HomeMy WebLinkAboutPR13002:ALLCO CHANGE ORDER #2 MEMORANDUM
CITY OF PORT ARTHUR
UTILITY OPERATIONS DEPARTMENT
TO:
FROM:
DATE:
SUBJECT:
Steve Fitzgibbons, City Manager
Kelly Eldridge, Director of Utility Operations
March 10, 2005
Proposed Resolution No. 13002
COMMENTS
RECOMMENDATION
I recommend that the City Council approve Proposed Resolution No. 13002 authorizing the
execution of Change Order No. Two to the contract between the City and ALLCO. Ltd.. related to
the Wastewater Rehabilitation Project. This change order decreases the total contract amount by
$586.99 to $9,479,532.96, and increases contract time by 38 calendar days.
BACKGROUND
In February 2004, the City Council awarded a construction contract to ALLCO, Ltd. for the
Wastewater Rehabilitation Project, Pioneer Park and Griffing Park areas. This project is part of
Phase I of the City's wastewater system improvements program. It includes the replacement of 25+
miles of the City's sewer lines identified in the Sanitary Sewer Evaluation Survey. Change Order No.
Two deletes the sewer line between Avenue B and 4th Ave. from this contract due to the lack of
easement on the 4th Ave. side. All other properties in this area have 5 to 10 foot easements along the
rear of each lot. The 5-foot easement on the Avenue B side is not sufficient to replace this line
without significantly encroaching on private property. This change order also adjusts certain pipe
bursting bid quantities on the bid form to match those sho,am on the contract plans. The bid form
shows approximately 11,000 LF of 6" HDPE pipe, when the plans show these segments to be 8"
HDPE pipe. We will for~vard this change order to the TWDB upon execution and anticipate their
approval.
BUDGET/FISCAL EFFECT
Change Order No. Two decreases the contract amount by $586.99 to $9,479.532.96.
STAFF/EMPLOYEE EFFECT
No anticipated effect on staffing. City staff will continue to monitor the progress of this project.
SUMMARY
I recommend that the City Council approve Proposed Resolution No. 13002 author/zing execution
of Chang~ Order No. Two to the contract with ALLCO, Ltd.
/aw
P.R. No. 13002
02/22/05 ~aw
RESOLUTION NO.
A RESOLUTION APPROVING CHANGE ORDER NO. TWO TO THE
CONTRACT BETWEEN THE CITY OF PORT ARTHUR AND ALLCO, LTD,
RELATED TO THE WASTEWATER REHABILITATION PROJECT.
(DECREASES THE CONTRACT AMOUNT BY $586.99 AND INCREASES
CONTRACT TIME BY 38 CALENDAR DAYS) ACCOUNT NO. 426-1625-
532.83-00. PROJECT NO. 426ALL.
WHEREAS, the City Council of the City' of Port Arthur has awarded the contract for the
Pioneer Park Area and Griffing Park Area Wastewater Rehabilitation Project to ALLCO, Ltd., in
Resolution No.04-038; and,
WHEREAS, Bob Shaw Consulting Engineers, Inc., as Owner's representative, has reviewed
and reconunends approval of Change Order No. Two. copy attached hereto and made a part hereof
as Exhibit "A", deleting one line segment and adjusting bid quantities for HDPE pipe included in
original project bid; decreasing contract amount by $586.99, and increasing contract time by 38
calendar days; NOW THEREFORE,
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF PORT ARTHUR:
THAT, the City Manager be authorized to execute Change Order No. Two (Exhibit A) to
the referenced contract, in the total amount of $(586.99); and,
THAT the total contract amount to be adjusted will be from Nine Million Four Hundred
Eighty. Thousand One Hundred Nineteen and 95i100 Dollars ($9,480,119.95) to Nine Million Four
Hundred Seventy-nine Thousand Five Hundred Thirty-two and 96/100 Dollars ($9,479,532.96); and,
THAT the contract time will be increased by a total of 38 calendar days; and,
THAT no other conditions or covenants of the contract are changed or waived by these
Change Orders; and,
P.R. No. 13002
02/22/05/aw
Page 2 of 2
THAT a copy of the caption of this Resolution be spread upon the Minutes of the City Council.
READ, ADOPTED AND APPROVED THIS __ day of ,2005
at a Regular Meeting of the City Council of the City of Port Arthur, Texas. by the following vote:
AYES: Mayor :
Councilmembers:
NOES: "
ATTEST:
Oscar G. Ortiz
Mayor
Evangeline Green
Ci~ Secretary
APPROVED AS TO FORM:
Mark Sokolow
CiD' Attorney
APPROVED FOR ADMINISTRATION:
Steve Fitzgibbons Kelly El~ridg~ --'o'
CiD' Manager Director of Utility Operations
APPROVED AS TO AVAILABILITY OF FUNDS:
Rebeccfi Underhill
Director of Finance
Account No. 426-1625-532.83-00, Project No. 426ALL
· - EXHIBIT A
CHANGE ORDER NO. 2
PAGE 1 OF 2
DATE: January 18, 2005
AGREEMENT DATE: March 10, 2004
NAME OF PROJECT: Wastewater Collection System Rehabilitation Griffing Park and Pioneer Park Areas
OWNER: City of Port Arthur, Texas
CONTRACTOR: AIIco, Ltd.
The following changes are hereby made to the CONTRACT DOCUMENTS:
Add 11,000 L.F. of~8" HDPE SDR17 Pipe Bursting
Delete 11,000 L.idl of 6" HDPE SDR17 Pipe Bursting
Add 38 Consecutive Calendar Days
Delete Line PP-5 (See Attached Cost Breakdown)
CHANGE TO CONTRACT PRICE:
ORIGINAL CONTRACT PRICE: $9,203,324.7'1
CURRENT CONTRACT PRICE adjusted by previous CHANGE ORDER: $9,480,119.95
The CONTRACT PRICE due to this CHANGE ORDER will be decreased by: $586.99
The new CONTRACT PRICE including this CHANGE ORDER will be $9,479,532.96
CHANGE TO CONTRACT TIME:
ORIGINAL CONTRACT TIME: 800 Consecutive Calendar Days
CURRENT CONTRACT TIME adjusted by pre~ious CHANGE ORDER: 920
CURRENT DATE OF COMPLETION: November 8, 2006
CONTRACT TIME due to this CHANGE ORDER will be increased by: 38 Calendar Days
New CONTRACT TIME including this CHANGE ORDER will be 958 calendar days
The DATE FOR COMPLETION of all work will be December 16, 2006.
DATE: January 18, 2005
CHANGE ORDER NO.: 2
NAME OF PROJECT: Wastewater Collection System Rehabilitation
Griffing Park and Pioneer Park Areas
PAGE 2 OF 2
No other Terms and Conditions of the Contract are changed as a result of this Change Order.
Contractor's acceptance of Change Order relieves City of any liability for additional costs incurred
by Contractor in his oerformance of the work covered by the Change Order.
RECOMMENDED BY:
Bob Shaw Consulting Engineers
REQUESTED BY:
AIIco. Ltd
CONTRACTOR OFFICER, (~R OWNER
ATTEST FDR CONTRACTOR
C-ORPORATC--S EAL
ORDERED BY:
ACCEPTED BY:
CITY OF PORT ARTHUR
CITY OF PORT ARTHUR, MAYOR
CITY OFPORTARTHUR. MANAGER
CITY SECRETARY
CITY SEAL
CITY ATTORNEY
APPROVED AS TO FORM
CItY OF PORT ARTHUR SANITARY SEWER REHABILITATION
PIONEER PARK ARffA LINE PP-5
ITEM CONTRACT DELETED
NO. ITEM DESCRIPTION QUANTITY UNiT QUANTITY UNIT COST TOTAL AMOUNT
1 8" PVC SDR-26 0'-5' 13,520 LF 367 $3663 $13,44321
2 8"PVCSDR*265'-10' 14,149 LF 851 $3663 $31,17213
3 10"PVCSDR-260'*5' 100 LF $3929 $00u
4 10" PVC SDR-26 5'-10' 100 LF $3929 $0.0u
5 12" PVC SDR-26 5'-10' 925 LF $47.41 $0.0U
6 15" PVC SDR-26 5'-10' 780 LF $47.47 S0.0U
7 8" PVC SDR-28 0'-5' UNDER PAVEMENT 13,909 LF 14 $37.06 $518.84
8 8" PVC SDR-26 5'-10' UNDER PAVEMENT 24,606 LF 46 $39,04 $1 79584
9 10" PVC SDR-26 0'*5' UNDER PAVEMENT 100 LF $40,43
10 10" PVC SDR-26 5'-10' UNDER PAVEMENT 2,615 LF $4241
11 12" PVC SDR-26 5'-10' UNDER PAVEMENT 320 LF $47.53 $000
12 15" PVC SDR-26 5'-10' UNDER PAVEMENT 780 LF $48.50 $0.0u
13 8" PVC SDR-26 C1160 HORIZONTAL BORE 100 LF $21.78 $00u
14 10" PVC SDR-26 C1160 HORIZONTAL BORE 100 LF $27,36 $00U
15 i12'PvcsDR-26CI160HORIZONTALBORE 100 LF $31,18 $00u
16 15" PVC SDR-26 C1160 HORIZONTAL BORE 100 LF $36,37 $00U
17 Y' HDPB SDR17 PIPE BURSTING 11,000 LF $29.15 $0.0tJ
18 "HDPB SDR17 PIPE BURSTING 7,000 LF $3315 $0.0U
19 10" HDPB SDR17 PIPE BURSTING ¢ 400 LF $35,90 $0.0u
20 12"'HDPE SDR17 PIPE BURSTING 400 LF $38.90
21 Concrete Box for STORM SEW. W/8" DI PIPE 1 EA $7,000.00 $0.OtJ
22 ¢' Service in street NEAR SIDE 584 EA $337.40 S0.0u
23 ¢" Service in street FAR SIDE 589 EA $523.80 S00C
24 ¢" Service IN ALLEY 628 EA 36 $281.00 $10,119.0(.
25 Remove & Replace Manhole 199 EA 2 $1,888.00 $37760~.
26 Remove Manhole 37 EA 2 S250.00 $500.bu
27 New Manhole 17 EA 2 S1,772.00 $3,544.0t,
28 Cleanout 55 EA 3 $300,00 $900.bL
29 Cleanout, Under Pavement 56 EA $882.00
30 9" & 10" DROP CONNECTION 48 EA $498.00 $00t
31 Remove & Replace 1-1/2"Asphalt 19,530 SY 26 $17.00 $442.06
32 Remove & Replace Concrete 6" to 8" thick 1,330 SY $60.00 $0.0t
33 Saw Cut Asphalt 52,249 LF 120 $1.25 $1500£
34 Saw Cut Concrete 2,650 LF $1.5C $0.0¢
35 Remove & Replace 10" to 24" RCP culverts 1,415 LF $25.26 $00(
36 Trench Safety 44,106 LF 897 $0.01 $8.~/
37 Design Trench Safety LS $500.06 $0.0£
38 Cement Stabilized Sand 3,017 CY $20.0~; $0.0£
39 ;rushed Limestone 18,006 TON $20.06 S0.0£
40 60/40 Fitl 2,00£ CY $6.06 S0.00
41 Sod Replacement 7,006 SF $25C S0,0C
42 ;hain Link Fence Remove & Replace PRIVATE 50C LF $t5.0C
43 Wood Fence Remove & Replace PRIVATE 50C LF $25.0C $00(
44 Brick Fence Remove & Replace PRIVATE 10C LF $75.0C $0
45 Chain Link Fence Remove CITY 10,29C LF $1.7~ $0.0(
46 Wood Fence Remove CITY 10,29C LF $2.0C $00(
47 Brick Fence Remove CITY 10C LF $110C $0 0(
TOTAL $66,366.9-¢
..... ITEMS TO BE DELETED VIA CHANGE ORDER