HomeMy WebLinkAboutPR 16727: EXECUTE CHANGE ORDER 1 TO CONTRACT WITH PLACO, LTD FOR PLEASURE ISLAND WWTP DIVERSION LIFT STATION PROJECT PUBLIC WORKS DEPARTMENT
COUNCIL ACTION MEMO
TO Stephen B. Fitzgibbons, City Manager
FROM Ross E. Blackketter, P.E., Director of Public Works
SUBJECT P.R. #16727 — CO -01— Placo for Pleasure Island WWTP Diversion Lift Station
DATE 06 October 2011
RECOMMENDATION:
I recommend that the City Council approve Proposed Resolution No. 16727, authorizing Change
Order 01 to the contract with Placo, Ltd. for the Pleasure Island WWTP Diversion Lift Station
project, decreasing the contract by the amount of $5,096.94 to a total of $278,827.55.
BACKGROUND:
The City Council previously executed a contract with Placo for the Pleasure Island WWTP
Diversion Lift Station project. Change Order 01, in the amount of $5,096.94, is for a revised
scope of work that is resulting in some cost savings. The project engineer, Arceneaux & Gates
Consulting Engineers, Inc., has reviewed the request, and recommends approval. In addition,
the Texas General Land Office, the agency administering this grant, now requires that the City
approve this change prior to their review and approval.
BUDGETARY /FISCAL EFFECT: •
Funds are available in the grant project ORPLEA, 141- 1201 - 532.59 -00.
EMPLOYEE /STAFF EFFECT:
None.
SUMMARY
I recommend that the City Council approve Proposed Resolution No. 16727, authorizing Change
Order 01 to the contract with Placo, Ltd. for the Pleasure Island WWTP Diversion Lift Station
project, decreasing the contract by the amount of $5,096.94 to a total of $278,827.55.
4‘e
Ross E. Blackketter, P.E.
Director of Public Works
REB /reb
S: \engineer \Documents \Cams\ Placo- PIDivLS— CO1.docc
P.R. 16727
10/06/11 reb
RESOLUTION NO.
A RESOLUTION AUTHORIZING THE CITY MANAGER TO EXECUTE
CHANGE ORDER 01 TO THE CONTRACT BETWEEN THE CITY OF
PORT ARTHUR AND PLACO, LTD. FOR THE PLEASURE ISLAND
WWTP DIVERSION LIFT STATION PROJECT, DECREASING THE
CONTRACT AMOUNT BY $5,096.94 TO A TOTAL OF $278,827.55.
ORPLEA, 141 - 1201 - 532.59 -00.
WHEREAS, in Resolution 11 -102, the City entered into a contract with Placo,
Ltd. for The Pleasure Island WWTP Diversion Lift Station project in the amount of
$283,924A9; and,
WHEREAS, Placo has requested Change Order 01 in the amount of a decrease
of $5,096.94, attached hereto as Exhibit "A" for a revised scope of work that is resulting
in some cost savings; and,
WHEREAS, this change must be approved by the City Council prior to review
and approval by the Texas General Land Office (GLO), the grant administrator; and,
WHEREAS, approval of Change Order 01 in the amount of $5,096.94,
decreasing the contract to a new total amount of $278,827.55, is herein deemed an
appropriate action; now, therefore,
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF PORT
ARTHUR:
THAT, the facts and opinions in the preamble are true and correct; and,
THAT, Change Order 01 is herein approved and the City Manager is authorized
to execute said Change Order; and,
P.R. 16727
Page 2
THAT, a copy of the caption of this Resolution be spread upon the Minutes of
the City Council.
READ, ADOPTED AND APPROVED this the day of , A.D. 2011
at a meeting of the City of Port Arthur, Texas by the following vote:
Ayes: Mayor:
Councilmembers:
Noes:
Mayor
Attest:
City Secretary
APPROVED AS TO FORM:
//AC 7
City Attor
P.R. 16727
Page 3
APPROVED FOR ADMINISTRATION:
d)—(1
Stephen B. Fitzgibbons Shawna Tubbs, CPPB
City Manager Purchasing Manager
/0 oo�A
Ross E. Blackketter, P.E.
Director of Public Works
APPROVED AS TO AVAILABILITY OF FUNDS:
/66,1V40#4
Deborah Echols, CPA
Director of Finance
Z: \ engineer\ Documents \ResolutionsWR16727.doc
EXHIBIT A
ARCENEAUX
GATES
CONSULTING
ENomss.s,
CHANGE ORDER No. 1
DATE: September 21, 2011 JOB NO. CPA -490 -3
AGREEMENT DATE: March 22. 2011
NAME OF PROJECT: PLEASURE ISLAND WWTP DIVERSION LIFT STATION
OWNER: City of Port Arthur
CONTRACTOR: PLACO, LTD.
The following changes are hereby made to the CONTRACT DOCUMENTS:
1. Modify the following Bid Items to the Contract and Scope of Work:
a. Delete Bid Item 5, GrasstoneTm II
($86.87/S.Y.) [ -] $ 13,899.20
b. Delete Bid Item 6, 6" Flexible Base Grade 3 Type "A"
($172.71/S.Y.) [ -] $ 4,317.75
2. Add the following Items to the Contract and Scope of Work:
a. 185 S.Y. 6 -Inch Reinforced Concrete
($53.75/S.Y) [+1 $ 9,943.75
b. 20 L.F. 18 -Inch Reinforced Concrete Pipe
($675.00/L.F.) [ +] $ 1.733.00
c. 2 EA. 18 -Inch Concrete Safety End Treatment
($721.63/EA.)
[ +1 $ 1,443.26
TOTAL $ (5,096.94)
RECEIVED
SEP 2 62011
PUBLIC WORKS
Admin. - City Hall
CHANGE ORDER NO. 1
® September 21, 2011
ARCENEAUX Job No. CPA -490, Contract No. 3
GATES
CONSULTING
ENOIIQffitS, INC.
CHANGE TO CONTRACT PRICE:
ORIGINAL CONTRACT PRICE: $283.924.49
CURRENT CONTRACT PRICE adjusted by previous CHANGE ORDER(S): $283,924.49
The CONTRACT PRICE due to this CHANGE ORDER will be {ira;reased} [decreased]
by: 5.096.94 Dollars
The new CONTRACT PRICE, including this CHANGE ORDER, will be $278,827.55
CHANGE TO CONTRACT TIME:
ORIGINAL CONTRACT TIME: 180 Calendar Days
CURRENT CONTRACT TIME adjusted by previous CHANGE ORDER: 180 Calendar Days
CURRENT DATE OF COMPLETION: October 28. 2011
CONTRACT TIME due to this CHANGE ORDER will be increased by 0 Days
The New DATE OF COMPLETION: October 28. 2011
No other Terms and Conditions of the Contract are changed as a result of this Change Order.
Contractor's acceptance of Change Order relieves OWNER of any liability for additional costs
incurred by Contractor in his performance of the work covered by the Change Order.
RECOMMENDED BY ENGINEER: ACCEPTED BY:
€ %
ARCENEAUX & GATES [CONTRACT , OFFICER OR OW
CONSULTING ENGINEERS, INC. PLACO LTD.
ACCEPTED BY:
CITY of PORT ARTHUR
2 of 2
4� ; 9
h CHAPTER
CONTRACT AMENDMENTS
Form 9 -4 Construction Contract Change Order Approval Request
Owner (Contractor Locality): Contract For (project description): Date: September 21, 2011
City of Port Arthur Pleasure Island WWTP
Diversion Lift Station
Project No. P08003
Phone #: 409 - 983 -8100
Contractor: Engineer: DR Contract No.
Placo, LTD. Arceneaux & Gates Consulting Engineers, Inc. DRS010148
P.O. Box 8120 3501 Turtle Creek Dr.
Lumberton, TX 77657 Suite 102
Port Arthur, TX 77642
Agreement Date: March 22, 2011
Phone #:409- 724 -7888 Change Order No. 1
Phone #:409- 755 -3878
Engineer's Project No. CPA - 490 -
You are hereby requested to comply with the following changes from the contract plans and specifications:
Item Description of Changes - Quantities, Units, Unit Prices, Decrease in Increase in
No. Change in Completion Scheduled, Etc. Contract Price Contract Price
1 Delete 160 SY— Grasstonen' 1I ($86.87/SY) ($13,899.20)
2 Delete 25 SY — 6 -Inch Flexible Base ($172.71/SY) ($4,317.75)
3 Add 185 SY — 6 -Inch Reinforced Concrete ($53.75/SY) $9,943.75
4 Add 20 LF 18 -Inch RCP ($86.65/LF) $1,733.00
5 Add 2 EA — 18 -Inch Concrete S.E.T.'s ($721.63/EA) $1,443.26
Change in Contract Price Change in Contract Time
($5,096.94) 0 calendar days
RECEIVED
SEP 2 62011
PUPi UC WORKS
Aumen. - City Hall
•
' CHAPTER 9
a • CONTRACT AMENDMENTS
Original Contract Price: $ 283,924.49 Original Contract Time: 180 days
Previous Change Order(s) Net Change From Previous
No. to No. $ 0.00 Change Orders 0 days
Contract Price Prior to Contract Time Prior to
this Change Order $ 283,924.49 this Change Order 180 days
Net lncFease /Decrease of Net Increase/Decrease of
this Change Order $5,096.94 this Change Order 0 days
Contract Price With all Contract Time With all
Approved Change Orders $ 278,827.55 Approved Change Orders 180 days
Cumulative % Change in Contract Price: -2 %
DR Division reimbursement of costs approved by this change order is subject to approval by TDRA.
RECOMMENDED: APPROVED: ACCEPT D:
By: W By: By:
ENGINEER (Authorized Signature) OWNER (Authorized Signature) CONTRA TOR (Authorized
Signature)
Date: 9A 3% Date: Date: 9- - A
Grantee: Port Arthur
DRS Contract No.: DRS010148
JUSTIFICATION FOR CHANGE Change Order No. 1
r e --_,,,
CHAPTER
,i..,, ,),,,,,
9
.)--- ;7 CONTRACT AMENDMENTS
1. Will this Change Order increase or decrease
the number of beneficiaries? ❑ Increase ❑ Decrease ® No Change
If there is a change, how many beneficiaries will be affected? Total L/ M
2. Effect of this change on scope of work: ❑ Increase ❑ Decrease El No Change
3. Effect on operation and maintenance costs: ❑ Increase E( Decrease ❑ No Change
4. Are all prices in the change order dependent upon unit prices
found in the original bid? ❑ Yes 0 No
If "No ", explain:
A quote was obtained from the contractor to install 18" RCP with SET and for 6"
Reinforced Concrete. The Reinforced Concrete will replace the original Grasstone Pavers that
were included in the original bid.
5. Will this change be completed within the contract period? El Yes ❑ No
If "No ", expected completion date:
(completion date)
6. Has this change created new circumstances or environmental
conditions which may affect the projects impact, such as
concealed or unexpected conditions discovered during actual
construction? ❑ Yes El No
If "Yes ", is an Environmental Re- assessment required? ❑ Yes ❑ No
F Ia.
0 3 .� CHAPTER 9
CONTRACT AMENDMENTS
A'
7. Is the Texas Commission on Environmental Quality (TCEQ)
clearance still valid? 0 Yes ❑ No
8. Is the TCEQ permit approval still valid? (sewer projects only) 0 Yes ❑ No
9. Are the handicapped access requirements /approval
still valid (if applicable)? 0 Yes ❑ No
10. Are other Disaster Recovery contractual special condition clearance
still valid? El Yes ❑ No
(If no, specify):
NOTE:
* Generally, a cumulative change in the contract price in excess of 25% cannot
be approved.
* Generally, items not included or identifying unit costs in the original bid
documents cannot be approved as change order items.