HomeMy WebLinkAboutPR 18250: CHANGE ORDER 3 EXCAVATORS & CONSTRUCTORS, LTD AND CHANGE ORDER 3 WITH GENERAL LAND OFFICE FOR HWY 87 INCREASING THE CONTRACT BY 17 DAYS MEMORANDUM
CITY OF PORT ARTHUR
UTILITY OPERATIONS DEPARTMENT
TO: John A. Comeaux P.E., Interim City Manager
FROM: John A. Tomplait, Assistant Director of Utility Operations
DATE: March 24, 2014
RE: Proposed Resolution No. 18250
RECOMMENDATION
1 recommend that the City Council approve Proposed Resolution No. 18250
authorizing the execution of Change Order number three (3) for the Highway 87 Water
Transmission Line Project with Excavators & Constructors, LTD., of Port Arthur,
Texas, this change order modifies the contract term that includes a time extension of
seventeen (17) days due to rain delays. This will bring the total time of the project to 299
days, ending May 14 2014.
BACKGROUND
The change order is for the Highway 87 water line project approved in Resolution No.
13 -294. A Hurricane Recovery Grant administered by the Texas General Land Office is
funding this project. This change order is for a time only extension. At this time the
project is approximately 87% complete, with approximately 57% of the contract time
used based on the contractors rate of production.
BUDGET /FISCAL EFFECT
This project will be funded through the GLO Project No. I21 SPW, Account No. 144-
1201- 532.59 -00.
SUMMARY
I recommend that the City Council approve Proposed Resolution No.18250.
P. R. No. 18250
03/24/14 JT
RESOLUTION NO.
A RESOLUTION AUTHORIZING THE CITY MANAGER
TO EXECUTE CHANGE ORDER NO. 3 BETWEEN THE
CITY OF PORT ARTHUR AND EXCAVATORS &
CONSTRUCTORS, LTD. AND CHANGE ORDER NO. 3
WITH THE GENERAL LAND OFFICE (GLO) FOR THE
HIGHWAY 87 WATER TRANSMISSION LINE
PROJECT, INCREASING THE CONTRACT TERM BY
SEVENTEEN (17) DAYS DUE TO RAIN DELAYS TO A
NEW TERM OF 299 DAYS.
WHEREAS, per Resolution No. 13 -294, the City entered into a contract for the
installation of a water transmission line along Highway 87 South with Excavators &
Constructors, Ltd. for the contract amount of $2,318,702.50; and,
WHEREAS, per Resolution No. 13 -400, the City Council authorized Change Order No.
1 between the City and Excavators & Constructors, Ltd and Change Order No. 1 with the GLO
for the Hwy 87 water transmission line tracer wire system increasing the contract amount by
$64,286.50 to a new total of $2,382,989; and,
WHEREAS, per Resolution No. 14 -043, the City Council authorized Change Order No.
2 between the City and Excavators & Constructors, Ltd and Change Order No. 2 with the GLO
that the Texas Department of Transportation has requested six (6) fire hydrants be replaced with
underground blow -off hydrants for the installation of a Water Transmission Line along Highway
87 South increasing the contract amount by $23,760.00 to a new total of $2,406,749.00,
increasing the contract time by twelve (12) days to a total of 282 days; and,
WHEREAS, Arceneaux & Gates Consulting Engineers, has requested Change Order No.
3 for a seventeen (17) day time extension with Excavators & Constructors, Ltd and Change
Order No. 3 with the GLO, the change order has been evaluated by Arceneaux & Gates
Consulting Engineers, and the Utility Operations Department (attached hereto as Exhibit "A ");
NOW THEREFORE,
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF PORT
ARTHUR:
P. R. No. 18250
03/24/14 JT
Page 2
THAT, the City Manager of the City of Port Arthur is hereby authorized and directed to
execute, on behalf of the City of Port Arthur, Change Order No. 3 between the CITY OF PORT
ARTHUR and Excavators & Constructors, LTD. and Change Order No. 3 with the GLO for the
increased contract time of seventeen (17) days for a new contract time of 299 days attached
hereto as Exhibit "A"; and,
THAT, this project will be funded by the Texas General Land Office, in Project No.
I21 SPW, Account No. 144 - 1201 - 532.59 -00; and,
THAT a copy of the caption of this resolution be spread upon the minutes of the City
Council.
READ, ADOPTED AND APPROVED THIS day of , 2014
at a Regular Meeting of the City Council of the City of Port Arthur, Texas, by the following
votes:
AYES: Mayor
Councilmembers:
NOES:
Deloris Prince
Mayor
P. R. No. 18250
03/24/14 JT
Page 3
ATTEST: APPROVED AS TO FORM:
Sherri Bellard Valecia Tizeno
City Secretary City Attorney
APPROVED FOR ADMINISTRATION:
/
John A. Comeaux, P.E. Shawna Tubbs, CPPB
Interim City Manager Purchasing Manager
Ind 1,,)
Jo A. Tomp it
Ass' tant Director of Utility Operations
APPROVED AS TO AVAILABILITY OF
FUNDS: N/A
•
Exhibit "A"
(Proposal for Contract Addition)
ARCENEAUX & GATES
ARCENEAUX
Consulting Engineers, & g Inc. 9
GATES A Burrow Global Company
Engineers • Surveyors • Planners
March 18, 2014
Mr. John Tomplait
Assistant Director of Water Utilities
City of Port Arthur
444 Fourth Street
Port Arthur, Texas 77640
RE: Change Order No, 3
Highway 87 Wa ter Line
Job No CPA -700
Dear Mr. Tomplait:
Attached is Change Order No. 3 for the Highway 87 Water Line. This change order is to
increase the contract time by 17 days. The contractor has requested a time extension of
17 days due to inclement weather conditions. I recommend that the City of Port Arthur
authorize this change to the contract. I have attached Change Order No. 3 which
modifies the contract to reflect this change for your consideration and action. Should
you have any questions or require additional information, please contact our office.
Very truly yours,
ARCENEAUX & GATES CONSULTING ENGINEERS, INC.,
A Burrow Global Company
TEXAS REGISTERED ENGINEERIN FIRM F -30
eestan Cole, PE
Staff Engineer
2901 Turtle Creek Dr., Suite 320 Port Arthur, TX 77642 Phone: 409/724 -7888 Fax: 409/724 -1447
ED
ARCENEAUX
GATES
CONSULTING
ENGINEERS, INC.
CHANGE ORDER No 3
DATE: March 18, 2014 JOB NO. CPA -700
AGREEMENT DATE: July 17, 2013
NAME OF PROJECT: HIGHWAY 87 WATERLINE
OWNER: CITY of PORT ARTHUR
CONTRACTOR: EXCAVATORS & CONSTRUCTORS, LTD.
The following changes are hereby made to the CONTRACT DOCUMENTS:
1. Add the following Items to the Contract and Scope of Work:
a. Increase contract time by 17 days
CHANGE ORDER NO. 3
March 17, 2014
ARCENEAUX Job No. CPA -700, Contract No. 1
GATES
CONSULTING
ENGINEERS, INC.
CHANGE TO CONTRACT PRICE:
ORIGINAL CONTRACT PRICE: $2,318,702.50
CURRENT CONTRACT PRICE adjusted by previous CHANGE ORDER(S): $2,406,749.00
The CONTRACT PRICE due to this CHANGE ORDER will be [increased]
[decreased]
by: Dollars
The new CONTRACT PRICE, including this CHANGE ORDER, will be $2,406,749.00
CHANGE TO CONTRACT TIME:
ORIGINAL CONTRACT TIME: 270 Calendar Days
CURRENT CONTRACT TIME adjusted by previous CHANGE ORDER: 282 Calendar Days
CURRENT DATE OF COMPLETION: April 15, 2014
CONTRACT TIME due to this CHANGE ORDER will be increased by 17 Days
The New DATE OF COMPLETION: May 14, 2014
No other Terms and Conditions of the Contract are changed as a result of this Change Order.
Contractor's acceptance of Change Order relieves OWNER of any liability for additional costs
incurred by Contractor in his performance of the work covered by the Change Order.
RECOMMENDED BY ENGINEER: ACCEPTED BY:
_
ARCENEAUX & GATES [CONTR - OR,2FFICER R OWNER]
CONSULTING ENGINEERS, INC. EXCAVATORS & CONSTRUCTORS, LTD.
ACCEPTED BY:
CITY of PORT ARTHUR
2 of 2
e 11/� o
P kskOmitt, Texas General Land Office
_ Disaster Recovery
j ..
eST latis HEo Y��G
Construction Contract Change Order Request Form
Engineer: Owner (Contractor Locality): Contractor:
Excavators & Constructors, LTD.
Aceneaux & Gates Engineers, Inc., City of Port Arthur
6601 Proctor Ext.
A Burrow Global Company 4th
2901 Turtle Creek Dr., Suite 320 444 4 Street Port Arthur, TX 77642
Port Arthur, TX 77642
Port Arthur, TX 77642
Phone No.:409- 983 -8100 Agreement Date:
Phone No.: 409 - 724 -7888
July 17,2013
Phone No.:409- 962 -2677
Contract For (Project Description):
Date: March 10, 2014 GLO Contract No.:
Project Code No.: P21105 Highway 87 Water Line 12- 305 - 025 -6542
Bid Package No.. 4 Change Order No.: 3
You are hereby requested to comply with the following changes from the contract plans and specifications:
Item Description of Changes: Quantities, Units, Unit Prices, Decrease in Increase in
No. Change in Completion Scheduled, Etc. Contract Price Contract Price
Increase contract time by 17 days
Construction Contract Change Order Request Form Page 1 of 3
CDBG Disaster Recovery Program May 2012
Change in Contract Price Change in Contract Time (Calendar Days)
Original Contract Price: $ 2,318,702.50 Original Contract Time: 270 days
Previous Change Order(s): Net Change From Previous
No. 1 to No. 2 $ 88,046.50 Change Orders: 12 days
Contract Price Prior to Contract Time Prior to
this Change Order: $ 2,406,749.00 this Change Order: 282 days
Net Increase /Decrease of Net Increase /D°�ase of
this Change Order: $ this Change Order: 17 days
Contract Price With all Contract Time With all
Approved Change Orders: $ 2,406,749.00 Change Orders: 299 days
Cumulative Percent Change in Contract Price ( + / -): Grantee Contract End Date:
3.8% (mm /dd /yy) 12 /31 /2015
Construction Contract Start Date: Construction Contract End Date:
ly
(mm /dd /yy) 8 /19 /2013 (mm /dd /yy) 5 /14 /203 KC
Reimbursements of costs included in this change order are subject to review by the GLO -DR program.
* This document may be executed prior to submission for GLO -DR program review, but all parties
involved will be held responsible if the change order or the amendment warranted as a result of
this change order is not in compliance with CDBG or HUD requirements.
RECOMME ED: APPROVED: ACCEPTED.
By: By: By: i ..
ENGINEER OWNER CONTR
Date: 3-/R /y Date: Date: 3 � 8 - i
Construction Contract Change Order Request Form Page 2 of 3
CDBG Disaster Recovery Program May 2012
JUSTIFICATION FOR CHANGE
1. Will this Change Order increase or decrease
the number of beneficiaries? ❑ Increase ❑ Decrease El No Change
If there is a change, how many beneficiaries will be affected? Total L/M
2. Effect of this change on scope of work: E1 Increase ❑ Decrease ❑ No Change
3. Effect on operation and maintenance costs: ❑ Increase ❑ Decrease 0 No Change
4. Are all prices in the change order dependent upon unit prices
found in the original bid? ❑ Yes ❑ No
If "No ", explain:
5. Has this change created new circumstances or environmental
conditions which may affect the project's impact, such as
concealed or unexpected conditions discovered during actual
construction? ❑ Yes 0 No
If "Yes ", is an Environmental Re- assessment required?
6. Is the Texas Commission on Environmental Quality (TCEQ)
clearance still valid? (if applicable) El Yes ❑ No
7. Is the TCEQ permit approval still valid? (sewer projects only) ❑ Yes ❑ No
8. Are the handicapped access requirements /approval
still valid? (if applicable) ❑ Yes ❑ No
9. Are other Disaster Recovery contractual special condition clearance
still valid? 0 Yes ❑ No
(If no, specify):
NOTE:
* Generally, a cumulative change in the contract price in excess of 25% cannot
be reviewed (18% decrease for counties).
Construction Contract Change Order Request Form Page 3 of 3
CDBG Disaster Recovery Program May 2012