HomeMy WebLinkAboutPR 17304: CHANGE ORDER NO. 1 WITH NELSON COLLABORATIVE CITY OF PORT ARTHUR
TRANSIT DEPT.
TO: FLOYD T. JOHNSON, CITY MANAGER AND CITY COUNCIL
FROM: COLLEEN W. RUSSELL, TRANSIT DIRECTOR
SUBJECT: P.R. NO. 17304 - CHANGE ORDER FOR NELSON COLLABORATIVE SERVICES
WITH PAT
DATE: 10/04/2012
RECOMMENDATION:
Recommend that Proposed Resolution No. 17304 be approved so that the design and bids may be
accepted in line with this contract and work on the renovation of PAT's complex can continue.
BACKGROUND:
The City of Port Arthur desires to execute a change order for the Architects, The Nelson Collaborative, to
design a fire system for Transit's complex. The system was originally overlooked, but with the Building
Storage codes of the International Code Council mandates this system by Law. This Agreement, entered
into as of October 2012, between the City of Port Arthur and The Nelson Collaborative for professional
services for Port Arthur Transit renovations will increase their fees from $72,000 to $86,415.31
BUDGETARY /FISCAL EFFECT:
The total remaining compensation for The Nelson Collaborative will be from the American Recovery and
Reinvestment Act (ARRA). This amount shall be from TX90 -X040 that are Federal Transit
Administration allocated funds. These funds in account 402 - 1508 - 54.561.00 are 100% reimbursable.
STAFFING /EMPLOYEE EFFECT:
With these changes the employees and shared assets of the Port Arthur Transit Department and FTA will
be under Code compliance.
SUMMARY:
Recommend -that Pro. ssed Resolution No. 17304 be approved so that the design and bids may be
acee ted1n e ith . s contract and work on the renovation of PAT's complex can continue.
Colleen W. ussel Transit Director
P.R. No. 17304
9/21/12 CWR
RESOLUTION NO.
A RESOLUTION AUTHORIZING THE CITY MANAGER
TO EXECUTE CHANGE ORDER 01 TO THE CONTRACT
BETWEEN THE CITY OF PORT ARTHUR AND THE
NELSON COLLABORATIVE FOR DESIGN OF
ADDITIONAL FIRE SAFETY EQUIPMENT, INCREASING
THE CONTRACT AMOUNT BY $14,415.31 TO A NEW
TOTAL OF $86,415.31; FUNDED FROM FEDERAL
TRANSIT ADMINISTRATION ALLOCATED FUNDS —
ARRA TX90 -X040
WHEREAS, per Resolution No. 11 -084, the City entered into a contract with The
Nelson Collaborative ( "Nelson ") for the design and oversight of the renovations of the Transit
Service Building and Transfer Center; and
WHEREAS, per Resolution No. 12 -286, "Nelson" was granted a ten (10) month
extension; and
WHEREAS, during the rebid of the project, it was determined that additional design for
fire safety components were required to be Code compliant, see explanation from Timothy
Barnes attached as Exhibit "A "; and
WHEREAS, approval of Change Order 01 increasing the contract amount by $14,415.31
to a new total of $86,415.31, funded from Federal Transit Administration allocated funds for
ARRA (America Recovery and Reinvestment Amendment) funds and these fees are 100 %, is
herein deemed appropriate.
NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE
CITY OF PORT ARTHUR:
P.R. NO. 17304
09 /21 /12CWR
Page 2
THAT the facts and opinions in the preamble are true and correct.
THAT Change Order 01 is herein approved and the City Manager is authorized to execute
said Change Order, in substantially the same form as attached hereto as Exhibit `B ".
THAT the payments are 100% reimbursable to the City by FTA from Account No. 402-
1508- 561.54 -00, which is an ARRA account.
THAT a copy of the caption of this Resolution be spread upon the Minutes of the City
Council.
READ, ADOPTED AND APPROVED this day of October A.D. 2012, at a
Regular Meeting of the City Council of the City of Port Arthur, Texas, by the following vote:
AYES:
Mayor:
Councilmembers:
NOES:
Mayor
ATTEST:
City Secretary
APPROVED AS T 1 FORM:
\C
A�� •
City Attorney
P.R. NO. 17304
09 /21 /12CWR
Page 3
APPROVED FOR ADMINISTRATION:
City Manager
APPROVED AS TO AVAILABILITY OF FUNDS:
Director of Finance (402- 1508 - 561.54 -00)
W. . kW. so
Pur hasing ► -a g er
I'
Di! r of Tran ,it
P.R. NO. 17304
09 /21 /12CWR
Page 4
EXHIBIT "A"
1
lig The Nelson Collaborative
Aio,.tt
r,i6i, trrrnt -i
ettlp Vaal Varsigr`mt Fir
0.01,1+41, 4./r) ,,t vt:t r:(
A 0,: Pi: a]r,,I4A, ,
October 16, 2012
VIA: Floyd.johnson @portarthur.net
Mr. Floyd Johnson 1
City of Port Arthur
City Manager
444 4 Street
Port Arthur, Texas 77641 -1089
RE: Transit Service Building Renovation — Additional Scope of Work
City of Port Arthur, Texas 1
TNC ProjectNo.: NO301 -C11 -002
Dear Mr. Johnson:
In response to your request during our meeting on Monday, October 15 we have attached the
following revised schedule for the remaining work for the renovation of the City of Port Arthur
Transit Service Building.
As was stated during the meeting and confirmed by both Butch Haas (Senior Building Inspector)
and Mark Mulliner (Fire Marshal), the original scope of work was not required to include a fire
suppression system under the 2006 International Building Code as adopted and used by the City
of Port Arthur during the design and review of the project at the time. The original project
received a permit in full compliance with the city's building code requirements and construction
had begun. While it was determined the project would have to be re -bid to meet the demands of
the FTA, the Transit Department requested the design team utilize that time to include a few
additional scope of work items as part of the revised bid documents to be issued to potential
bidders. The inclusion of the new automatic fire suppression system in the renovation of the
Transit Service Building was included during the re- bidding period in response to city moving to
adopt the 2012 International Building Code for all future projects. The bid documents as issued
on July 30, 2012 to the general contractors and resubmitted for permit includes the new fire
suppression system along with other requested additional scope of work items by the city.
As part of our previous construction administration services to the City of Port Arthur for the
Service Building, the design team reviewed all systems and products proposed by the general
contractor to be used and/or installed on this project to ensure full compliance with the Federal
Buy America Clause, the drawings and specifications. A record copy of the products is kept in
our office and an additional copy is transmitted to the Transit Department for their record, and a
final copy is kept by the general contractor on site for review at any time. This process will
continue in earnest once construction starts again. We are in contact with N & T Construction
(General Contractor) at this time to ensure submittal of the fire suppression system drawings by
the Sub - Contractor is made to the fire marshal to complete the permit process for the fire
protection system.
ss \\M: \Nelson Collaboranve \ CLIENTS \ City of Port Arthur- NO301\NO301 -C -11- 0002 \Drawings \Re - Package for
Ridding\ Specs \ CuyofPor rArthur_ Addmonal, SersicesPees_ lutomaticSponklerSysuar _101612.doc
1
lit The Nelson Collaborative
F'r:ayram Manayp. men!
CwsuzgProrr „loam¢yrerrr.,ni
A p:t K Ccrwr.;.
We will continue to work jointly with the city to observe, review and coordinate the work of the
construction team to ensure full compliance with the city's goals, federal construction clauses,
and the drawings and specifications. If we can be of any further assistance, or if you have any
questions, please do not hesitate to contact me at any time.
Sincerely,
Timothy Barnes, AIA
Director of Architecture
Email: timothy.barnes @propmg.com
cc:
Colleen Russell, Transit
Debra Ambroise, Transit
Butch Haas, Building Codes
Mark Mulliner, Fire Marshal
Valecia Tizeno, City Attorney
Mark Nelson, P2MG
City of Port Arthur
REVISED CONSTRUCTION SCHEDULE
Renovation of Transit Service Facility
TNC Project No. NO301 -C11 -002
Revised: October 16, 2012
Start Requested Revisions June 18, 2012
Construction Documents 95% Review July 2, 2012
Release for Invitation to Bid July 30, 2012
Pre -Bid Conference at 10:00 am (City Council Conference Room) August 16, 2012
Proposal Submissions due by 3:00 pm (City Secretary's Office) August 29, 2012
Recommendations 'to City of Port Arthur August 31, 2012
Award Construction Contract by City October 1, 2012
Construction to Begin October 22, 2012
Substantial Completion of Project / Owner Move In March 31, 2013
Punch List & Close -Out Complete April 30, 2013
cc: Mr. Mike Nelson, P2MG
Ms. Colleen Russell, Port Arthur
Mrs. Debra Ambroise, Port Arthur
Ms. Valecia Tizeno, Port Arthur
File 2B
M:\Nelson Collaborative \CLIENTS \City of Port Arthur- NO301\NO301 -C -11-0002 \TransitServiceCenter _Construction Schedule] 01612.doc
P.R. NO. 17304
09 /21 /12CWR
Page 5
EXHIBIT "B"
The Nelson Collaborative CHANGE ORDER NUMBER 1
a►cecr Job No. NO301-C-11-002
Program Management
Construction Management
A P2MG COMM).
CHANGE TO CONTRACT PRICE:
ORIGINAL CONTRACT PRICE: $72,000.00
CURRENT CONTRACT PRICE adjusted by previous CHANGE ORDER(S): $0.00
The CONTRACT PRICE due to this CHANGE ORDER will .increased] [decreased]
be by: $14,415.31 Dollars
The new CONTRACT PRICE, including this CHANGE ORDER, will be $86.415.31
CHANGE TO CONTRACT TIME:
ORIGINAL CONTRACT TIME: 300 Calendar Days
CURRENT CONTRACT TIME adjusted by previous CHANGE ORDER(S): 0 Days
CURRENT DATE OF COMPLETION: April 25, 2013
CONTRACT TIME due to this CHANGE ORDER will be increased by 0 Days
The New DATE OF COMPLETION: April 25, 2013
No other Terms and Conditions of the Contract are changed as a result of this Change
Order. Contractor's acceptance of Change Order relieves OWNER of any liability for
additional costs incurred by Contractor in his performance of the work covered by the
Change Order.
RECOMMENDED BY ARCHITECT: ACCEPTED BY:
f A
.4414:41 4111Pr
The Nelso Co aborative Transit Direct