pass Slabs CO # 1 Page 2 of 2
EXI-II~I'T "~"
a
s. pr15764
CHANGE ORDER NO.Ol
DATE: February 26, 2010
ORIGINAL AGREEMENT DATE: January 26, 2010
AAR INCORPORATED ".
PROJECT DESCRIPTION: Asbestos abatement and demolition of two buildings in Sabine
Pass, along with the removal of two dead trees.
ORIGINAL CONTRACT TERM: ~ 30 days
NEW CONTRACT TERM including the CHANGE ORDER will be: SAME
CHANGE TO CONTRACT AMOUNT:
ORIGINAL CONTRACT AMOUNT: $14;250.00
CONTRACT AMOUNT due to this CHANGE ORDER will be INCREASED
by: $ 3,550.00
NEW CONTRACT AMOUNT including the CHANGE ORDER will be: $17,800.00
AAR INCORPORATED:
Signature
Printed Name
CITY OF PORT ARTHUR:.
Steve Fitzgibbons
City Manager
~.
S.pri5764 ~ ~ ~~