CITY OF PORT ARTHUR
UTILITY OPERATIONS DEPARTMENT
TO: Stephen Fitzgibbons, City Manager
FROM: Kelly Eldridge, Director of Utility Operations
DATE: December 5, 2011
SUBJECT: Proposed Resolution No. 16812
RECOMMENDATION
I recommend that the City Council approve Proposed Resolution No. 16812 authorizing the execution of
Change Order No. 6 to the contract between the City and ALLCO, Inc., of Beaumont, Texas, increasing
the contract amount by $95,534.44, for the Sanitary Sewer Rehabilitation by the Pipe Bursting and
Sliplining Methods, Basins PA64C & PA66, Contract No. 6, City Project No. 404PB6.
BACKGROUND
This project was for the cleaning, television inspection, and rehabilitation of approximately 83,000 feet of
sanitary sewer mains, plus the replacement of every service connection served by these main lines in the
Port Acres area. The original project scope included the inspection of all lines that used older - technology
pipe material, with an estimate of having to replace /rehabilitate about 80% of those lines. Change Order
No. 6 addresses three separate items. The first item deals with the replacement of a 60" drop manhole on
the 30" diameter gravity sewer along WPA Road near the DD #7 Pump Station. In the course of
performing line repairs and manhole rehabilitation under Changer Order No. 4, the contractor discovered
what we had thought to be a line cave -in to actually be a catastrophic drop manhole failure. Drop MH's
are used where at major elevation changes in the flow lines of the incoming and outgoing sewer lines.
This failure was considered a safety hazard due to its proximity to the adjacent highway and railroad
tracks, and had to completed ASAP. Railroad and TXDOT personnel were on site to observe the extent of
repairs. The second item is due to the alignment of the sanitary sewer line along a section of 61 S' Street.
The gravity sewer line along 61' St. is generally in the shoulder of the roadside ditch. However, a 138
foot section juts out into the pavement, apparently in an effort to avoid other very close infrastructure in
the immediate area. This will force the contractor to remove & replace this short, but deep section under
pavement. The last item simply restores some previously deleted manhole rehabilitation work. A previous
changer order deleted more than originally thought.
BUDGET/FISCAL EFFECT
Change Order No. 6 increases the contract amount by $95,534.44. Note that we are already over the grant
amount, so these funds will have to come out of the City Sewer Bond Fund.
STAFF/EMPLOYEE EFFECT
None.
SUMMARY
I recommend that the City Council approve Proposed Resolution No. 16812.
P.R. No. 16812
12/05/11
RESOLUTION NO.
A RESOLUTION AUTHORIZING THE EXECUTION
OF CHANGE ORDER NO. 6 TO THE CONTRACT
BETWEEN THE CITY OF PORT ARTHUR AND
ALLCO, INC. FOR THE SANITARY SEWER
REHABILITATION BY THE PIPE BURSTING AND
SLIPLINING METHODS PROJECT, BASINS PA64C &
PA66, CONTRACT NO. 6, INCREASING THE
CONTRACT AMOUNT BY $95,534.44, ACCOUNT
NO. 404-1625-532.83-00, Project No. 404PB6.
WHEREAS, the City is currently under an Agreed Order with the TCEQ to rehabilitate its
sanitary sewer system; and,
WHEREAS, there exists a need to reduce flows and eliminate sanitary sewer overflows in
our collection and treatment systems; and,
WHEREAS, on October 20, 2009, by Resolution No. 09 -489, the City Council awarded the
Sanitary Sewer Rehabilitation by the Pipe Bursting and Sliplining Methods, Basins PA64C & PA66,
Contract No. 6, City Project No. 404PB6 to ALLCO, Inc.; and,
WHEREAS, subsequent to the work already performed under this contract, there exists a
need to amend the bid schedule to reflect the actual project scope and to perform additional work
associated with the TCEQ Agreed Order, and such changes must be done by a contract change order;
and,
WHEREAS, Arceneaux & Gates Consulting Engineers, Inc. recommends Change Order No.
6, increasing the contract amount by $95,534.44, and not changing contract time; NOW
THEREFORE,
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF PORT ARTHUR:
THAT the City Council of the City of Port Arthur hereby authorizes the City Manager to
execute Change Order No. 6 (attached as Exhibit "A ") to the contract between the City of Port
P.R. No. 16812
12/05/11
Page 2 of 3
Arthur and ALLCO, Inc. for the Sanitary Sewer Rehabilitation by the Pipe Bursting and Sliplining
Methods, Basins PA64C & 66, Contract No. 6, City Project No. 404PB6, increasing the contract
amount by $95,534.44, and not changing contract time; and,
THAT, the City Secretary shall provide a copy of this Resolution with an original Change
Order No. 6 to Arceneaux & Gates Consulting Engineers for forwarding to the TWDB for
processing and approval; and,
THAT, a copy of the caption of this Resolution be spread upon the Minutes of the City
Council.
READ, ADOPTED AND APPROVED THIS day of , 2011
at a Regular Meeting of the City Council of the City of Port Arthur, Texas, by the following vote:
AYES: Mayor
Councilmembers:
NOES:
Deloris Prince
Mayor
ATTEST: APPROVED AS TO FORM:
* Vcc,
Sherri Bellard Valecia Tizeno `
City Secretary City Attorney
P.R. No. 16812
12/05/11
Page 3 of 3
APPROVED FOR ADMINISTRATION:
Stephen Fitzgibbons
City Manager
Ross Blackketter, P.E.
Director of Public Works
C4
Kelly Ethridge
Director of Utility Operations
APPROVED AS TO AVAILABILITY OF FUNDS:
4,144,ti-10,4/
Deborah Echols
Director of Finance
Account No.: 404 - 1625 - 532.83 -00
Project No.: 404PB6
EXHIBIT A
(Change Order No. 6)
ARCENEAUX '
GATES
CONSULTING
ENGINEERS, INC.
CHANGE ORDER No. 6
DATE: November 21, 2011 JOB NO. CPA -490 -6
AGREEMENT DATE: November 13, 2009
NAME OF PROJECT: SANITARY SEWER REHABILITATION by PIPE BURSTING
and SLIP LINING METHODS, BASINS PA64C & 66
OWNER: City of Port Arthur r--- — --�
CONTRACTOR: ALLCO, Inc.
The following changes are chan hereby made to tht D
Y
1. ADD the following Items and /or qui
Technical Specifications:
A. 1 EA. 60 -Inch Fiberglass Manh
($32,007.87/EA.) '.87
B. 138 L.F. 10 -Inch Sanitary Sew€
($ 361.18/L.F.) .76
C. Bid Item No. 29, Rehab of Man■ ,o,c vvairwIu one -- -
inch Coating Liner material of approved mix Design
276 V.F. @ $ 95.00 [ +] $ 26,220.00
SUBTOTAL $ 108,070.63
BID ADJUSTMENT FACTOR [X] 0.884
TOTAL ADJUSTED BID $ 95,534.44
r
CHANGE ORDER NO. 6
® November 21, 2011
ARCENEAUX Job No. CPA -490, Contract No. 6
GATES
CONSULTING
ENGINEERS, INC.
CHANGE TO CONTRACT PRICE:
ORIGINAL CONTRACT PRICE: $2,748,577.00
CURRENT CONTRACT PRICE adjusted by previous CHANGE ORDER(S): $3,328,841.62
The CONTRACT PRICE due to this CHANGE ORDER will be [increased] {deer-eased]
by: $95,534.44 Dollars
The new CONTRACT PRICE, including this CHANGE ORDER, will be $3,424,376.06
CHANGE TO CONTRACT TIME:
ORIGINAL CONTRACT TIME: 550 Calendar Days
CURRENT CONTRACT TIME adjusted by previous CHANGE ORDER: 550 Calendar Days
CURRENT DATE OF COMPLETION: March 17, 2012
CONTRACT TIME due to this CHANGE ORDER will be increased by 0 Days
The New DATE OF COMPLETION: March 17, 2012
No other Terms and Conditions of the Contract are changed as a result of this Change Order.
Contractor's acceptance of Change Order relieves OWNER of any liability for additional costs
incurred by Contractor in his performance of the work covered by the Change Order.
RECOMMENDED BY ENGINEER: ACCEPTED BY:
//
ARCS X &G ATES [CONTRACTOR, OFFICER OR OWN"]
CON • ING ENGINEERS, INC. ALLCO, Inc.
ACCEPTED BY:
CITY of PORT ARTHUR
2 of 2
1
ARCENEAUX '
GATES
CONSULTING
ENGINEERS, INC.
CHANGE ORDER No. 6
DATE: November 21. 2011 JOB NO. CPA -490 -6
AGREEMENT DATE: November 13. 2009
NAME OF PROJECT: SANITARY SEWER REHABILITATION by PIPE BURSTING
and SLIP LINING METHODS, BASINS PA64C & 66
OWNER: City of Port Arthur
CONTRACTOR: ALLCO, Inc.
The following changes are hereby made to the CONTRACT DOCUMENTS:
1. ADD the following Items and /or quantities to the Contract Documents and
Technical Specifications:
A. 1 EA. 60 -Inch Fiberglass Manhole
($32,007.87/EA.) [ +] $ 32,007.87
B. 138 L.F. 10 -Inch Sanitary Sewer Main
($ 361.18/L.F.) [ +] $ 49.842.76
C. Bid Item No. 29, Rehab of Manhole Wall with one
inch Coating Liner material of approved mix Design
276 V.F. @ $ 95.00 [ +] $ 26,220.00
SUBTOTAL $ 108,070.63
BID ADJUSTMENT FACTOR [X] 0.884
TOTAL ADJUSTED BID $ 95,534.44
CHANGE ORDER NO. 6
® November 21, 2011
ARCENEAUX Job No. CPA -490, Contract No. 6
&
GATES
CONSULTING
ENGINEERS. INC.
CHANGE TO CONTRACT PRICE:
ORIGINAL CONTRACT PRICE: $2.748,577.00
CURRENT CONTRACT PRICE adjusted by previous CHANGE ORDER(S): $3.328.841.62
The CONTRACT PRICE due to this CHANGE ORDER will be [increased] {decreased}
by: $95.534.44 Dollars
The new CONTRACT PRICE, including this CHANGE ORDER, will be $3.424.376.06
CHANGE TO CONTRACT TIME:
ORIGINAL CONTRACT TIME: 550 Calendar Days
CURRENT CONTRACT TIME adjusted by previous CHANGE ORDER: 550 Calendar Days
CURRENT DATE OF COMPLETION: March 17. 2012
CONTRACT TIME due to this CHANGE ORDER will be increased by 0 Days
The New DATE OF COMPLETION: March 17. 2012
No other Terms and Conditions of the Contract are changed as a result of this Change Order.
Contractor's acceptance of Change Order relieves OWNER of any liability for additional costs
incurred by Contractor in his performance of the work covered by the Change Order.
RECOMMENDED BY ENGINEER: ACCEPTED BY:
/ t
�. ... d
ARCE , I X & GATES (CONTRACTOR, OFFICER OR OWN' ' ]
IP
CON • ING ENGINEERS, INC. ALLCO, Inc.
ACCEPTED BY:
CITY of PORT ARTHUR
2 of 2