HomeMy WebLinkAboutPR 18251: CHANGE ORDER NO. 1 WITH PLACO, LTD SABINE PASS METERING FACILITY, INCREASE 22 DAYS MEMORANDUM CITY OF PORT ARTHUR UTILITY OPERATIONS DEPARTMENT TO: John A. Comeaux P.E., Interim City Manager FROM: John A. Tomplait, Assistant Director of Utility Operations DATE: March 24, 2014 RE: Proposed Resolution No. 18251 RECOMMENDATION 1 recommend that the City Council approve Proposed Resolution No. 18251 authorizing the execution of Change Order number one (1) for the Sabine Pass Metering Facility with Placo, Ltd., of Lumberton, Texas, this change order modifies the contract term that includes a time extension of twenty -two (22) days due to inclement weather conditions. This will bring the total time of the project to 112 days, ending April 26, 2014. BACKGROUND The change order is for the construction of a metering station adjacent to the Sabine Pass Standpipe. This is required to accurately meter consumption from the Sabine Pass side to the Sabine Pass Liquefaction /Cheniere LNG facility. The project includes two large City -owned meters and the required backflow prevention devices. The project was approved in Resolution No. 13-493 for the amount of $115,000.00 and a ninety (90) day contract term. This change order is for a time only extension. At this time the project is approximately 10% complete, with approximately 60% of the contract time used based on the contractors rate of production. BUDGET /FISCAL EFFECT This project will be funded through Account No. 429- 1258 - 532.59 -00, Project No. WSI001 • SUMMARY I recommend that the City Council approve Proposed Resolution No.18251. P. R. No. 18251 03/24/14 JT RESOLUTION NO. A RESOLUTION AUTHORIZING THE CITY MANAGER TO EXECUTE CHANGE ORDER NO. 1 BETWEEN THE CITY OF PORT ARTHUR AND PLACO, LTD; FOR THE SABINE PASS METERING FACILITY, INCREASING THE CONTRACT TIME BY TWENTY -TWO (22) DAYS DUE TO INCLEMENT WEATHER CONDITIONS TO A NEW TERM OF 112 DAYS. WHEREAS, per Resolution No. 12 -523, the City entered into a contract for the installation of a Metering Facility to meter potable water from Sabine Pass to the Sabine Pass Liquefaction LNG facility in the amount of $115,000.00 with a contract term of ninety (90) days; and WHEREAS, an additional 22 days is requested by Placo, Ltd., to complete the additional work specified in their contract for the Sabine Pass Metering Facility with a new completion date of April 26, 2014; and WHEREAS, Arceneaux & Gates Consulting Engineers, has requested Change Order No. 1 increasing the contract time by an additional 22 days to a new contract term of 112 days with Placo Ltd. And the change order has been evaluated by Arceneaux & Gates Consulting Engineers, and the Utility Operations Department (attached hereto as Exhibit "A "); NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF PORT ARTHUR: THAT, the City Manager of the City of Port Arthur is hereby authorized and directed to execute, on behalf of the City of Port Arthur, Change Order No. 1 between the CITY OF PORT ARTHUR and Placo, Ltd. for the increased contract time of twenty -two (22) days for a new contract term of 112 days attached hereto as Exhibit "A "; and, THAT, this project is funded in Project No. WSI001, 429 - 1258 - 532.59 -00; and, P. R. No. 18251 03/24/14 JT Page 2 THAT a copy of the caption of this resolution be spread upon the minutes of the City Council. READ, ADOPTED AND APPROVED THIS day of , 2014 at a Regular Meeting of the City Council of the City of Port Arthur, Texas, by the following votes: AYES: Mayor Councilmembers: NOES: Deloris Prince Mayor ATTEST: APPROVED AS TO FORM: Sherri Bellard alecia (Vzeno City Secretary City Attorney P. R. No. 18251 03/24/14 JT Page 3 APPROVED FOR ADMINISTRATION: 1 � .� J John A. Comeaux, P.E. Shawna Tubbs, CPPB Interim City Manager Purchasing Manager ohn • . Tompl . 't • 'stant Director of Utility Operations APPROVED AS TO AVAILABILITY OF FUNDS: N/A Exhibit "A" (Proposal for Contract Addition) ARCENEAUX & GATES ARCENEAUX Consulting Engineers, & 5 Inc. g GATES A Burrow Global Company Engineers • Surveyors • Planners March 18, 2014 Mr. John Tomplait Assistant Director of Water Utilities City of Port Arthur 444 Fourth Street Port Arthur, Texas 77640 RE; Change Order No, 1 Sabine Pass Metering Facility Job No. CPA -890 Dear Mr. Tomplait: Attached is Change Order No. 1 for the Sabine Pass Metering Facility. This change order is to increase the contract time by 22 days. The contractor has requested a time extension of 22 days due to inclement weather conditions. I recommend that the City of Port Arthur authorize this change to the contract. I have attached Change Order No. 1 which modifies the contract to reflect this change for your consideration and action. Should you have any questions or require additional information, please contact our office. Very truly yours, ARCENEAUX & GATES CONSULTING ENGINEERS, INC., A Burrow Global Company TEXAS REGISTERED ENGINEERING FIRM F -30 Keestan Cole, PE Staff Engineer 2901 Turtle Creek Dr., Suite 320 Port Arthur, TX 77642 Phone: 409/724 -7888 Fax: 409/724 -1447 ARCENEAUX GATES CONSULTING ENGINEERS, INC. CHANGE ORDER No. 1 DATE: March 18, 2014 JOB NO. CPA -890 AGREEMENT DATE: November 15, 2013 NAME OF PROJECT: SABINE PASS METERING FACILITY OWNER: CITY of PORT ARTHUR CONTRACTOR: Placoo Ltd. The following changes are hereby made to the CONTRACT DOCUMENTS: 1. Add the following Items to the Contract and Scope of Work: a. Increase contract time by 22 days CHANGE ORDER NO. 1 March 18, 2014 ARCENEAUX Job No. CPA-890 GATES CONSULTING ENGINEERS, INC. CHANGE TO CONTRACT PRICE: ORIGINAL CONTRACT PRICE: $115,000.00 CURRENT CONTRACT PRICE adjusted by previous CHANGE ORDER(S): $ The CONTRACT PRICE due to this CHANGE ORDER will be [eased] [deeressed] by: Dollars The new CONTRACT PRICE, including this CHANGE ORDER, will be $115,000.00 CHANGE TO CONTRACT TIME: ORIGINAL CONTRACT TIME: 90 Calendar Days CURRENT CONTRACT TIME adjusted by previous CHANGE ORDER: Calendar Days CURRENT DATE OF COMPLETION: April 4, 2914 CONTRACT TIME due to this CHANGE ORDER will be increased by 22 Days The New DATE OF COMPLETION: April 26, 2014 _ No other Terms and Conditions of the Contract are changed as a result of this Change Order. Contractor's acceptance of Change Order relieves OWNER of any liability for additional costs incurred by Contractor in his performance of the work covered by the Change Order. RECOMMENDED BY ENGINEER: ACCEPTED BY: ARCENEAUX & GATES [CONTP CTOR, OFFICER OR OWNER] CONSULTING ENGINEERS, INC. PLACO, LTD. ACCEPTED BY: CITY of PORT ARTHUR 2 of 2