COUNCIL ACTION MEMO
TO Stephen B. Fitzgibbons, City Manager
FROM Ross E. Blackketter, P.E., Director of Public Works
SUBJECT P.R. #16835 — CO -01 — ALLCO for Storm Sewer Improvements Along Kansas
Avenue (aka Rev. Raymond Scott)
DATE 03 January 2012
RECOMMENDATION:
I recommend that the City Council approve Proposed Resolution No. 16835, authorizing Change
Order 01 to the contract with ALLCO, L.L.C. for the Storm Sewer Improvements Along Kansas
Avenue (aka Rev. Raymond Scott), extending the contract by 124 days with no change to the
amount.
BACKGROUND:
The City Council previously executed a contract with ALLCO for the Storm Sewer Improvements
Along Kansas Avenue (aka Rev. Raymond Scott). Change Order 01 is for a time extension for
124 calendar days with no change in the contract dollar amount in order to complete the punch
list items. The project engineer, Arceneaux & Gates Consulting Engineers, Inc., has reviewed
the request, and recommends approval. In addition, the Texas General Land Office, the agency
administering this grant, now requires that the City approve this change prior to their review
and approval.
BUDGETARY /FISCAL EFFECT:
None.
EMPLOYEE /STAFF EFFECT:
None.
SUMMARY
I recommend that the City Council approve Proposed Resolution No. 16835, authorizing Change
Order 01 to the contract with ALLCO, L.L.C. for the Storm Sewer Improvements Along Kansas
Avenue (aka Rev. Raymond Scott), extending the contract by 124 days with no change to the
amount.
e4.1/.
Ross E. Blackketter, P.E.
Director of Public Works
REB /reb
S: \engineer \Documents \Cams\ ALLCO - KSDrng— CO1.docx
P.R. 16835
01/03/12 reb
RESOLUTION NO.
A RESOLUTION AUTHORIZING THE CITY MANAGER TO EXECUTE
CHANGE ORDER 01 TO THE CONTRACT BETWEEN THE CITY OF
PORT ARTHUR AND ALLCO, L.L.C. FOR STORM SEWER
IMPROVEMENTS ALONG KANSAS AVENUE (AKA REV. RAYMOND
SCOTT), INCREASING THE CONTRACT TERM BY 124 DAYS WITH
NO CHANGE TO THE CONTRACT AMOUNT.
WHEREAS, in Resolution 11 -104, the City entered into a contract with ALLCO,
L.L.C. for Storm Sewer Improvements Along Kansas Avenue (aka Rev. Raymond Scott);
and,
WHEREAS, ALLCO has requested Change Order 01 increasing the term by 124
days to complete outstanding items with no change to the contract amount, attached
hereto as Exhibit "A "; and,
WHEREAS, this change must be approved by the City Council prior to review
and approval by the Texas General Land Office (GLO), the grant administrator; and,
WHEREAS, approval of Change Order 01 increasing the term by 124 days, is
herein deemed an appropriate action; now, therefore,
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF PORT
ARTHUR:
THAT, the facts and opinions in the preamble are true and correct; and,
THAT, Change Order 01 is herein approved and the City Manager is authorized
to execute said Change Order; and,
THAT, a copy of the caption of this Resolution be spread upon the Minutes of
the City Council.
P.R. 16835
Page 2
READ, ADOPTED AND APPROVED this the day of , A.D. 2012
at a meeting of the City of Port Arthur, Texas by the following vote:
Ayes: Mayor:
Councilmembers:
Noes:
Mayor
Attest:
City Secretary
APPROVED AS TO FORM:
\10,(L.
City Attorney
P.R. 16835
Page 3
APPROVED FOR ADMINISTRATION:
1L M_ _ L / 4 '1- - �J
Stephen B. Fitzgibbons Shawna Tubbs, CPPB
City Manager Purchasing Manager
e /%,
Ross E. Blackketter, P.
Director of Public Works
APPROVED AS TO AVAILABILITY OF FUNDS:
/ // /
,
Deborah Echols, CPA
Director of Finance
Z: \engineer\ Documents \Resolutions \PR16835.doc
EXHIBIT A
ARCENEAUX
GATES
CONSUMING
ENGINEERS, INC.
CHANGE ORDER No. 1
DATE: December 19, 2011 JOB NO. CPA -510
AGREEMENT DATE: March 29, 2011
NAME OF PROJECT: STORM SYSTEM SEWER IMPROVEMENTS along
KANSAS AVENUE (AKA REV. RAYMOND SCOTT) from
WEST 19 STREET to WEST THOMAS BOULEVARD
OWNER: CITY OF PORT ARTHUR
CONTRACTOR: ALLCO, L.L.C.
The following changes are hereby made to the CONTRACT DOCUMENTS:
CHANGE TO CONTRACT PRICE:
ORIGINAL CONTRACT PRICE: $626,630.00
CURRENT CONTRACT PRICE adjusted by previous CHANGE ORDER(S):
The CONTRACT PRICE due to this CHANGE ORDER will be fifteFeased-} [deer
by: Dollars
The new CONTRACT PRICE, including this CHANGE ORDER, will be
CHANGE TO CONTRACT TIME:
ORIGINAL CONTRACT TIME: 180 Calendar Days
CURRENT CONTRACT TIME adjusted by previous CHANGE ORDER: 180 Calendar Days
CURRENT DATE OF COMPLETION: October 28, 2011
CONTRACT TIME due to this CHANGE ORDER will be increased by 124 Days
The New DATE OF COMPLETION: February 29. 2012
CHANGE ORDER NO. 1
® December 19, 2011
ARCENEAUX Job No. CPA -510, Contract No. 1
GATES
CONSULTING
ENGINEERS, INC.
No other Terms and Conditions of the Contract are changed as a result of this Change Order.
Contractor's acceptance of Change Order relieves OWNER of any liability for additional costs
incurred by Contractor in his performance of the work covered by the Change Order.
RECOMMENDED BY ENGINEER: ACCEPTED BY:
ARCENE r' & GATES
[CO RACTOR, 0 CER OR OWNER]
CONSU T NG ENGINEERS, INC. ALLCO, L.L.C.
ACCEPTED BY:
CITY of PORT ARTHUR
2 of 2
r
43 ° � CHAPTER 9
P006. CONTRACT AMENDMENTS
Form 9 -4 Construction Contract Change Order Approval Request
Owner (Contractor Locality): Contract For (project description): Date: December 19, 2011
City of Port Arthur Storm Sewer System
Improvements Along Kansas
Avenue Project No. P08006
Phone #: 409 - 983 -8100
Contractor: Engineer: DR Contract No.
ALLCO, L.L.C. Arceneaux & Gates Consulting Engineers, Inc. DRS010148
P.O. Box 3684 3501 Turtle Creek Dr.
Beaumont, TX 77704 Suite 102
Port Arthur, TX 77642
Agreement Date: March 29, 2011
Phone #:409- 724 -7888 Change Order No. 1
Phone #:409- 962 -2677
Engineer's Project No. CPA -510
You are hereby requested to comply with the following changes from the contract plans and specifications:
Item Description of Changes - Quantities, Units, Unit Prices, Decrease in Increase in
No. Change in Completion Scheduled, Etc. Contract Price Contract Price
Change in Contract Price Change in Contract Time
$ 0 124 calendar days
OF r 10.
I "' If 4 CHAPTER
9
CONTRACT AMENDMENTS
Original Contract Price: $ 626,630.00 Original Contract Time: 180 days
Previous Change Order(s) Net Change From Previous
No. to No. $ 0.00 Change Orders 0 days
Contract Price Prior to Contract Time Prior to
this Change Order $ 0.00 this Change Order 180 days
Net trIsceaseigesFease of Net Increase /Decrease of
this Change Order $ 0.00 this Change Order 124 days
Contract Price With all Contract Time With all
Approved Change Orders $ 0.00 Approved Change Orders 304 days
Cumulative % Change in Contract Price: 0%
DR Division reimbursement of costs approved by this change order is subject to approval by TDRA.
RECOMMENDED APPROVED: ACCEPT
By: - By: By:
r
EN e ` ;" Authorized Signature) OWNER (Authorized Signature) CONTRACTOR (Authorized
Signature)
Date: 1 2.27-1 t Date: Date: / 0 ,//
Grantee: Port Arthur
DRS Contract No.: DRS010148
JUSTIFICATION FOR CHANGE Change Order No. 1
1. Will this Change Order increase or decrease
the number of beneficiaries? 0 Increase 0 Decrease El No Change
• 't.
L1* CHAPTER 9
CONTRACT AMENDMENTS
If there is a change, how many beneficiaries will be affected? Total UM
2. Effect of this change on scope of work: ❑ Increase ❑ Decrease 0No Change
3. Effect on operation and maintenance costs: ❑ Increase ❑ Decrease 0 No Change
4. Are all prices in the change order dependent upon unit prices
found in the original bid? 0 Yes ❑ No
If "No ", explain:
5. Will this change be completed within the contract period? ❑ Yes 0 No
If "No ", expected completion date: February 29, 2012
(completion date)
6. Has this change created new circumstances or environmental
conditions which may affect the project's impact, such as
concealed or unexpected conditions discovered during actual
construction? ❑ Yes 0 No
If "Yes ", is an Environmental Re- assessment required? ❑ Yes ❑ No
t, , CHAPTER 9
� " CONTRACT AMENDMENTS
TEX S
7. Is the Texas Commission on Environmental Quality (TCEQ)
clearance still valid? El Yes ❑ No
8. Is the TCEQ permit approval still valid? (sewer projects only) El Yes ❑ No
J Y
9. Are the handicapped access requirements/approval
PP
still valid (if applicable)? El Yes ❑ No
10. Are other Disaster Recovery contractual special condition clearance
still valid? El Yes ❑ No
(If no, specify):
NOTE:
* Generally, a cumulative change in the contract price in excess of 25% cannot
be approved.
* Generally, items not included or identifying unit costs in the original bid
documents cannot be approved as change order items.