3/25/14 jd
RESOLUTION NO.
A RESOLUTION AUTHORIZING THE CITY MANAGER TO EXECUTE CHANGE ORDER
NO. 1 TO THE CONTRACT BETWEEN THE CITY OF PORT ARTHUR AND L & L GENERAL
CONTRACTORS OF BEAUMONT, TEXAS, FOR THE CONSTRUCTION OF THE PLEASURE ISLAND
RECREATION CORRIDOR TRAIL, SECTION 2, INCREASING THE CONTRACT AMOUNT BY
$2,995.68 TO A NEW CONTRACT AMOUNT OF $93,606.68.
WHEREAS, per Resolution No. 13 -586, the City Council awarded a contract for the construction
of the Pleasure Island Recreation Corridor Trail, Section 2 (fishing platform) to L & L General Contractors
of Beaumont, Texas; and,
WHEREAS, during the construction of the Pleasure Island Recreation Corridor Trail, Section 2
(fishing platform), Arceneaux & Gates Consulting Engineers, Inc. determined the need to install support
angle iron and associated fasteners to complete the project; and,
WHEREAS, the engineer recommends proposed Change Order No. 1, attached as Exhibit "A ", to
accomplish this work;
NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF PORT ARTHUR:
THAT, the City Manager of the City of Port Arthur is hereby authorized and directed to execute,
on behalf of the City of Port Arthur, Change Order No. 1 (attached as Exhibit "A ") to the contract
between the City of Port Arthur and L & L General Contractors for the need to install support angle iron
and associated fasteners, increasing the total amount by $2,995.68; and,
THAT, Change Order No. 1 increases the contract amount to a new total of $93,606.68, and does
not change the contract time of the project; and,
THAT, a copy of the caption of this resolution be spread upon the minutes of the City Council.
READ, ADOPTED, AND APPROVED, this day of April 2014, AD, at a Regular Meeting of
the City Council of the City of Port Arthur, Texas by the following vote:
•
•
AYES: Mayor
Councilmembers:
NOES:
Deloris Prince
Mayor
ATTEST:
Sherri Bellard, City Secretary
APPROVED AS TO FORM:
/ i' (ACII
.1 Tizeno, C y j ev
APPROVED FOR ADMINISTRATION:
John Comeaux, Interim City Manager
APPROVED AS TO AVAILABILITY OF FUNDS:
I I
Deborah H. Echols, Finance Director
,
Shawna Tubbs, Purchasing Manager
EXHIBIT "A"
ARCENENTX at GATES
• ARCENEMIX
Consulting Engineers,
GATES A Burrow Global Company
Engineers • Surveyors 1 Matters
March 20, 2014
Mr. Jimmy R. bike •
Executive Director
Pleasure Island Commission
520 Pleasure Pier Blvd.
Pert Arthur, Texas 77640
RE: PROPOSAL POR .COAfTRACT ADDITION
PLEASURE ISLAND RECREAnom CORRIDOR TRAIL SEC 2
(FISHING PIER REPLACEMENV
Job No PIC-460
Dear Mr, Dike:
Attached is Change Order No 1 for the Recreation Corridor Trail Sec 2. This change
order is to Over additional cost to install Support - angle iron and associated fasteners for
construction of the boardwalk. These support angles and fasteners were not included in
• the original Contract Documents or bid price; however, are needed to complete the
project. The total . 00.t for the additional supports and fasteners is $2,995,68. This
Change Order does affect the Contract Time. I recommend that the City of Port Arthur
authorize this change to the contrabt. I have attached Change Order No 1 which
modifies the contract to reflect this change for your consideration and action. Should
you have any questions or require additional information, please contact our office.
Very truly yours,
ARCENEAUX GAMS CONSUL me ENGINEERS, INC.,
A Burtow Global Company
• rims latitST&RED ENGINEERING 01111$1 P30
Paul M. White, PE
Project Manager
2901 Turtle Creek Dr., Suite 320 Port Arthtir, rt. 77642 Riotte! 409/724-7888 Fax; 409/724-1447
--- 7
ARCENEAUX
&
GATES j
comt)141NO
iliintirEftS, INC.
CHANGE ORDER No. 1
DATE: March 20, 2014 JOB NO; PIC-480
AGRI:EMENT DATE: Dedernber 3, 2014
NAME OF PROJECT: Pleasure Island Recreation Corridor Trail Sec. 2
(Fishirio Per Replacement) ,
OWNER CITY of PORT ARTHUR,
CONTRACTOR: 1.81 General CC:infractors
The following changes are hereby inade to the CONTRACT DOCUMENTS:
1. Add the following Items to the Contract and Scope of Work:
Additional Materials and Labor to Fabricate the
boardwalk. (pier).
Angle Iron Brackets Fabrication 39 CI $25.00 $ 075.00
Angle: Iron Brackets Install 39 © $22.00 $ 858.00
W k 5" EIDG Bolts 156 © $0.75 $ 117.00
W 0-GEE Washers 312 @ $0.70 $. 218.40
W Nut HOG 312 @ $0.25 78.00
Equipment 250.00
Subtotal 1 $2,49.6.40
Overhead 1 4 1 $ 249.64
Profit 249.64
TOTAL 1_2,,a1§,As
CHANGE ORDER NO 1
March 20, 2014
ARCENEAUX job NO. PIC Contract No. 1
L GATES
tzwisviaola
trantatas.010.
CHANGE TO CONTRACT PRICE:
ORIGINAL CONTRACT PRICE: 590,611.00
CURRENT CONTRACT PRICE adjusted by prevmus CHANGE ORDER() : $90,511,00
'The CONTRACT PRICE due to this CHANGE ORDER Will be [increased]
fdeerel
by; 52,995.68 Dollar§„,
The new CON TRACF PRICE, including this CI LANGE ORDER w11 be $93,606,68
CHANGE TO CONTRACT Timg
ORIGINAL CONTRAC'TTIME:: 45 CaleniLat Da
CURRENT CONTRACT TIME adjusted by preViotis CHANGE ORDER:: , ,45 Calehdai DOs
CURRLNI DATE OF COMPLEnON:: 15_2014 4
CONTRACT TIME due to this CHANGE ORDER Will be ihe:reethed .„0 Oaks_
The New DATE Of COMPLETION;
No other Terms and Conditions of the Contract are changed as a result of this Change. Order.
Contractoes acceptance of Change Order relieves OWNER of any liability for additional costs
incurred by Contractor in his performance of the work covered by the Change Order.
RECOMMENDED BY ENGINEER: A CCEPY'Fil) BY:
ARCENEAUX & GATES (CONTRACIOR, cirri OF9 OR &NEM
CONSULTING ENGINE-01s, INC. L&L GENERAL CONTRACTORS
ACCEPTED BY:
CITY Of PORT ARTHUR
2 of 2
LAL General Contractors 1.
11988 FM 365 West
Beaumont, TX 77705
• Ph: 409-706-1344
Fax: 409-796-1341
• Date: 3/18/2014
Change Order #: 1
Contract Name; City of Port Arthur. - Plasore Wand Retreation CoorridOr Trail Section
Project # PIC
YOU are herepy anthOrizedlOAttlyikkiltelt___Ilhiljing&sticl
d Erin king era to:P*71)01one and installtAg
• ITEM QTY COST TOTAL
fabricate Additional Angle Iron OraeketS 39 $ 25 00 975.00
Install Additional Angle Iron tteatket.§ 39 $ 22.00 $ 858.00
Additional 1/2" x 5" 140G Bolts 156 1.17.00
Additional 1/2" OGEE WASHERS HOG .312 $ 0.70 $ 218;40
Additional 1/2" NUT HOG 312. $ 0.25 $ 78,00
Equipment 1 $ 250.00 $: 250.00
Subtotal 'S 2,496,40
Overhead 10.00% 249.64 •
Profit 1000% $ 249.64.
TOTAL CHANGE INCREASE • 2,995.68
• This change order reflects:
XX a cost increas of $ 2,9954
All other terms, conditions and covenants ofthe aforementioned contract remain unchanged,
. . ...ealrerw.nrnmrto
Owner Dote
• RenteSentative
1
1.AL General Contraetors Date
Representative