HomeMy WebLinkAboutPR13354: LANDFILL/SCS ENG. PUBLI'C WORKS DEPARTMENT
COUNCI~L ACI'ZON MEMO
TO Steve Fitzgibbons, City Manager
FROM John A. Comeaux, P.E., Director of Public Works
SUBJECT P.R. #13354 - Change Order 03 for Contract with SCS Engineers
DATE November 29, 2005
RECOMMENDAT'LON:
! recommend that the City Council approve Proposed Resolution No. 13354, authorizing Change
Order 03 to the existing contract with SCS Engineers, increasing the scope of services and
increasing the contract amount by $12,000 to a new total of $360,000.
BACKGROUND:
Because the City landfill was approaching capacity and needed expansion, in August 2002, the City
entered into a contract with SCS Engineers for Landfill Permitting and Design. The City has since
executed two change orders, increasing the project budget by $38,000 to a total of $348,000.
SCS has completed the permit application process to the point of having the permit considered
Technically Complete by the Texas Commission on Environmental Quality (TCEQ). Recently, a
Request for a Contested Case Hearing was presented to the TCEQ by an adjoining landowner.
This request requires additional work by SCS to respond to this issue and provide a Response to
Comments for the TCEQ. Accordingly, SCS has requested an increase in scope in the amount of
$12,000.
Change Order 03 will increase the contract by $12,000 to a new total of $360,000.
BUDGETARY/F?SCAL EFFECT:
Funding is available in Solid Waste account 403-1274-533.54-00.
EMPLOYEE/STAFF EFFECT:
None.
SUMMARY
! recommend that the City Council approve Proposed Resolution No. 13354, authorizing Change
Order 03 to the Landfill Permitting and Design contract with SCS Engineers, increasing the contract
amount by $12,000 to a total of $360,000.
Director of Public Works
JA¢/reb
Z:\engineer\Documents\Cams\$CS-CO3.doc
P.R. No. 13354
11/29/05 reb
RESOLUTZON NO.
A RESOLU'rZON AUTHORTZI'NG THE MAYOR AND CZTY MANAGER TO
EXECUTE CHANGE ORDER 03, I'NCREASTNG THE SCOPE OF SERVTCES
FOR THE CONTRACT DATED AUGUST 20, 2002 BETWEEN THE cTrY OF
PORT ARTHUR AND SCS ENGTNEERS OF BEDFORD, TEXAS FOR
LANDFZLL PERM~i m~NG AND DESZGN AND ZNCREASZNG THE BUDGET
FOR THXS PRO3ECT BY $12,000 TO A TOTAL OF $360,000. SOLZD
WASTE ACCOUNT 403-1274-533.54-00.
WHEREAS, a contract for the permitting and design for the City landfill was executed
between the City of Port Arthur and SCS Engineers of Bedford, Texas on August 20, 2002; and,
WHEREAS, the original budget for this contract was $310,000; and,
WHEREAS, the City has executed two change orders, raising the budget by $38,000 to
a total of $348,000
WHEREAS, due to the landfill permit being contested, and work outside the original
scope are required from SCS to respond to the Request for a Contested Case Hearing, SCS has
submitted a request for additional services to this contract in the amount of $12,000 (see
attached Exhibit "A'~; and,
WHEREAS, approval of Change Order 03 (attached as Exhibit "B'~ to increase the
budget by $12,000 is herein deemed an appropriate action, and approval of Change Order 03
will increase the existing contract budget to an amount of $360,000; now, therefore,
BE TI' RESOLVED BY THE cTrY COUNCXL OF THE CTrY OF PORT ARTHUR:
THAT, Change Order 03 is herein approved and the City Manager is authorized to
execute said Change Order; and,
THAT, a copy of the caption of this Resolution be spread upon the Minutes of the City
Council.
P.R. No. 13354
Page 2
READ, ADOPTED AND APPROVED this the _ day of ., A.D. 2005 at a __
meeting of the City of Port Arthur, Texas by the following vote: Ayes:
Mayor:
Councilmembers:
Noes:
Mayor
Attest: APPROVED AS TO FORM
City Secretary City Attorney
APPROVED FOR ADMINISTRATION:
Stephen Fitzgibbons JoiA. Comeaux, P.E.
City Manager Director of Public Works
APPROVED AS TO AVATLABI~L~I-Y OF FUNDS:
Rebecca Underhill, CPA
Director of Finance
Z:\engineer\Documents\Resolutions\PR~.3354.doc
EXHIBTT A
Environmental Consultants 1901 Centrczl Drive 817 571-2288
Sulte 550 FAX 817 57t-2188
Bedford, Texos 76021 www.scsengineers.corn
November 3, 2005
SCS Project No. 16202007.00
Mr. John A. Comeaux, P.E., Director of Public Works
City of Port Arthur sent via FedX
444 4th Street
Port Arthur, Texas 77640
Subject: Landfill Expansion Permitting and Design
Request for Budget Increase for Out-of-Scope Services
under our Existing Agreement
Dear Mr. Comeaux:
Per your request, this letter is to request an increase in the project budget for additional services
required to provide technical support associated with the Contested Case Hearing and related services.
As you know, through the combined efforts of the City and SCS Engineers (SCS), we achieved the
status of having the permit considered Technically Complete by the Texas Commission on
Environmental Quality (TCEQ). However, the request for a Contested Case Heating has now
continued to require our involvement since the initial filing of this request on January 3, 2005. As you
know, SCS has continued to work with the City, the City's attomey, and the TCEQ in addressing this
additional, unanticipated aspect of the permit process. Our services have included (1) obtaining the
TCEQ's approval for an extension for the submittal of the Site Operating Plan permit modification, (2)
obtaining the TCEQ's approval for an extension for the of the deadline for the TCEQ's deadline for a
settlement offer for a Supplemental Envirormtental Project, (3) assisting in developing a request for the
TCEQ's Temporary Authorization of a vertical increase in the approved final elevations at the City's
landfill, (4) and other services as detailed in our invoices.
Our currently approved budget for permitting services is $348,000. With your approval of this change,
the new revised budget will be $360,000. These services will be performed on a time-and-materials
basis; our invoices will include details of our expenditures. As you know, a preliminary hearing is
scheduled for November 9, 2005 before a administrative law judge of the State Office of
Administrative Hearings. This revised budget is intended to include our providing limited technical
support to the hearing process for the expected accelerated schedule. We will keep you advised of our
progress in the permitting process.
We appreciate the opportunity to be of continued service to the City of Port Arthur. Please advise if
you have any questions on this or other matters.
S ncere!y,.~_)
Vice President
SCS ENGINEERS
cc: Gerald Robinson, City of Port Arthur
E:~PRO/ECTS~PtArIhurX16202007~PM\ht¢,L-bud ehg req 110305.doe SCS ENGINEERS
offices Nalionwlde
EXHIBI'T B
CHANGE ORDER NO. 03
DATE: December 6, 2005
ORIGINAL AGREEMENT DATE: August 20, 2002
SCS ENGINEERS
SCS PROJECT NUMBER: 16202007.00
PROJECT DESCRIPTION: Landfill Permit Amendment and Design
CHANGE IN SCOPE:
Additional services required for response to Request for a Contested Case Hearing and
for a Response to Comments.
CHANGE TO CONTRACT AMOUNT:
ORIGINAL CONTRACT amount: $310,000
CURRENT CONTRACT PRICE (adjusted by previous CHANGE ORDER): $348,000
The Contract Amount due to this CHANGE ORDER will be (increased/decreased) by:
$12,000
The new CONTRACT AMOUNT including the CHANGE ORDER will be: $360,000
SCS ENGINEERS
Signature
Kevin D. Yard, P.E.
Printed Name
CITY OFPORTARTHUR
Stephen Fitzgibbons
City Manager
File: Z:\engineer\Documents\Contracts\ScopeChg No. 3 112905.doc