HomeMy WebLinkAboutPR 16816: CHANGE ORDER NO. 6 TO THE WASTEWATER TREATMENT PLANT REHAB PROJECT CONTRACT NO. 5 WITH ALLCO, INC. MEMORANDUM CITY OF PORT ARTHUR UTILITY OPERATIONS DEPARTMENT TO: Stephen Fitzgibbons, City Manager FROM: Kelly Eldridge, Director of Utility Operations /6i,/ - DATE: December 6, 2011 SUBJECT: Proposed Resolution No. 16816 RECOMMENDATION I recommend that the City Council approve Proposed Resolution No. 16816 authorizing the execution of Change Order No. 6 to the contract for the Wastewater Treatment Plant Rehabilitation Project, Contract No. 5, City Project No. 404WWT with ALLCO, Inc., of Beaumont, Texas, in the amount of $238,824.90, and increasing contract time by 120 days. BACKGROUND As a part of the Agreed Judgment between the City and the Texas Attorney General's Office/TCEQ Enforcement Division, we were required to have our WWTP's evaluated for deficiencies that have caused, or may cause, violations of our effluent permit. Item1: In the process of replacing equipment in Final Clarifier No. 403 at the Port Acres WWTP, it was determined that the Scum Collector Assembly was severly corroded and in need of replacement. The contractor has provided a replacement cost of $15,819.00. Item 2: During preparation for the installation of the new clarifier bridge in Primary Clarifier "A" at the Main WWTP, we found that the Center Pier support and rake assembly was badly bent and twisted beyond repair. This was the only item not already being replaced in this clarifier. Without replacement, total failure of the clarifier could occur at any time. The contractor has provided a cost of $223,820.00 for this item, along with a time extension request of 120 days. Item 3: While attempting to install an "Insta- valve" for the Sludge Thickener at the Main WWTP, the 50 -year old piping began splitting. We found about 50 feet of deteriorated pipe in need of replacement in order to complete the work, and did not have to use the expensive "insta- valve ". The extra piping costs $10,141.30. Item 4: This item deletes the " Insta- valve" at - $10,955.40. BUDGET /FISCAL EFFECT We have already committed all of our available ARRA grant funds on current projects. Therefore, we will utilize our existing bond funds that we allocated for this work before the grant became available. This Change Order adds 120 days to the contract time. STAFF /EMPLOYEE EFFECT City staff and our consulting engineer, Arceneaux & Gates, will continue to oversee this project. SUMMARY I recommend that the City Council approve Proposed Resolution No. 16816 authorizing the execution of Change Order No. 6 to the contract for the Wastewater Treatment Plant Rehabilitation Project, Contract No. 5, City Project No. 404WWT with ALLCO, Inc., of Beaumont, Texas, increasing the contract amount $238,824.90, and increasing contract time by 120 days. P.R. No. 16816 12/06/11 RESOLUTION NO. A RESOLUTION AUTHORIZING THE EXECUTION OF CHANGE ORDER NO. 6 TO THE WASTEWATER TREATMENT PLANT REHABILITATION PROJECT, CONTRACT NO. 5, BETWEEN THE CITY OF PORT ARTHUR AND ALLCO, INC., OF BEAUMONT, TEXAS, INCREASING THE CONTRACT AMOUNT BY $238,824.90 AND INCREASING CONTRACT TIME BY 120 DAYS. ACCOUNT NO. 404 - 1625 - 532.83 -00, CITY PROJECT NO. 404WWT. WHEREAS, the City is currently under an Agreed Judgment with the Texas Attorney General's Office and the TCEQ to rehabilitate its sanitary sewer system; and, WHEREAS, there exists a need to upgrade and rehabilitate our collection system and treatment plants in order to bring them into permit compliance and eliminate design deficiencies; and, WHEREAS, the City of Port Arthur and Arceneaux & Gates Consulting Engineers have found this additional work is required to meet the requirements of our Agreed Judgment, and requested a Change Order proposal from our contractor, ALLCO, Inc.; and, WHEREAS, ALLCO, Inc. responded with an acceptable proposal and Arceneaux & Gates Consulting Engineers, Inc. has reviewed the proposal and recommends Change Order No. 6 in the total amount of $238,824.90, increasing the contract amount from $9,239,744.72 to $9,478,569.62, and increasing contract time by 120 days for this additional work; NOW THEREFORE, BE IT RESOLVED BY THE CITY • COUNCIL OF THE CITY OF PORT ARTHUR: THAT the City Council of the City of Port Arthur hereby authorizes the City Manager to execute Change Order No. 6 (copy attached hereto as Exhibit "A ") to the contract for the P.R. No. 16816 12/06/11 Page 2 of 3 Wastewater Treatment Plant Rehabilitation Project, Contract No. 5 between the City and ALLCO, Inc., of Beaumont, Texas, increasing the contract amount by $238,824.90 and increasing the contract time by 120 days; and, THAT, the City Secretary shall provide a copy of this Resolution with an original Change Order No. 6 to Arceneaux & Gates Consulting Engineers for forwarding to the TWDB for processing and approval; and, THAT, a copy of the caption of this Resolution be spread upon the Minutes of the City Council. READ, ADOPTED AND APPROVED THIS day of 2011 at a Regular Meeting of the City Council of the City of Port Arthur, Texas, by the following vote: AYES: Mayor Councilmembers: NOES: Deloris Prince, Mayor ATTEST: APPROVED AS TO FORM: Sherri Bellard Valecia Tizeno City Secretary City Attorney P.R. No. 16816 12/06/11 Page 3 of 3 APPROVED FOR ADMINISTRATION: Stephen Fitzgibbons City Manager Ross Blackketter, P.E. Director of Public Works Kelly Eld *d e Y g Director of Utility Operations NA&A.c14, /42 Shawna Tubbs, PPB Purchasing Manager APPROVED AS TO AVAILABILITY OF FUNDS: &Oaf ‘i-co Deborah Echols Director of Finance Acct. No. 404 - 1625 - 532.83 -00 Project No. 404WWT EXHIBIT A (Change Order No. 6) CHANGE ORDER NO. 6 November 10, 2011 ARCENEAUX Job No. CPA -490, Contract No. 5 GATES CONSULTING ENGINEERS, INC. CHANGE ORDER No. 6 DATE: November 10, 2011 JOB NO. CPA -490, Contract No. 5 AGREEMENT DATE: November 13, 2009 NAME OF PROJECT: Main and Port Acres WWTP Rehabilitation to serve the City of Port Arthur OWNER: CITY OF PORT ARTHUR CONTRACTOR: ALLCO, LTD. The following changes are hereby made to the CONTRACT DOCUMENTS: Add the following Items to the Contract: 1. Furnish and install new Scum Collector Assembly in Final Clarifier #403 @ Port Acres WWTP. Per attached proposal (Contractor's C.O. #11). Complete in place. Lump sum price is as follows: SUBTOTAL ITEM 1 $15,819.00 2. Furnish and install remaining clarifier equipment for Primary Clarifier "A" © Main WWTP to replace damaged clarifier center pier, rack arm, etc. Stilling well and bridge are in Base Bid. Per attached proposal (Contractor's C.O. #12). Complete in place. Add 120 days for installation. Lump Sum price is as follows: SUBTOTAL ITEM 2 $223,820.00 3. Replacement of approximately 50 -LF 12 -inch cast iron pipe (CIP) at Sludge Thickener @ Main WWTP. Work performed by field work order due to "rotten" 12 -inch CIP splitting when uncovered for installation of 12 -inch "Insta- valve" per Change Order No. 5. Work included installation of City furnished pipe; pumping; plugging of piping; cement stabilized sand backfill; labor; etc. Per attached Contractor's Field Work Order. Complete in place. Lump Sum price is as follows: SUBTOTAL ITEM 3 $10,141.30 4. Delete 12 -inch "Insta- valve" (see Change Order No. 5, item 2) from scope due to replacement of piping and plugging of flows in item 3 above. Lump Sum price is as follows: SUBTOTAL ITEM 4 - $10,955.40 Z:\A&G ENGINEERING A&G PROJECTSICPA- 490\ CONTRACT 5 - MAIN WWTPWDMINISTRATIONICONTRACT DOCUMENTSICHANGE ORDERSICHANGE ORDER NO 61CHANGE ORDER NO6.doc CHANGE ORDER NO. 6 November 10, 2011 ARCENEAUX Job No. CPA -490, Contract No. 5 GATES CONSULTING ENGINEERS, INC. TOTAL $ 238,824.90 CHANGE TO CONTRACT PRICE: ORIGINAL CONTRACT PRICE: $8,141,753.00 CURRENT CONTRACT PRICE adjusted by previous CHANGE ORDER(S): $9,239,744.72 The CONTRACT PRICE due to this CHANGE ORDER will be [increased] [ a°^�sed; by: $238,824.90 Dollars The new CONTRACT PRICE, including this CHANGE ORDER, will be $9,478,569.62 CHANGE TO CONTRACT TIME: ORIGINAL CONTRACT TIME: 450 Calendar Days CURRENT CONTRACT TIME adjusted by previous CHANGE ORDER: 562 Calendar Days CURRENT DATE OF COMPLETION: March 23, 2012 CONTRACT TIME due to this CHANGE ORDER will be increased by 120 Days The New DATE OF COMPLETION: July 21, 2012 No other Terms and Conditions of the Contract are changed as a result of this Change Order. Contractor's acceptance of Change Order relieves OWNER of any liability for additional costs incurred by Contractor in his performance of the work covered by the Change Order. RECOMMENDED BY ENGINEER: ACCEPTED BY: ARCENEAUX & GATES [CONTRACTOR, OFFICER OR OWNER] CONSULTING ENGINEERS, INC. ALLCO, Ltd. ACCEPTED BY: CITY OF PORT ARTHUR Z:U1&G ENGINEERINGIA&G PROJECTSICPA- 4901CONTRACT 5 - MAIN WWTPIADMINISTRATIONICONTRACT DOCUMENTSICHANGE ORDERSICHANGE ORDER NO EXCHANGE ORDER NO 6 .doc CHANGE ORDER NO. 6 November 10, 2011 ARCENEAUX Job No. CPA -490, Contract No. 5 GATES CONSULTING ENGINEERS, INC. CHANGE ORDER No. 6 DATE: November 10, 2011 JOB NO. CPA -490, Contract No. 5 AGREEMENT DATE: November 13, 2009 NAME OF PROJECT: Main and Port Acres WWTP Rehabilitation to serve the City of Port Arthur OWNER: CITY OF PORT ARTHUR CONTRACTOR: ALLCO, LTD. The following changes are hereby made to the CONTRACT DOCUMENTS: Add the following Items to the Contract: 1. Furnish and install new Scum Collector Assembly in Final Clarifier #403 © Port Acres WWTP. Per attached proposal (Contractor's C.O. #11). Complete in place. Lump sum price is as follows: SUBTOTAL ITEM 1 $15,819.00 2. Furnish and install remaining clarifier equipment for Primary Clarifier "A" © Main WWTP to replace damaged clarifier center pier, rack arm, etc. Stilling well and bridge are in Base Bid. Per attached proposal (Contractor's C.O. #12). Complete in place. Add 120 days for installation. Lump Sum price is as follows: SUBTOTAL ITEM 2 $223,820.00 3. Replacement of approximately 50 -LF 12 -inch cast iron pipe (CIP) at Sludge Thickener @ Main WWTP. Work performed by field work order due to "rotten" 12 -inch CIP splitting when uncovered for installation of 12 -inch "Insta- valve" per Change Order No. 5. Work included installation of City furnished pipe; pumping; plugging of piping; cement stabilized sand backfill; labor; etc. Per attached Contractor's Field Work Order. Complete in place. Lump Sum price is as follows: SUBTOTAL ITEM 3 $10,141.30 4. Delete 12 -inch "Insta- valve" (see Change Order No. 5, item 2) from scope due to replacement of piping and plugging of flows in item 3 above. Lump Sum price is as follows: SUBTOTAL ITEM 4 - $10,955.40 MSG ENGINEERINGA&G PROJECTSICPA- 490 \CONTRACT 5 - MAIN WWTPIADMINISTRATIONICONTRACT DOCUMENTSICHANGE OROERSICHANGE ORDER NO 6\CHANGE ORDER NO 6 .tloc CHANGE ORDER NO. 6 �i November 10, 2011 ARCENEAUX Job No. CPA -490, Contract No. 5 GATES — CONSULTING ENGINEERS, INC. TOTAL $ 238,824.90 CHANGE TO CONTRACT PRICE: ORIGINAL CONTRACT PRICE: $8,141,753.00 CURRENT CONTRACT PRICE adjusted by previous CHANGE ORDER(S): $9,239,744.72 The CONTRACT PRICE due to this CHANGE ORDER will be [increased] [deer-eased} by: $238,824.90 Dollars The new CONTRACT PRICE, including this CHANGE ORDER, will be $9A78,569.62 CHANGE TO CONTRACT TIME: ORIGINAL CONTRACT TIME: 450 Calendar Days CURRENT CONTRACT TIME adjusted by previous CHANGE ORDER: 562 Calendar Days CURRENT DATE OF COMPLETION: March 23, 2012 CONTRACT TIME due to this CHANGE ORDER will be increased by 120 Days The New DATE OF COMPLETION: July 21, 2012 No other Terms and Conditions of the Contract are changed as a result of this Change Order. Contractor's acceptance of Change Order relieves OWNER of any liability for additional costs incurred by Contractor in his performance of the work covered by the Change Order. RECOMMENDED BY ENGINEER: ACCEPTED BY: ARCENEAUX & GATES [CONTRACTOR, OFFICER OR OWNER] CONSULTING ENGINEERS, INC. ALLCO, Ltd. ACCEPTED BY: CITY OF PORT ARTHUR Z % MG ENGINEER1NGA&G PROJECTS\CPA- 4901CONTRACT 5 - MAIN WWTPIADMINISTRATION \CONTRACT DOCUMENTS\CHANGE ORDERSICHANGE ORDER NO 6 \CHANGE ORDER NO 6 .doc •