HomeMy WebLinkAboutPR 13566: ALLCO, LTD MEMORANDUM
CITY OF PORT ARTHUR
UTILITY OPERATIONS DEPARTMENT
TO: Stephen Fitzgibbons, City Manager
FROM: Kelly Eldridge, Director of Utility Operations
DATE: May 17, 2006
SUBJECT: Proposed Resolution No. 13566
COMMENTS
RECOMMENDATION
I recommend that the City Council approve Proposed Resolution No. 13566 authorizing the
execution of Change Order No. Six to the contract between the City and ALLCO, Ltd., related to the
Wastewater Rehabilitation Project. This change order increases the total contract amount by $6,241.00
to $9,827,081.86, and does not increase contract time.
BACKGROUND
In February 2004, the City Council awarded a construction contract to ALLCO, Ltd. for the
Wastewater Rehabilitation Project, Pioneer Park and Griffing Park areas. This project is part of
Phase I of the City's wastewater system improvements program. It includes the replacement of 25+
miles of the City's sewer lines identified in the Sanitary Sewer Evaluation Survey.
Change Order No. Six amends the contract bid items to add certain required improvements to the
two lift stations constructed in Griffing Park. In particular, our consulting engineer made these
improvements for better access, including wider gates, additional concrete slab and fence, and
limestone drives.
We will forward this change order to the TWDB upon execution and anticipate their approval.
BUDGET/FISCAL EFFECT
Change Order No. Six increases the contract amount by $6,241.00 to $9,827,081.86.
STAFF/EMPLOYEE EFFECT
No anticipated effect on staffing. City staff will continue to monitor the progress of this project.
SUMMARY
! recommend that the City Council approve Proposed Resolution No. 13566 authorizing execution
of Change Order No. Six to the contract with ALLCO, Ltd.
P.R. No. 13566
0~/1~/06/aw
RESOLUTION NO.
A RESOLUTION AUTHORIZING THE EXECUTION OF CHANGE ORDER
NO. SIX TO THE CONTRACT BETWEEN THE CITY OF PORT ARTHUR
AND ALLCO, LTD, RELATED TO THE WASTEWATER REHABILITATION
PROJECT. (INCREASES THE CONTRACT AMOUNT BY $6,241.00)
ACCOUNT NO. 426-1625-532.83-00, PROJECT NO. 426ALL.
WHEREAS, the City Council of the City of Port Arthur has awarded the contract for the
Pioneer Park Area and Griffing Park Area Wastewater Rehabilitation Project to ALLCO, Ltd., in
Resolution No.04-038; and,
WHEREAS, Bob Shaw Consulting Engineers, Inc., as Owner's representative, has prepared,
reviewed, and recommends approval of Change Order No. Six, copy attached hereto and made a pan
hereof as Exhibit "A", for additional work not included in original project bid; increasing contract
amount by $6,241.00; NOW THEREFORE,
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF PORT ARTHUR:
THAT, the City Manager be authorized to execute Change Order No. Six (Exhibit A) to the
referenced contract, for a change in the scope of the work in the total amount of ($6,241.00); and,
THAT the total contract amount to be adjusted will be from Nine Million Seven Hundred
Eight Hundred Twenty Thousand Eight Hundred Forty and 86/100 Dollars ($9,820,840.86) to Nine
Million Eight Hundred Twenty-seven Thousand Eighty-one and 86/100 Dollars ($9,827,081.86);
and,
THAT the contract time will not be increased by this Change Order; and,
THAT no other conditions or covenants of the contract are changed or waived by this
Change Order; and,
THAT a copy of the caption of this Resolution be spread upon the Minutes of the City
Council.
P.IL No. 13566
05/1'7/06/aw
Page 2 of 2
READ, ADOPTED AND APPROVED THIS __ day of ,2006
at a Regular Meeting of the City Council of the City of Port Arthur, Texas, by the following vote:
AYES: Mayor ;
Councilmembers:
NOES:
Oscar G. Ortiz
Mayor
ATTEST: APPROVED AS TO FORM:
Evangeline Green Mark Sokolow
City Secretary City Attorney
APPROVED FOR ADMINISTRATION:
Stephen Fitzgibbons Kelly-Elc}~ic~g~ - ~
City Manager Director of Utility Operations
APPROVED AS TO AVAILABILITY OF FUNDING:
Rebecca Underhill
Director of Finance
426-1625-532.83-00, Project No. 426ALL
EXHIBIT A
BOB SHAW ~
Consulting Engineers
May 10, 2006
Mr. Keith Burrell L trr~vt~[~/,iZ~.
Allco, Ltd.
P. O. Box 3684
Beaumont, Texas 77704-36~4
Re: City of Po~ ~h~
Wastewater Collection System
Rehabilitation - Griffing Park
and Pioneer Park ~ea
Job No. CPA-0~
Dear Mr. Burrell:
Enclosed is Change Order No. 6 to the referenced project. If this meets your approval,
please have this document signed and attested and returned to me. I will then forward it to
the City of Port Arthur. After the City has executed the document, I will send it to the Texas
Water Development Board for their approval.
Sincerely,
Bob Shaw, P.E.
Bob Shaw Consulting Engineers
BS/cc
Enclosure
copy: d~lr. Kelly Eldridge - City of Port Arthur
4749 Twin Czty Highway, Suite 305 Port Arthur, Texas 77642 Phone: (409) 962-0263 Fax: (409) 963-3101
CHANGE ORDER NO. 6
PAGE 1 OF 2
DATE: May 10, 2006
AGREEMENT DATE: March 10, 2004
NAME OF PROJECT: Wastewater Collection System Rehabilitation Griffing Park and Pioneer Park Areas
OWNER: City of Port Arthur, Texas
CONTRACTOR: AIIco, Ltd.
The following changes are hereby made to the CONTRACT DOCUMENTS:
Add Improvements to Highland lift station for better access and
maintenance, including wider gate, additional fence, concrete
slab and limestone drive .............................................................. $ 2,919.00
Add Improvements to West Park lift station for better access and
maintenance, including wider gate, additional fence, concrete
slab and limestone drive ............................................................... $ 3,322.00
$ 6,241.00
CHANGE TO CONTRACT PRICE:
ORIGINAL CONTRACT PRICE: $9,203,324.71
CURRENT CONTRACT PRICE adjusted by previous CHANGE ORDER: $9,820,840.86
The CONTRACT PRICE due to this CHANGE ORDER will be increased by: $6,241.00
The new CONTRACT PRICE including this CHANGE ORDER will be: $9,827,081.86
CHANGE TO CONTRACT TIME:
ORIGINAL CONTRACT TIME: 800 Consecutive Calendar Days
CURRENT CONTRACT TIME adjusted by previous CHANGE ORDER: 958
CURRENT DATE OF COMPLETION: December 16, 2006
CONTRACT TIME due to this CHANGE ORDER will be increased by: 0 Calendar Days
New CONTRACT TIME including this CHANGE ORDER will be 958 calendar days
The DATE FOR COMPLETION of all work will be December 16, 2006.
DATE: May 10, 2006 PAGE 2 OF 2
CI-{AAIGE ORDER NO,: 8
NAME OF PROJECT: Wastewater Collection System Rehabilitation
Griffing Park and Pioneer Park A~'ees
No other Ten'Da and Conditions of the Contract are changed es a result of this Change Order,
Contractor's acceptance of Change Order relieves City of any liability for additional costs incurred
by Contractor in his performance of the WOrk covered by the Change Order.
RECOMMENDED BY: REQUESTED 'BY:
Bob Shaw Consulting Engineers AIIco, Ltd.
CONTRACTOR, OFFICER, OR OWNER
CORPORATE SEAL
ORDERED BY:
CITY OF PORT ARTHUR
ACCEPTED BY:
CITY OF PORT ARTHUR, MAYOR
CITY OF PORT ARTHUR, MANAGER
CiTY SECRETARY
CITY SEAL
CITYATTORNEY
APPROVEDA$ TO FORM