HomeMy WebLinkAbout(05) TRAFFIC SIGNAL STUDY CITY OF PORT ARTHUR, TEXAS
PUBLIC WORKS DEPARTMENT
MEMORANDUM:
FROM: .John A. Comeaux, P. E., Director of Public Works
DATE: May 20, 2005
SUB3ECT: West Port Arthur Road and Hwy 365 Traffic Signal
For you information. Janet Manley, TxDOT Traffic Engineer, reported today that
TxDOT has completed a warrant study on subject location and determined that a
traffic signal is warranted. John Barton, TxDOT District Engineer, has approved the
installation.
A funding request will be submitted to _IOHRTS for CMAQ funding at their next
meeting in June. The project will then be ranked along with other projects for
TxDOT funding. When funding is approved, TxDOT will install the signal and the
City will be responsible for maintenance.
The estimated time period for approvals, contracting and installation is twelve
months.
Tf additional information is needed, please let me know.
cc: Ross Blackketter
Dale Watson