HomeMy WebLinkAboutPR 16053: ALLCO, INC., CHANGE ORDER #3 MEMORANDUM CITY OF PORT ARTHUR UTILITY OPERATIONS DEPARTMENT TO: Stephen Fitzgibbons, City Manager FROM: Kelly Eldridge, Director of Utility Operations �C�c , DATE: September 1, 2010 SUBJECT: Proposed Resolution No. 16053 RECOMMENDATION I recommend that the City Council approve Proposed Resolution No. 16053 authorizing the execution of Change Order No. 3 to the contract for the Wastewater Treatment Plant Rehabilitation Project, Contract No. 5, City Project No. 404WWT with ALLCO, Inc., of Beaumont, Texas, in the amount of $151,459. BACKGROUND As a part of the Agreed Judgment between the City and the Texas Attorney General's Office /TCEQ Enforcement Division, we were required to have our WWTP's evaluated for deficiencies that have caused, or may cause, violations of our effluent permit. The subsequent construction project is for the rehabilitation of deficiencies noted during this evaluation inspection of our Main and Port Acres WWTP's. During the award process, it became apparent that the bids were well above ARRA funding, so we deleted several Alternate Bid Items in an effort to get closer to our grant amount. Unfortunately, one of the associated items, the Main WWTP Sludge Thickener, has failed. Many of the minor repairs to the unit remained in the Base Bid, but we deleted an Alternate Bid Item that included some major items that also needed repairs, in hopes of getting funding from another grant source. The center drive mechanism has failed. It appears the 50 year old bearing housing has collapsed, causing the unit to lean and not operate. This unit is basically a 45 foot diameter concrete cylinder, with a conical bottom & center drain that operates by rotating rake arms that pull settled sludge to the center, while clarified water overflows the top and is directed to other treatment units. The center drive provides the rotation. With this unit out of service, we are in violation of out TCEQ permit, and there is no redundant unit. We are making arrangements to remove the rotating mechanism, the bridge to the center drive, and all rotating equipment from the basin in an effort to manually remove sludge from the unit without causing serious operational problems for the rest of the WWTP. Instead of performing the minor repairs included in the Base Bid, we have asked ALLCO, Inc. to provide pricing for replacement of the center pier, bridge, drive, scraper /skimmer, weirs, baffle, etc. The total provided by the contractor includes the new equipment, plus reprioritizes their work to get this unit back in order as soon as possible. That means they will have to make the emergency thickener tank modifications, remove all piping & equipment, and manually clean out our sludge holding lagoon, Allco will have to stop working on all other pay items to complete this priority item. Arceneaux & Gates Consulting Engineers has reviewed this proposal and recommends Change Order No. 3 to complete this work. While ALLCO has not asked for a time extension for this work, the change order includes a 41 day time extension for inclement weather since the start of the project. BUDGET/FISCAL EFFECT We have already committed all of our available ARRA grant funds on current projects. Therefore, we will utilize our existing bond funds that we allocated for this work before the grant became available. STAFF/EMPLOYEE EFFECT City staff and our consulting engineer, Arceneaux & Gates, will continue to oversee this project. SUMMARY I recommend that the City Council approve Proposed Resolution No. 16053 authorizing the execution of Change Order No. 3 to the contract for the Wastewater Treatment Plant Rehabilitation Project, Contract No. 5, City Project No. 404WWT with ALLCO, Inc., of Beaumont, Texas, increasing the contract amount $151,459, and contract time by 41 calendar days due to inclement weather P.R. No. 16053 09 -01 -10 RESOLUTION NO. A RESOLUTION AUTHORIZING THE EXECUTION OF CHANGE ORDER NO. 3 TO THE WASTEWATER TREATMENT PLANT REHABILITATION PROJECT, CONTRACT NO. 5, BETWEEN THE CITY OF PORT ARTHUR AND ALLCO, INC., OF BEAUMONT, TEXAS, INCREASING THE CONTRACT AMOUNT BY $151,459 AND CONTRACT TIME BY 41 CALENDAR DAYS. ACCOUNT NO. 404 -1625- 532.83 -00, CITY PROJECT NO. 404WWT. WHEREAS, the City is currently under an Agreed Judgment with the Texas Attorney General's Office and the TCEQ to rehabilitate its sanitary sewer system; and, WHEREAS, there exists a need to upgrade and rehabilitate our treatment plants in order to bring them into permit compliance; and, WHEREAS, subsequent to the rehabilitation work already initiated, the Main WWTP Sludge Thickener failed; and, WHEREAS, Arceneaux & Gates Consulting Engineers found this additional work is required to meet the requirements of our Agreed Judgement, investigated remedies, and requested a Change Order proposal from our contractor, ALLCO, Inc.; and, WHEREAS, ALLCO, Inc. responded with an acceptable proposal and Arceneaux & Gates Consulting Engineers, Inc. has reviewed the proposal and recommends Change Order No. 3 in the amount of $151,459, increasing the contract amount from $8,513,516 to $8,664,975, and increasing contract time by 41 calendar days due to inclement weather; NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF PORT ARTHUR: THAT the City Council of the City of Port Arthur hereby authorizes the City Manager to execute Change Order No. 3 (copy attached hereto as Exhibit "A ") to the contract for the P.R. No. 1603 09 -01 -10 Page 2 of 3 Wastewater Treatment Plant Rehabilitation Project, Contract No. 5 between the City and ALLCO, Inc., of Beaumont, Texas, increasing the contract amount by $151,459 and the contract time by 41 calendar days; and, THAT, a copy of the caption of this Resolution be spread upon the Minutes of the City Council. READ, ADOPTED AND APPROVED THIS day of 2010 at a Regular Meeting of the City Council of the City of Port Arthur, Texas, by the following vote: AYES: Mayor Councilmembers: NOES: Deloris Prince, Mayor ATTEST: Sherri Bellard Acting City Secretary P.R. No. 16053 09 -01 -10 Page 3 of 3 APPROVED FOR ADM Stephen Fitzgibbons City Manager /, 2 • i Ai; / / , Ross Blackke"er, PE Director of Public Works /4-1 J GG i`1 Kelly El4ridge Director of Utility Operations APPROVED AS TO AVAILABILITY OF FUNDS: / JQId t ,, Deborah Echols Director of Finance Acct. No. 404 - 1625 - 532.83 -00 Project No. 404WWT APPROVED AS TO FORM: dill / CITY ATTORNE EXHIBIT A (Change Order No. 3) ARCENEAUX GATES CONSULTING ENGINEERS, INC. CHANGE ORDER No. 3 DATE: August 30, 2010 JOB NO, CPA -490, Contract No. 5 AGREEMENT DATE: November 13, 2009 NAME OF PROJECT: Main and Port Acres WWTP Rehabilitation to serve the City of Port Arthur OWNER: CITY OF PORT ARTHUR CONTRACTOR: ALLCO, LTD. The following changes are hereby made to the CONTRACT DOCUMENTS: 1. Add Complete Rehabilitation of Main WWTP Sludge Thickener to the project. Rehabilitate the Existing Sludge Thickener including ALL NEW thickener equipment including center pier, bridge, drive, scrapper /skimmer, weirs, baffles, etc. in lieu of limited rehabilitation in Scope of Work Item 3.1.13 (in Base Bid). Including emergency thickener tank modifications, sludge holding pond cleaning, sludge pumping, equipment removal, piping, etc. to get the basin operational following equipment failure. $ 151,459.00 SUBTOTAL ITEM 1 $ 151,459.00 2. Additional time for weather delays — Forty -one (41) Calendar Days. Authorize time extension for weather days including seven (7) calendar days for February 2010; twelve (12) calendar days for March 2010; five (5) calendar days for June 2010; and, seventeen (17) calendar days for July 2010. $ 0.00 SUBTOTAL ITEM 2 $ 0.00 TOTAL $ 151,459.00 CHANGE ORDER NO. 3 ® August 30, 2010 ARCENEAUX Job No. CPA -490, Contract No. 5 GATES CONSULTING ENGINEERS, INC. CHANGE TO CONTRACT PRICE: ORIGINAL CONTRACT PRICE: $8,141,753.00 CURRENT CONTRACT PRICE adjusted by previous CHANGE ORDERS ): $8,513,516.00 The CONTRACT PRICE due to this CHANGE ORDER will be [increased] {dccrccd} by: $151 ,459.00 Dollars The new CONTRACT PRICE, including this CHANGE ORDER, will be $8,664,975.00 CHANGE TO CONTRACT TIME: ORIGINAL CONTRACT TIME: 450 Calendar Days CURRENT CONTRACT TIME adjusted by previous CHANGE ORDER: 515 Calendar Days CURRENT DATE OF COMPLETION: July 9, 2011 CONTRACT TIME due to this CHANGE ORDER will be increased by 41 Days The New DATE OF COMPLETION: August 19, 2011 No other Terms and Conditions of the Contract are changed as a result of this Change Order. Contractor's acceptance of Change Order relieves OWNER of any liability for additional costs incurred by Contractor in his performance of the work covered by the Change Order. RECOMMENDED BY ENGINEER: ACCEPTED BY: ARCENEAUX & GATES [CONTRACTOR, OFFICER OR OWNER] CONSULTING ENGINEERS, INC. ALLCO, Ltd. ACCEPTED BY CITY OF PORT ARTHUR AUG, 30. 2010 11:5i)AM Al 1 co Inc. 409 - 3357 NO. 4579 P. 1 ALIC0 DESIGN BUILD CONSTRUCTION MANAGEMENT GENERAL CONTRACTOR p 0. Box 3684, Beaumont, Texas 77704 Phone: 409 - 8604459 Fax: 409 - 860.3867 Email: allco @allco.com I August 30, 2010 Arceneaux & Gates Consulting Engineers 3501 Turtle Creek Drive, Suite 102 Port Arthur, Tcxas 77642 Attn: Calvin Prosen 1 Re: City of Port Arthur Main Wastewater Treatment Plants Section 3.1,13 — Sludge Thickener Rehab Our Job No. TX -646 . Dear Mr. Prosen: Attached is our Request for Change Order to replace all of the equipment for the Sludge Thickener ai the Main Wastewater Treatment Plant for the City of Port Arthur, for the sum of ONE HUNDREU1 FIFTY ONE THOUSAND FOUR HUNDRED FIFTY NINE DOLLARS ($151,459.00). The backup is attached, If you have any questions concerning this matter, please feel free to call the undersigned. Very truly yours, ALLCO Billy Patterson attachments AUG. 30. 2010 11:50AM Al l co Inc. 409 -860 -3851 NO. 4579 P. 2 ALLUU 1NG. ;ti rib 4f V , _4fiTrikf: 9::iX )' Vi'; c °• 4 1;iIs , °} m 9 ummu •'-'S 8126/2010 ALTS ATE BID 3 A 22 1451 ;a BILLY PATERSON i a;R'E ' l ilitt1M i.'0 10:4 APS �' v ;w�� ? _ ".act y ii_,f��;st ° f3 '1a� i 1'4'ti��lc�,l;w 7 r + P �ti; - ,a '^'M'S45e .' ja s x;' , A ;y: ?3;! �,: IA �3`' d ic �, t ., ° I, . •f ' $V •11 .,0T ' uu5 r [ cnpy¢ _ ��q�ry .., :,, ,ht `�� , �V ; & 1 .. _ Y 11IU ; s A :i& R1r�T' .' C{[9YS GL�4}: 161T.1WfIFR;l.�dl.+ AL Limtitimaugml 0 0 0 REHABILITATE THE EXISTING 0 0 0 SLUDGE THICKENER INCLUDING 0 0 j 0 ALL NEW THICKENER EQUIP - I 0 0 0 MENT INCLUDING CENTER PIER 0 0 0 BRIDGE DRIVE, SCRAPPER/ 0 0 i 0 SKIMMER ,WEIRS, BAFFLES, 0 0 I 0 ETC, IN LIEU OF REHABILITA- 0 0 0 TION AS INDICATED IN SCOPE 0 0 ! 0 OF WORK ITEM 3,1.13, ALL IN 0 0 0 STRICT ACCORDANCE WITH 0 0 0 THE PLANS AND SPECIFICA- 0 0 0 FOR 0 0 0 0 0 0 Replace existing stilling well 0 0 I 0 0 0 0 3 man crew 60,0 MH 48.00 2880 0 0 0 0 0 0 0 Remove drive and replace 0 0 0 ; 0 with new drive 0 0 0 0 0 0 3 man crew 80.0 MH 48.00 3840 0 0 0 0 0 0 0 Replace effluent weir 141.0 LF 0 0 0 0 0 0 0 0 3 man crew 80,0 MH 48.00 3840 0 0 0 0 0 0 I 0 1/2" x 6" s.s, cinch anchors 98.0 EA 0 4,50 432 0 0 0 0 0 0 THCCKNER EQUIPMENT 1.0 LS 0 120990.00 120990 0 0 0 0 0 0 0 0 0 0 0 0 0 0 ' �.. : N- :. . , i ., x . ; .. '.:'4 .. 'c7�i: .: ° .... .. - ! 3 . v: : ���?3 E r Y t , 'Kn r .? ; 0 :Y . , fi!tx- Ir. U..a' ,, i`i ✓ te'; .:. �i ,;j� 'Yn.h ��' =. �'.1aii��F .,, t , :.k•(K -. , ,. , �� t'�`' 1 �' �:. j . . ... . TOTAL ITEM C • STS $10,560 $121422 $0 ' ` ' $0 � ..', ''. �7 . 4 fAgz' n. p / y , , :1`!�dJ}i l 7,,: l,- c. ,, _,,..t t X:,,;6 ,..fs.�_ I 'A';7' u 1�1F 7 {s� c. : ;: o 1 ;'n !': . . ',e n':,,'.' ., 50 HR WK 3,698 `A TAX 14256 SA T 0 14,256 0 0 TAX &INS 4,582 18,818 140,240 MARKUP 11219 151,499 . AUG. 30. 2010 11:50AM Al 1 co Inc. 409 -3600 -3857 NO. 4579 P. 3 ill J Ly '4r 11«: L 'J JiiM 4,.'S e lb b - 11) .._.________-- AUG Z 5 2010 Environmental Treatment Technologies, Inc. August 21, 2010 Mr. Hilly Patterson Alico, Inc. P. O. Box 3884 Beaumont, Texas 77704 Reference: City of Port Arthur, Texas - Main Plant Wastewater Treatment Plant Improvements Gravity Sludge Thickener Dear Billy: r We have had numerous conversations with Calvin Prosen and Enviroquip, Inc concerning the possibility of eliminating some of the scope of supply for the existing Gravity Sludge Thickener and thus reducing the cost of the Proposed Change Order for the Gravity Sludge Thickener., Calvin has pointed out to us that upon removal of the existing gravity sludge thickener mechanism, there are several components that may be reutilized in the final arrangement that would be acceptable to the Engineer and hopefully acceptable to the City of Port Arthur, Texas. We are please to propose the following for your consideration. 1. We will provide the following as new items, which shall be supplied as hop dip galvanized, and delivered to the jobsite. a, One New Access Bridge complete with galvanized steel grating and i aluminum handrails and drive platform to accept the new drive assembly provided in the base bid amount previously authorized in your Purchase Order No. 006162. I b. One New Center Pier to support the new drive gear arrangement. c, One New Drive Cage Assemb! for attachment to the new drive ear 9 Assembly gear arrangement and to rotate the sludge collections arms, d. Two New Sludge Collection Arms for attachment to the new drive cage I assembly. New Sludge Collection Arms to be complete with New Sludge Plows and Squeegees. Representing Ma nufa c turer s of Water and Wastewater Treatment Equipment 17226 Northshare Drive Montgomery, Texas 7735fi Phone; 936- 448 -6520, FAX; 936 -448 -6523 Austin Houston AUG. 30. 2010 11:51AMI AI lco Inc. 409 - 860 N0,4579 e. All New Required Fasteners, and Drill -In Anchor Bolts, for the items listed above (a thru d) plus the new drive assembly. 2. We will incorporate the following existing items into the proposed arrangement: a. The existing stainless steel influent well will be re- utilized and we will provide attachment to the New Access Bridge. (NOTE: The Influent Well does not rotate and is utilized to support one end of the side feed: arrangement Influent Feed Pipe.)' The existing Influent Well has a special fitting for the distribution of the side feed which will be re- utilized. b. The existing stainless steel ninety degree V -notch weirs will be re- utilized. (NOTE: These weirs are thicker than normal weir plates and sealing them against the existing reinforced concrete wall will be the responsibility of Allco, Inc.) c. The side feed Influent Pipe shall be the responsibility of AlIco, Inc., and shall not be provided by ETT. The side feed Influent Pipe must span between the existing wall pipe connection and the inlet connection on the existing influent feed well. (NOTE: The existing side inlet influent feed' pipe may be approved for re- utilization by the Engineer and the City of Port Arthur.) The net cost reduction for re- utilizing the existing items mentioned above is $ 35,000.00. To keep this paperwork as simple as possible, we proposed to delete the cost reduction shown' above completely from the original ADDER AMOUNT OF $ 155,990.00, Thus the new REVISED ADDER AMOUNT WOULD BE $ 120,990.00, The net cost to Allco, Inc., would be the same, although the savings are technically attributable to the Base Bid Item, Ve truly yours, ( 3 0. Peter J. Cze ki, -4- sident • ! • Environmental Treatment Technologies, Inc. • • 1 REQUEST FOR EXTENSION OF TIME DUE TO WEATIIER OR SUPPLIES CITY OF PORT ARTHUR DATE: August 13_, 2010 MONTH OF: ale ru , 2010 CITY of PORT ARTHUR, TEXAS WATER UTILITIES DEPARTMENT P.O. BOX 1089 CITY of PORT ARTHUR, TEXAS 77641 -1089 ATTENTION: Kelly Eldridge. Director of Water Utilities Gentlemen: We request extension of completion time on our Contract due to the days of work lost as specified (list dates actually lost: do not include days not normally worked such as Saturdays, Sundays, or holidays): Dates Lost: 02/11/10, 02/12/10, 02/14/10, 02/15/10, 02/26/10 Days Lost (5) / 5 x 7= 7 Calendar Days Requested Reasons for Request: Delays due to inclimate weather and unworkable site conditions C. ac o�� By: Approved for extension of calendar days. Disapproved. Date: , 20 CITY OF CITY OF PORT ARTHUR, TEXAS BY: City Manager pistribution by City Original: Water Utilities Department xc: Engineer Contractor CPA Federally Funded REQUEST FOR EXTENSION OF TIME DUE TO WEATHER OR SUPPLIES CITY OF PORT ARTHUR DATE: August 13_, 2011 MONTH OF: March , 2010 CITY of PORT ARTHUR, TEXAS WATER UTILITIES DEPARTMENT P.O. BOX 1089 CITY of PORT ARTHUR, TEXAS 77641 -1089 ATTENTION: Kelly Eldridge. Director of Water Utilities Gentlemen: We request extension of completion time on our Contract due to the days of work lost as specified (list dates actually lost: do not include days not normally worked such as Saturdays, Sundays, or holidays): Dates Lost: 03/01/10, 03/02/10, 03/08/10, 03/09/10, 03/10/10.. 03/16/10, 03/17/10 03/25/10 Days Lost ( / 5 x 7 = 12 Calendar Days Requested Reasons for Request: Delays due to inclimate weather, unworkable site conditions, and flow issues to the Main Plant. Con : • Alle .411rAle mi Y Approved for extension of calendar days. Disapproved. Date: , 20 CITY OF CITY OF PORT ARTHUR, TEXAS BY: City Manager Distribution by City Original: Water Utilities Department xc: Engineer Contractor CPA Federally Funded REQUEST FOR EXTENSION OF TIME DUE TO WEATHER OR SUPPLIES CITY OF PORT ARTHUR DATE: August 13 , 2010 MONTH OF: _June_, 2010 CITY of PORT ARTHUR, TEXAS WATER UTILITIES DEPARTMENT P.O. BOX 1089 CITY of PORT ARTHUR, TEXAS 77641 -1089 ATTENTION: Kelly Eldridge. Director of Water Utilities Gentlemen: We request extension of completion time on our Contract due to the days of work lost as specified (list dates actually lost: do not include days not normally worked such as Saturdays, Sundays, or holidays): Dates Lost: 06/01 /10, 06/28/10.06/30/10 Days Lost (I) / 5 x 7 = 5 Calendar Days Requested Reasons for Request: pelays due to inclimate weather. unworkable site conditions. and flow issues to the Main Plant. Contracto .4 By: li rr i Approved for extension of calendar days. Disapproved. Date: , 20 CITY OF CITY OF PORT ARTHUR, TEXAS BY: City Manager Distribution by City Original: Water Utilities Department xc: Engineer Contractor CPA Federally Funded REQUEST FOR EXTENSION OF TIME DUE TO WEATHER OR SUPPLIES CITY OF PORT ARTHUR DATE: August 13_, 2010 MONTH OF: _ JuLi , 2010 CITY of PORT ARTHUR, TEXAS WATER UTILITIES DEPARTMENT P.O. BOX 1089 CITY of PORT ARTHUR, TEXAS 77641 -1089 ATTENTION: Kelly Eldridge. Director of Water Utilities Gentlemen: We request extension of completion time on our Contract due to the days of work lost as specified (list dates actually lost: do not include days not normally worked such as Saturdays, Sundays, or holidays): Dates Lost: 07/02/10, 07/08/10, 07/09/10, 07/19/10.07/20/10, 07/21/10, 07/22/10, 07/23/ 11 07/26 /10.07/27/10, 07/28/1 Q. 07/29/10 Days Lost (12) / 5 x 7 = 17 Calendar Days Requested Reasons for Request: Delays due to inclunate weather, unworkable site conditions. and flow issues to the Main Plant. Contractor By: Approved for extension of calendar days. Disapproved. Date: , 20 CITY OF CITY OF PORT ARTHUR, TEXAS BY: City Manager Distribution by City Original: Water Utilities Department xc: Engineer Contractor CPA Federally Funded