HomeMy WebLinkAboutPR 15847: ALLCO, LTD. CHANGE ORDER FOR MAIN/PORT ACRES WWTP REHABILITATION PROJECTMEMORANDUM CITY OF PORT ARTHUR UTILITY OPERATIONS DEPARTMENT TO: Stephen Fitzgibbons, City Manager FROM: Kelly Eldridge, Director of Utility Operations Jl ~J,j-%J~ DATE: April 14, 2010 ~'"" SUBJECT: Proposed Resolution No. 15847 COMMENTS RECOMMENDATION I recommend that the City Council approve Proposed Resolution No. `15847 authorizing the execution of Change Order No. 1 to the contract between the City and ALLCO, Ltd., related to the Main and Port Acres W WTP Rehabilitation Project, CPA-490, ContractNo. 5. This change order simply deals with changing the Davis-Bacon Labor Classification and Minimum Wage Scale to reflect the trades on this project. This Change Order will not change the contract amount or contract time. BACKGROUND City contracts routinely utilize Davis-Bacon Wage Rates for vazious types of projects. These wage scales vary from project to project, especially for plant-site projects vs. off-site work. Apparently, the scale provided with our bid documents did not reflect all the trades to be used on this project. Our consultant has provided a-new Davis-Bacon Labor Classification and Minimum Wage Scale that does reflect these trade classifications. Being a contractor that routinely works on all types of projects, ALLCO, Ltd. acknowledged the proper wage scale and is not requesting any change in contract amount or time. This is an ARRA grant project that includes substantial rehabilitation and expansion work at our lazgest WWTPs. Change Order No. i simply replaces the original classification and wage scale. BUDGET/FISCAL EFFECT Change Order No. 1 does not change the contract amount or contract time. STAFF/EMPLOYEE EFFECT None. SUMMARY I recommend that the City Council approve Proposed Resolution No. 15847 authorizing execution of Change Order No. 1 to the contract between the City and ALLCO, Ltd., related to the Main and Port Acres WWTP Rehabilitation Project, CPA-490; Contract No. 5. P.R. No. 15847 04/14/10 RESOLUTION NO. A RESOLUTION AUTHORIZING THE EXECUTION OF CHANGE ORDER NO. ONE TO THE CONTRACT RELATED TO THE MAIN AND PORT ACRES WWTP REHABILITATION PROJECT, CPA-490, CONTRACTNO. S. (NO CHANGE IN CONTRACT AMOUNT OR TIME). WHEREAS, the City Council of the City of Port Arthur has awarded the contract for the Main and Port Acres WWTP Rehabilitation Project, CPA-490, Contract No. 5 to ALLCO, Ltd., in Resolution No.09-512; and, WHEREAS, Arceneaux & Gates Consulting Engineers, Inc., as Owner's representafive, has prepared, reviewed, and recommends approval of Change Order No. 1, copy attached hereto and made a part hereof as Exhibit "A", changing the Davis-Bacon Labor Classification and Minimum Wage Scale to reflect the trades on this project; Not changing the contract amount or contract time; NOW THEREFORE, , BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF PORT ARTHUR: THAT, the City Manager be authorized to execute Change Order No. 1 (Exhibit "A") to the referenced contract, changing the Davis-Bacon Labor Classification and Minimum Wage Scale to reflect the trades on this project; and, THAT the total contract amount is NOT CHANGED by this Change Order; and, THAT the contract time is NOT CHANGED by this Change Order; and, THAT no other conditions or covenants of the contract aze changed or waived by this Change Order; and, THAT a copy of the caption of this Resolution be spread upon the Minutes of the City Council. P.R. No. 15847 04/14/10 Page 2 of 2' READ, ADOPTED AND APPROVED THIS day of , 2010 at a Regulaz Meeting of the City Council of the City of Port Arthw, Texas, by the following vote: AYES: Mayor Councihnembers: NOES: ATTEST: Terri Hanks City Secretary APPROVED FOR ADMINISTRATION: Stephen Fitzgibbons City Manager ~~ ~ Ross Blackketter, P.E. Director of Public Works Ke ly El 'dge Director of Utility Operations Deloris Prince Mayor APPROVED AS TO FORM: Gf~C C~ Valecia Tizeno City Attorney EXHIBIT A ARCENEAIIX GATES coxsmrrxac CNGIIPEERI, LPC. Memo Ta Mr. Ross Blackketter, P.E. From: Cahn D. Prosen, P.E. CC: Mr. Kelly Eldrige Project file Dane: April 14, 2010 Email: Fa~c Re: Change Order No. 1 Job: Contad 5, Main & PortAcresWWTP Rehabilitation to serve City of Port Arthur A&G PROJECT NO. CPA490, CONTRACT 5 Attached is the executed change order no. 1 for the Contract 5; Main 8 Port Acres WWTP Rehabilitation project. Arceneaux 8 Gates recommends approval of this change order. This change order is to change the Davis-Bacon Wage Rate from the decision included in the contract documents to the wage rate decision that better reflects the trades on the project. The original wage rate decision did not provided for most of the trades involved in the project. The change to the contract for this change order is $0.00 and no time extension. Please present this change order to the City Council for approval so the Contractor can begin using • these rates in their payroll. After Council approval and execution by the City, please return a copy to Arceneaux 8 Gates for our records and further distribution to the Contractor. If you have any questions, please give us a call. Sincerely, ~c -~op.,t.~-~- Calvin D. Prosen, P.E. Arceneaux & Gates, Consulting Engineers ~i~~~;~ ~.~~r~.s ~or~~ DATE: A~1 1.2010 JGB NO. CPA-4~0, Cor,Lraci No. 5 AGREEP/~NT DATE: December 16 2000 NAME GF PRGJECT: MJain and Pert Acres 1`~h/TP P.ehab*ation is serve tia~ Cirv oz` Pari Arthur G~YNER: CITY OF PGRT ARTHUR f CGNTRACTGR: ALLCO.LTD The ioIlowing changes are hereby n•,aAe to the CGNTP.ACT DGCIPilEN'TS: i, Tit9 ®a~aie~~amnn daixsr CiassiJaca4ivn and ~9inin~cs+~ ~la~t/e ~ai~, i'Xi1801 i7, HeaaryP is ts~ be repiaceri in iFs entirety ~3idi LaY®r Ciassi8i~alicar~ and i+,9initvaisavi V'lage Sale, TX1ljA1®2, FEeavy (98311 2/28 5 0). Gost for change ...........................................................................................................$0.00 ~c~;~~4 c~~~ GGIDiIILTiLG ENGLIcE35, L:G. Cfx ~1PaCE 3'O CO~+IT~CT T'Y3sCE; ~~~~1~~ ~~~~~ r~~, ~ ~~,~a a, zs~~~ ORIGINAL CON'T'RACT PP.TCE: 58 141.753.00 CURRE?dT CONTRAC T PRICE adjusted by previcus Ci-IFd+If'iE OTZDEP.;S j: $8.141,753.00 The CO`dT~ACT PRICE due to this CHANGE ORDER will bz ~ts:~-easy-d} [decrzaszd; by: 50.00 Dollars Thz new CONTP~AC~ PP.TCE, including this CHANGE OP.DER, will be 58.141.753.00 C1=IA1\TGE'r0 COi~iTRACT TIME: ORIGT1dAT, COIVT'T:ACT TIt,RE: 450 Calendar-0avs CURRENT CONTRACT TIME adjusted by previous CHANGE ORDER: 450 Calendar Days CURRENT DATE OF CONIPLETTON: Mtay 5, 2011 CONTRACT TIME due to this CHANGE ORDER will be increased by 0 Days The Ne~.v DATE OF COMPT.ETTON: No other Tzrms and Condittons of tTae Contract are changed as a result of this Change Order. Con~actar's acceptance of Change Order relieves O~JNEP. ai` any i_iability for additional costs incuried by Contractor in his performance of the work ccverzd by the Change Order. REC0IVLVIEiVDED BY ENGINEER: ACCEPTED BY: L-ELJCti,~ FV I n.B~J-,.~ ' ~~r-c(~a ~Go~C~GC.~-mt=~ ARS .~ra7EJAWJIL $ ~AYE~ (fANTRA TOR,OFFICERGROWNEP.] ~~~~~~~r~~ s~s~~er~~s~~~, ass?. ~~,~~~s ~a~, ACCEPTED BY: ~9`P9° 2`s~ $''d3R'~ ~"a~~'~9t9R