HomeMy WebLinkAboutPR 17694: CHANGE ORDER 01 TO CONTRACT WITH L&L GENERAL CONTRACTORS FOR CUNSTRUCTION OF TRANSIT AUTO-SCRUBBER CITY OF PORT ARTHUR
TRANSIT DEPARTMENT
M emo
TO: Deborah Echols, Finance Director
C: Shawna Tubbs, Purchasing Manager
Val Tizeno, City Attorney
FROM: COLLEEN RUSSELL, DIRECTOR OF TRANSIT
SUBJECT: Justification for Large part of the change order was the need for the pit- trench system
DATE: July 18, 2013
SUMMARY: The Change order showed an increase due to the need for a pit- trench not in the original
bid or drawings. The quote shows the reasonableness of the pricing and the cost of all quotes obtained
by L & L General Contractors, Beaumont, TX. It is recommended therefore, that P.R. 17694 be approved
in order for the auto - scrubber work to be completed and be incompliance with the BUY AMERICA
criteria and justification warranted by the Federal Transit Administration (FTA).
BACKGROUND: This resolution justifies that L & L General Contractors got the best buy for the pit that
was missing from the drawings with an understanding that this will not be supplied by the auto - scrubber
vendor, the best pricing on the pit was obtained by the contractor as construction of the auto - scrubber
progressed. In doing so, the quotes obtained are shown as said proof, as all other changes would have
meant a price reduction, the pit- trench increased the change order. This is justification that the $8778
was the best price and with compilation of data from the other changes , Change Order 1 increased the
original total from $791,000 to $ 795,616.50. As required for FTA overview a justification with
reasoning and quotes are provided as to the Change Order's need and cost.
Best Regards,
e4 e ,n, C
Ms. Colleen Russell, Transit Directo
P.R. No. 17694
6/22/13 CWR
RESOLUTION NO.
A RESOLUTION AUTHORIZING THE CITY MANAGER TO EXECUTE
CHANGE ORDER 01 TO THE CONTRACT BETWEEN THE CITY OF
PORT ARTHUR AND GADV, INC. DBA L & L GENERAL
CONTRACTORS OF BEAUMONT, TEXAS FOR THE CONSTRUCTION
OF THE TRANSIT AUTO SCRUBBER FACILITY, INCREASING THE
CONTRACT AMOUNT BY $4,615.50 TO A NEW TOTAL OF $795,616.50
(ACCOUNT NO. 402 - 1508 - 561.82 -00, GRANT NOS. TX -96 -X042, TX -96-
X040, TX -96 -X859, ALI NOS. 11.44.02 AND 11.44.03).
WHEREAS, per Resolution No. 13 -122, the City Council entered into a
contract with GADV, Inc., dba L & L General Contractors of Beaumont, Texas in the amount of
$791,000 for the construction of the Auto Scrubber (bus wash) facility for the Transit
Department; and
WHEREAS, Port Arthur Transit is requesting that the City Council approve
Change Order 01 increasing L & L General Contractors' contract in the amount of $4,616.50 to a
new total of $795, 616.50 for additional cost of the auto scrubber pit and labor attached hereto as
Exhibit "A "; and
WHEREAS, the City's portion of the construction increase is 20% or $923.30, and the
Federal Transit Administration will cover 80% or $3,963.20 of the additional cost, which will be
taken from grant TX90 -X590 as (capital funds for construction); and
WHEREAS, the majority the remaining funds will be covered by (ARRA) The American
Reinvestment and Recovery Act.
NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY
OF PORT ARTHUR:
P.R. NO. 17694
Page 2
THAT, the facts and opinions in the preamble are true and correct.
THAT, the City Manager is authorized to execute said Change Order, in substantially the
same form as attached as Exhibit "A ".
THAT, the increase payments are to be accounted against grant funds in TX90 -X859 and
other funds against grant TX96 -X042 that are capital funds. However, this payment will be
made solely from TX90 -859 funds that are apportioned as 80:20 per the small urban 5307
funding of 49CFR with 80 percent being reimbursable to the City.
THAT, a copy of the caption of this Resolution be spread upon the Minutes of the City
Council.
READ, ADOPTED AND APPROVED this 9th day of July A.D. 2013, at a Regular
Meeting of the City Council of the City of Port Arthur, Texas, by the following vote:
AYES:
MAYOR
COUNCILMEMBERS:
NOES:
Mayor
ATTEST:
City Secretary
P.R. NO. 17694
Page 3
APPROVED AS TO FORM:
City Attorne
Assistant City Manager- Project Manager
APPROVED FOR ADMINISTRATION:
City Manager
c 0
Director of Trans
APPROVED AS TO AVAILABILITY OF FUNDS:
0
Director of Finance (401- 1509 - 561.82.00)
Purchasing Manager
P.R. NO. 17694
Page 4
EXHIBIT "A"
(Change Order 1 and Explanation for
L & L Contractors, of Beaumont, TX)
f
_ rt =- = Document G701 aai 2001 if
I . _ _ Change Order
• . and = f CHANGE ORDER NUMBER: 001 OWNER:
' of Port 2 I ur Trenstt : us Wash DATE: June 17, 2013 ARCHITECT: Facility '
32 Dallas Avenue ! CONTRACTOR:' ►:ii
. Port Arthur, Texas 77641
TO CONTRACTO R , (Name a`irdaddress): ARCHITECT'S PROJECT NUMBER: NO301 -C -12-003 FIELD' 0 L & L General C 1 CONTRACT DATE: April 1, 2013 OTHER: El
11988 FM 365 West Road
i CONTRACT FOR: General Construction
, Beaumont, Texas 77705 t
I. \ "THE CONTRACT IS CHANGED AS FOLLOWS:
\ \ 1 (Include,.ivhere applicable anj undisputed amount attributable to previously executed Construction Change Directives)
, ) Item 1:,Providingexterior plsistet in` lieu of masonry wainscot
6
Item 2: Providing 400 amp disconnect and self- contained meter can as requested by Entergy
{ ' 1 Item 3: Providing concrete pits at Equipment Room
\ hem 4: Providing trench for ender.chasis Wash cabling
" / /'
' 1 ,
/ f ,!
J /' —� t The original Contract C_JLS,I was �. $ 791,000.'00
. .The net change by previously authorized Change Orders $ 0.00
The Contract Stun priorr. to this Change Order was $ 791,000.00
The Contract Sum will be intr by this Change Order in the amount of $ 4,616.50
The new Contract Sum including this Change Order will be $ 795,616.50
`�
The Contract Time will be increased by Zero (0) days.
The date of Substantial Completion as of the date of this Change Order therefore is September 8, 2013
' TOTE: This Change Order`d�ies not include changes ih the Contract Sum, Contract Time or Guaranteed Maximum Price which have
N been authorized by Construction Change Directive until the cost and time have been agreed upon by both the Owner and
Contractor, in which case a Change Order iitxecuted to supersede the Construction Change Directive.
\\ NOT, VALID - UNTIL E - BY THE ARCHITECT CONTRACTOR AND OWNER.
e ' i ` The N C L & L General Contractors City of Part Arthur
u 1 ARCHITECT (Finn name) CONTRACTOR (Finn name) OWNER (Firm name)
`5450 NortIvest - Ce itral Drive, #330, 11988 .FM 365 West Road 444 4 Street
' i Houston, Texas 77092N Beaumont, Texas 77705 Port Arthur, Texas 77641
' AD• - ESS ` i ADDRESS ADDRESS
F a-41LOO . .4 ■ . i - - BY ( Signature /r BY (Signature) BY (Signature)
KG. mot !' : arnes AIA Mr. Kirk LeBlanc Mr. Floyd Johnson
(Typed name) (Typed name) (Typed name)
1
June 11, 2013
DATE i DATE DATE
MA boeunnen t 0701" —2001. Copyright 0 1979, 1987, 2000 and 20D1 by The American Institute of Architects. All rights reserved. WARNING: This NO
Ootuansrrt Is protected 'by U.th. Copyright Law - old Innis retUbti*1 Tretdlie. Unauthorized tspsodar:tion DT dlstrths:Ow f dnia AIA' DOcumsrrt, or arty i
portion of it, may rsauft in HMO civil and criminal penalties, and wet be prosecuted to the mbw
timm *Awn pout* under the law. This document was
produced by AIA software at 09:47:01 on 07/18/2013 under Order No.1044780190 1 which expires on 02126/2014, and is not for resale. (1718707819)
User Notes:
1011T he Nelson Collaborative
Ac
Engineering
Pin Management
Construction Management
AMOOaap.ny
Change Proposal Request
Project: Transit Bus Wash Facility Request No.: 01
City of Port Arthur
TNC Project No.: NO301 -C42 -003 Date: April 22.2013
To: L & L General Contractors
11988 FM 365 West
Beaumont, Texas 77705
Email: landlgeneralcontractors.com
Attention: Mr. Kirk LeBlanc
This is a request for an itemized quotation in the Contract Sum and/or time for the following proposed modifications to the
Contract Documents.
This request is not an authorization for changes or addition al work and it does not revise the contract price.
Description of Work:
1. Provide credit to Owner to delete King Size Brick at exterior elevation
2. Provide credit to Owner to delete 2" Rigid Insulation board at exterior elevation
3. Provide credit to Owner to delete 2" metal framing stud at exterior elevation
4. Provide credit to Owner to delete %s" gypsum sheathing at exterior elevation
5. Provide scheduled 1" plaster w/ acrylic finish on metal lath and damproofing on existing cmu
back -up wall
Attachments: The Nelson Collaborative Drawing dated April 22, 2013.
This change proposal was initiated at the request of the:
[ ] Owner [X] Architect [ ] Engineer [ ] Contractor [ ] Other
dioseti„. i3demeao.
Timothy Bames, AIA
Project Manager
cc: Mrs. Debra Ambroise, Port Arthur
Mr. Joseph Enciso, P2MG
File 5B
L &L General Contractors
11988 FM 365 West Rd.
Beaumont, TX 77705
Ph: 409- 796 -1344
Fax: 409 - 796 -1341
Date: 4/30/2013
Contract Name: City of Port Arthur — Bus Wash Facility
Change Order #: 1- A
You are hereby authorized to proceed with the following work:
1. Add for 400 amp 480 volt non fused disconnect ($3,643.50)
2. Add for (2) Labor for installation of 400 amp disconnect. ( $104.50)
3. Add for 320 amp meter can and lugs. ($488.00)
4. Add for (2) Labor for 320 amp meter can ($104.50)
5. Deduct for CT can. ($396.00)
6. Deduct for J box and rubber coated lugs ($440.50)
7. Deduct (2) Labor for installation of J box ($104.50)
8. Deduct (2) Labor for installation of CT can and Entergy furnished Meter can ($104.50)
OHP 10% (329.50)
NOTE: When using a CT can Entergy supplies the meter as part of their service, therefore a meter
was never included in the base bid.
This change order reflects:
XX a cost increase of $ 3.624.50
a cost reduction of $
no change in cost
All other terms, conditions and covenants of the aforementioned contract remain unchanged.
Owner Date
Representative
4/30/2013
L &L General Contractors Date
Representative
L &L General Contractors
11988 FM 365 West Rd.
Beaumont, TX 77705
Ph: 409 - 796 -1344
Fax: 409 - 796 -1341
Date: 5/6/2013
Contract Name: City of Port Arthur — Bus Wash Facility
Change Order #: 1— lb
You are hereby authorized to proceed with the following work:
1.) Credit Materials/Labor to delete King Size Brick at exterior elevation
Materials 2,065.00
Labor 3,558.00
OH &P 600.00
DEDUCT 6,223.00
2.) Credit Materials/Labor to delete 2" metal framing studs, 2" Rigid
Insulation board and 1/2" gypsum sheathing at exterior elevation
Materials 3,008.00
Labor 5,113.00
OH &P 900.00
DEDUCT 9,021.00
3.) Provide 1" plaster w/ acrylic finish on metal lath and damproofing
on existing CMU back -up wall.
Materials 2,300.00
Labor 3,580.00
OH &P 588.00
ADD 6,468.00
This change order reflects:
a cost increase of $
XX a cost reduction of $ 8,776.00
no change in cost
All other terms, conditions and covenants of the aforementioned contract remain unchanged.
Owner Date
Representative
5/6/2013
L &L General Contractors Date
Representative
at L &L on
11988 FM General 365 West Rd tractors
Beaumont, TX 77705
Ph: 409- 796 -1344
Fax: 409 - 796 -1341
Date: 6/3/2013
Contract Name: City of Port Arthur — Bus Wash Facility
Change Order #: 1 —C
You are hereby authorized to proceed with the following work:
Additional 6 "x6" trench for the high pressure chassis wash with grating.
Materials 750.00
Labor 150.00
OH &P 90.00
This change order reflects:
XX a cost increase of $ 990.00
a cost reduction of $
no change in cost
All other terms, conditions and covenants of the aforementioned contract remain unchanged.
Owner Date
Representative
6/3/2013_
L &L General Contractors Date
Representative
L1 ee Con
11988 &L G FM n 365 ral West Rd. tractors
Beaumont, TX 77705
Ph: 409 - 796 -1344
Fax: 409 - 796 -1341
Date: 5/23/2013
Contract Name: City of Port Arthur — Bus Wash Facility
Change Order #: 1 .- D
You are hereby authorized to proceed with the following work:
Installations of Concrete Pit 1 and Pit 2 with Plumbing
Materials 5,750.00
Labor 2,630.00
OH &P 798.00
This change order reflects:
XX a cost increase of $ 8,778.00
a cost reduction of $
no change in cost
All other terms, conditions and covenants of the aforementioned contract remain unchanged.
Owner Date
Representative
5/23/2013_
L &L General Contractors Date
Representative
May 20, 2013
Chris Comalander Construction
12392 Fm 365 Bmt, TX 77705
409 - 284 -2102
Proposal
City of Port Arthur Bus Wash Facility
244 Procter St
Port Arthur, TX
Furnish and install (2) precast concrete catch basins 48 "x48 "x72" with manhole cover:
Concrete catch basins will be constructed of 4500psi concrete with #3 rebar at 8" on
center each way.
Delivered and installed at the elevation determined by L &L General Contractors at the
City of Port Arthur's bus wash facility located at 244 Procter St.
Exclusions:
Any plumbing /electrical.
Any backfilling.
Total Price $10,283.00
Excludes Sales tax
Payment due net 30. Proposed price good for 60 days.
Thanks for the opportunity to bid this contract. Please feel free to contact me if I may be of
further assistance.
Chris Comalander
Outback Construction
7459 Fm 365 Bmt, TX 77705
409 - 796 -2121
Bid Quote
May 23, 2013
L &L General Contractors
Job:
PA Bus Wash
(2) 4500 psi concrete water catch basins 4'x4'x6'
(2) Cast iron grates
(1) Deliver and install
Piping, tie -ins, etc. to be done by others.
Total Price $11,007.00
Does not include any applicable tax
Full payment upon delivery and installation.
Bradley Burrell
Owner Outback Construction