COUNCIL ACTION MEMO
TO Floyd T. Johnson, City Manager
FROM John A. Comeaux, P.E, Assistant City Manager - Operations
SUBJECT P.R. #17631 — CO #01: N. & T. Construction Co., Inc. for the Renovation of the
Downtown Pavillion
DATE 26 March 2013
RECOMMENDATION:
I recommend that the City Council approve Proposed Resolution No. 17631, authorizing Change
Order #01 in extending the contract by 80 days bringing the total time to 210 days.
BACKGROUND:
The City Council previously executed a contract with N. & T. Construction Co., Inc. for the
Renovation of the Downtown Pavillion. The original time was one hundred thirty (130) days.
Change Order #01 will increase the contract time by eighty (80) days bringing the total contract
time to two hundred ten days (210) days with bid price amount remaining at $453,000.
BUDGETARY /FISCAL EFFECT:
Funding is available in 120 - 1429 - 582 -59.06 and 001 - 1003 - 512.59.00, Project M12005
EMPLOYEE /STAFF EFFECT:
None.
SUMMARY
I recommend that the City Council approve Proposed Resolution No. 17631, authorizing Change
Order #01 in extending the contract by 80 days bringing the total time to 210 days.
John A. Comeaux, P.E.
Assistant City Manager- Operations
JAC /rtb
S: \electrical_sec \ROE \Downtown Pavilion \CO1 -N &T Time Extension \CAM -001
P.R. 17631
03/26/13 rtb
RESOLUTION NO.
A RESOLUTION AUTHORIZING THE CITY MANAGER TO EXECUTE
CHANGE ORDER NO. 01 TO THE CONTRACT BETWEEN THE CITY
OF PORT ARTHUR AND N. & T. CONSTRUCTION CO., INC. FOR
THE RENOVATION TO THE DOWNTOWN PAVILION, INCREASING
THE CONTRACT TIME BY EIGHTY (80) DAYS TO A NEW TOTAL OF
TWO HUNDRED TEN (210) DAYS. ACCOUNT # 120- 1429 -582-
59.06 AND 001 - 1003 - 512.59.00, PROJECT M12005.
WHEREAS, on 15 October 2012, the City entered into a contract with N. & T.
Construction Co., Inc. for the Renovation for the Downtown Pavilion in the amount of
$453,000; and,
WHEREAS, the contract time commenced on November 12, 2012 and terminate
on May 27, 2013; and,
WHEREAS, N. & T. Construction Co., Inc. has requested a change order
increasing the original contract time by eighty (80) days to a new contract term of two
hundred ten (210) days due to lost days associated with changes made in ASI #2 which
includes additional structural steel, additional labor to erect the structural steel, and
additional supervision, attached hereto as Exhibit "A ", and,
WHEREAS, approval of Change Order No. 01 increasing the contract time to
two hundred ten (210) days is herein deemed an appropriate action; now, therefore,
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF PORT
ARTHUR:
THAT, the facts and opinions in the preamble are true and correct; and,
THAT, Change Order No. 01 is herein approved and the City Manager is
authorized to execute said Change Order; and,
P.R. 17631
03/26/13 rtb
THAT, a copy of the caption of this Resolution be spread upon the Minutes of
the City Council.
READ, ADOPTED AND APPROVED this the day of , A.D. 2013
at a meeting of the City of Port Arthur, Texas by the following vote:
Ayes: Mayor:
Councilmembers:
Noes:
Mayor
Attest:
Sherri Bellard
City Secretary
APPROVED A TO FORM: APPROVED FOR ADMINISTRATION:
Va
Valecia eno Floyd T. Johnson
City Attorney City Manager
APPROVED AS FOR AVAILABILITY OF
FUNDS:
Deborah Echols, CPA John A. Comeaux, P.E.
Director of Finance Assistant City Manager - Operations
4/ ' di�4 sT-
S awna Tubbs, CPPB
Purchasing Manager
P.R. 17631
03/26/13 rtb
EXHIBIT A
Construction Co., Inc
N GENERAL CONTRACTORS
CONSTRUCTION MANAGERS
March 26, 2013
City of Port Arthur
444 4` Street
4 Floor
Port Arthur, TX 77640
Re: Port Arthur Pavilion Renovations
Port Arthur, Texas
N &T Construction Co., Inc. is requesting an additional 80 days to be added to our contract time
for lost days associated with ASI #2. The changes made in ASI #2 include additional structural
steel, additional labor to erect the structural steel, and additional supervision. Our revised
completion date would be August 15, 2013.
If this is acceptable, please incorporate these days into our contract.
Thank •
/ �
/
Lauren Williams
Project Manager
CHANGE ORDER NO. 01
DATE: 26 March, 2013
ORIGINAL AGREEMENT DATE: 15 October 2012
N. & T. CONSTRUCTION CO., INC.
PROJECT DESCRIPTION: Renovation for the Downtown Pavilion
CHANGE TO CONTRACT TERM:
ORIGINAL CONTRACT term: 130 Days
CURRENT CONTRACT TERM (adjusted by previous CHANGE ORDER): N/A
The Contract Amount due to this CHANGE ORDER will be (increased /decreased) by:
N/A
The new CONTRACT TERM including the CHANGE ORDER will be: 210 Days
CHANGE TO CONTRACT AMOUNT:
ORIGINAL CONTRACT amount: $453,000.00
CURRENT CONTRACT PRICE (adjusted by previous CHANGE ORDER): N/A
The Contract Amount due to this CHANGE ORDER will be (increased /decreased) by:
N/A
The new CONTRACT AMOUNT including the CHANGE ORDER will be: N/A
N. & T. Construction Co., Inc.:
Signature
Charlie Jabbia
Printed Name
CITY OF PORT ARTHUR
Floyd T. Johnson
City Manager
S: \electrical_sec \ROE \Downtown Pavilion \CO1 -N &T Time Extension \CO1 Form