HomeMy WebLinkAboutPR 17115: CHANGE ORDER 5 ACCEPTANCE AND FINAL PAYMENT FOR PRIMARY GENERATORS MEMORANDUM
CITY OF PORT ARTHUR
UTILITY OPERATIONS DEPARTMENT
TO: John Comeaux, P.E., Acting City Manager
FROM: Kelly Eldridge, Director of Utility Operations )46
DATE: June 26, 2012 +
SUBJECT: Proposed Resolution No. 17115
RECOMMENDATION
I recommend that the City Council approve Proposed Resolution No. 17115 authorizing the
execution of Change Order No. 5 (Final) to the contract between the City and T. Johnson
Industries, Inc., of Lumberton, Texas, decreasing the contract amount $904.61 an increase the
contract time by 61 calendar days, for the Primary and Secondary Generators for the Main
Wastewater Treatment Plant and Primary Generator for the Main Outfall Lift Station Project.
This PR also accepts the project and authorizes final payment (release of retainage).
BACKGROUND
This project is for the provision of emergency generators at the above facilities. The TDRA has
provided grant funds for this work. This change order provides for additional electrical surge
protection equipment at the WWTP, waterproof coating to the electrical switchgear building,
deletes unused supplemental items, and also provides a short time extension for this work. The
new contract date of completion is July 31, 2012. A Final Inspection was conducted on this
project and A &G issued an Engineer's Certificate of Completion dated June 22, 2012.
BUDGET/FISCAL EFFECT
The Change Order decreased the contract amount by $904.61, Project No. ORPRIM, ORMSEC,
& ORMAIN.
For Finance: ($452.305) ORPRIM
($452.305) ORMSEC
$0 ORMAIN
STAFF/EMPLOYEE EFFECT
City staff will operate and maintain these generators.
SUMMARY
I recommend that the City Council approve Proposed Resolution No. 17115.
1
P.R. No. 17115
06/26/12
RESOLUTION NO.
A RESOLUTION AUTHORIZING THE EXECUTION
OF CHANGE ORDER NO. 5 (FINAL), THE
ACCEPTANCE OF THE PROJECT, AND FINAL
PAYMENT FOR THE PRIMARY AND SECONDARY
GENERATORS FOR THE MAIN WAS "1'EWATER
TREATMENT PLANT AND PRIMARY GENERATOR
FOR THE MAIN OUTFALL LIFT STATION PROJECT,
ACCOUNT NO. 141 - 1201 - 532.59 -00, PROJECT NO.
ORPRIM, ORMSEC, & ORMAIN.
WHEREAS, the City is currently under an Agreed Order with the TCEQ to rehabilitate
its sanitary sewer system; and,
WHEREAS, the City is in need of upgrading key lift stations and WWTP'S to provide
electrical power during emergency conditions in order to continue to provide service and to meet
TCEQ Design Criteria; and,
WHEREAS, the City applied for, and received, a grant from the Texas Department of
Rural Affairs for such emergency generators; and,
WHEREAS, on June 28, 2011, by Resolution No. 11 -239, the City Council awarded the
Primary and Secondary Generators for the Main Wastewater Treatment Plant and Primary
Generator for the Main Outfall Lift Station project to T. Johnson Industries, Inc. in the amount of
$1,192,605.70; and,
WHEREAS, during the course of the project, the City has requested additional work to
install surge protection equipment that will facilitate the operation and maintenance of the Main
WWTP generator supplied under this project; and,
WHEREAS, Arceneaux & Gates Consulting Engineers, Inc. prepared and recommends
Change Order No. 5 (attached as Exhibit "A ") to include such work and decreased the contract
amount by $904.61 and increase the contract time by 61 calendar days, and a Final Inspection
has been conducted, and Arceneaux & Gates Consulting Engineers, Inc. has issued an
EXHIBIT A
(Change Order No. 5)
CB
ARCENEAUX
GATES
CONSULTING
ENGINEERS, INC.
CHANGE ORDER No. 5
DATE: June 27, 2012 JOB NO. CPA -570
AGREEMENT DATE: July 5, 2011
NAME OF PROJECT: PRIMARY & SECONDARY GENERATORS for MAIN WWTP
and PRIMARY GENERATOR for MAIN OUTFAL LIFT STATION
OWNER: CITY of PORT ARTHUR
CONTRACTOR: T. JOHNSON INDUSTRIES, INC.
The following changes are hereby made to the CONTRACT DOCUMENTS:
1. Delete /Adjust the following Bid Items to actual quantities used:
a. Bid Item No. 2, Extra Reinforcing Steel
200 LB. @ $0.75. [ -] $ 150.00
b. Bid Item No. 3, Extra Class "A" Concrete
20 C.Y. @ $150.00. [ -] $ 3,000.00
c. Bid Item No. 4, Extra- Cement Stabilized Sand
20 C.Y. @ $30.00. [ -] $ 600.00
SUB -TOTAL ($ 3,750.00)
2. Add the following Items to the Contract and Scope of Work:
a. Paint the Exterior of the new ATS
Building at the Main WWTP with
Watertite Latex Concrete Masonry [ +] $ 2,193.53
b. Install One Surge Protector on Main Plant
Secondary Service ATS [ +] $ 651.86
SUB -TOTAL ( +] $ 2,845.39
TOTAL ($ 904.61)
CHANGE ORDER NO. 5
I ED June 27, 2012
ARCENEAUX Job No. CPA -570, Contract No. 1
GATES
CONSULTING
ENGINEERS, INC.
CHANGE TO CONTRACT PRICE:
ORIGINAL CONTRACT PRICE: $1,192,605.70
CURRENT CONTRACT PRICE adjusted by previous CHANGE ORDER(S): $1,260,288.49
The CONTRACT PRICE due to this CHANGE ORDER will be [increased] [decreased]
by: $904.61 Dollars
The new CONTRACT PRICE, including this CHANGE ORDER, will be $1,259,383.88
i
CHANGE TO CONTRACT TIME:
ORIGINAL CONTRACT TIME: 150 Calendar Days
CURRENT CO adjusted by previous TIME adjusted b revious CHANGE ORDER: 316 Calendar Days
CURRENT DATE OF COMPLETION: May 31, 2012
CONTRACT TIME due to this CHANGE ORDER will be increased by 61 Days
The New DATE OF COMPLETION: July 31, 2012
No other Terms and Conditions of the Contract are changed as a result of this Change Order.
Contractor's acceptance of Change Order relieves OWNER of any liability for additional costs
incurred by Contractor in his performance of the work covered by the Change Order.
RECOMMENDED BY ENGINEER: ACCEPTED BY:
4 %)
ARCENE & GATES [CONTRACTOR, ! <' ER OR OWNER]
CONS LTI G ENGINEERS, INC. T. JO SON INDRUSTRIES, INC.
ACCEPTED BY:
CITY of PORT ARTHUR
2 of 2
EXHIBIT "B"
(Engineer's Certificate of Completion)
•
ENGINEER'S CERTIFICATE OF COMPLETION
Project: PRIMARY & SECONDARY GENERATORS FOR MAIN WWTP
AND PRIMARY GENERATOR FOR MAIN OUTFALL LIFT
STATION
Date Of Issuance: June 27, 2012
Owner(s): CITY OF PORT ARTHUR
Owner's Project No.: CPA -570, Contract No. 1
Engineer: ARCENEAUX & GATES CONSULTING ENGINEERS, INC., A
BURROW GLOBAL COMPANY
Contractor: T. JOHNSON INDUSTRIES, INC.
This Engineer's Certificate of Completion applies to all Work under the Contract Documents or to
the following specified parts thereof:
TO CITY OF PORT ARTHUR
[OWNER]
AND TO T. JOHNSON INDUSTRIES, INC.
[CONTRACTOR]
The Work to which this Certificate applies has been inspected by authorized representatives of
Owner, Contractor and Engineer, and that Work is hereby declared to be complete in accordance
with the Contract Documents on
June C 2012 4. 0 F T 4: LN
DATE OF COMPLETION c .• • • • • • •.� ! ••
Executed by Engineer on June 27, 2012 i * • % *
JOE M. WILSON, JR. f
-0 92067 �cr
E •
1 � .! / DENS 0 2
11 \\ o ALs9r
BY: 1111111k IMIO
ARCENEAUX & � TES. * -TING ENGINEERS, INC., [SEAL]
A BU • OW GLOBAL COMPANY
1/1
EXHIBIT "C"
(Contractor's Certificate and Release)
CONTRACTOR'S CERTIFICATE OF GUARANTEE
FROM: T. JOHNSON INDUSTRIES, INC.
(Name of Contractor)
TO: CITY OF PORT ARTHUR
REFERENCE CONTRACT NO. CPA -570, Contract No.1
ENTERED INTO THE 5th DAY OF July, 2011 BETWEEN THE CITY OF PORT ARTHUR AND T.
JOHNSON INDUSTRIES, INC.
OF LUMBERTON, TEXAS
(City) (State)
FOR THE PRIMARY & SECONDARY GENERATORS FOR MAIN WWTP AND PRIMARY
GENERATOR FOR MAIN OUTFALL LIFT STAION to SERVE the CITY OF PORT ARTHUR,
CPA -570, CONTRACT NO. 1 .
LOCATED IN THE CITY OF PORT ARTHUR, TEXAS
KNOW ALL MEN BY THESE PRESENTS:
1. T. JOHNSON INDUSTRIES, INC. does hereby guarantee all of the work done under the above
referenced contract to be free from faulty materials in every particular, and free from improper
workmanship, and against injury from proper and usual wear•, and agrees to replace or re- execute without
cost to the Owner and Operator such work as may be found to be improper or imperfect, and to make good
all damage caused to other work or materials, due to such required replacement or re- execution.
2. This guarantee shall cover a period of one (1) year from the date of acceptance of all work under this
Contract, as evidenced by the Engineer's Certificate of Completion.
3. This Certificate is given in connection of the final payment under the contract between the Owner and
T. JOHNSON INDUSTRIES, INC. and with the knowledge that it will be relied upon in making such
payment and that such payment would not be made except upon the truth of the matter contained in this
affidavit.
IN W ESS WHE' OF, the undersigned has signed and sealed this instrument this .. ZA - -1 day
of _ /, ! , 2012.
(CO h/ ORATE SEAL) T. JOHNSON INDU J IES, INC.
(Contractor)
BY: , Owner
( Terry Johns. •
1/2
Terry Johnson, being first duly sworn on oath, deposes and says, first that he /she is the
Owner of T. JOHNSON INDUSTRIES, INC.
(Title) (Name of Company)
second, that he has read the foregoing certificate by him subscribed as Owner
(Title)
of T. JOHNSON INDUSTRIES, INC.
(Name of Company)
Affiant further states that the matters and things stated herein are true.
�•` • ANAHE D DRAKE ,1
4 , . , t.t.E
t - I Z , , Notary Public I
*� STATE OF TEXAS ( erry Johnson
1L `'"' � COMM. _ March 29, 2015 1)
Subscribed and sworn to before me thisOv day of j .1� , 2012.
My commission expires: -3 /c0/he
(Date)
1.0 11
(Nota usl)
2/2
EXHIBIT "D"
(Contractor's Certificate of Guarantee)
CONTRACTOR'S CERTIFICATE AND RELEASE
FROM: T. JOHNSON INDUSTRIES, INC.
(Name of Contractor)
TO: CITY OF PORT ARTHUR
(Owner)
REFERENCE CONTRACT NO. CPA - 570, CONTRACT NO. 1 ENTERED INTO THE 5 DAY
OF JULY, 2011, BETWEEN THE CITY OF PORT ARTHUR
AND T. JOHNSON INDUSTRIES, INC.
(Name of Contractor)
OF LUMBERTON, TEXAS
(City) (State)
FOR THE: PRIMARY & SECONDARY GENERATORS FOR MAIN WWTP AND PRIMARY
GENERATOR FOR MAIN OUTFALL LIFT STATION
KNOW ALL MEN BY THESE PRESENTS:
1. The undersigned hereby certifies that there is due from, and payable by, the Owner to the
Contractor under the contract and duly approved Change Orders and modifications the balance of
SIXTY SIX THOUSAND NINE HUNDRED THIRTY EIGHT DOLLARS and FORTY SIX CENTS
($ 66,938.46)
2. The undersigned further certifies that in addition to the amount set forth in Paragraph 1, there are
outstanding and unsettled the following items which he claims are just and due and owing by the
Owner to the Contractor:
(a)
(b)
(c)
(d)
(Itemize claims and amounts due) (If none, so state)
3. The undersigned further certifies that all work required under this contract, including work required
under Change Order(s) numbered 1 - 5 has been performed in accordance with the terms thereof,
and that there are no unpaid claims for materials, supplies, or equipment and no claims of laborers
or mechanics for unpaid wages arising out of the performance of this contract, and that the wage
rates paid by the Contractor were in conformity with the contract provisions relating to said wage
rates.
1/2
5. That in consideration of the payment of the amount stated in Paragraph 1 hereof, the undersigned
does hereby release the Owner and Operator from any and all claims arising under or by virtue of
this contract, except the amount listed in Paragraph 2 hereof due from the Owner; provided,
however, that if for any reason the Owner does not pay in full the amount stated in Paragraph 1
hereof, said deduction shall not affect the validity of this release, but the amount so deducted shall
be automatically included under Paragraph 2 as an amount which the Contractor has not released
but will release upon payment thereof. The Contractor further certifies that upon the payment of the
amount listed in Paragraph 2 hereof, and of any amount which may be deducted from Paragraph 1
hereof, he will release the Owner and Operator from any and all claims of any nature whatsoever
arising out of said contract or modification thereof, and will execute such further releases or
assurances as the Owner and Operator may request.
IN WI , SS I :REOF, the undersigned has signed and sealed this instrument 4i-cra y
of , 2012.
(CORP. =`i SEAL)
T. JOHNSON INDUST _.i�c:� , C.
iii • (Contractor)
BY: ./ `, - — -
(Terry Johnson)
Terry Johnson , bei • first duly sworn on oath, deposes and says, first, that
(Terry Johnson)
he is the Owner of T. JOHNSON INDUSTRIES, INC.
(Title) (Name of Company)
second, that he has read the foregoing certificate by him subscribed as Owner
(Title)
of T. JOHNSON INDUSTRIES, INC.
(Name of Company)
giant further states that the matters and things stated herein are .
(Terry o , so
Subscribed and sworn to before me this ____ day of , 2012.
My commission expires Q 3 -9 7 �� •
( Da
0. - - •A K 0 DRAKE , 110
. )l �` ,
1 '%;. 41 STATE OF TEXAS (Notary Pub ic
1 ._. °` __ Comm. T . March 29, 2015 , I
2/2
EXHIBIT "E"
(Certificate of Acceptance)
CERTIFICATE OF ACCEPTANCE
FOR
PRIMARY AND SECONDARY GENERATORS
FOR THE MAIN WASTEWATER TREATMENT
PLANT AND PRIMARY GENERATOR FOR THE
MAIN OUTFALL LIFT STATION PROJECT
IN THE
CITY OF PORT ARTHUR
TO: T. Johnson Industries, Inc.
Date:
Gentlemen:
This is to certify that the City of Port Arthur, Texas, accepts the PRIMARY AND
SECONDARY GENERATORS FOR THE MAIN WASTEWATER TREATMENT
PLANT AND PRIMARY GENERATOR FOR THE MAIN OUTFALL LIFT STATION
PROJECT on the basis of the Engineer's Certificate of Completion by Joe M. Wilson, Jr., P.E.,
of Arceneaux & Gates Consulting Engineers, the Contractor's Certificate of Guarantee, and the
Contractor's Certificate and Release, executed by Terry Johnson, Owner, of T. Johnson
Industries, Inc.
John Comeaux, P.E.
Acting City Manager
ATTEST:
Sherri Bellard
City Secretary