HomeMy WebLinkAboutPR 18336: CHANGE ORDER NO. 1 BASCO CONSTRUCTION, INC. MEMORANDUM
CITY OF PORT ARTHUR
PUBLIC WORKS - ENGINEERING DIVISION
TO: John A. Comeaux, P.E., Interim City Manager
FROM: Leslie E. McMahen, P.E., Interim City Engineer
DATE: May 14, 2014
RE: Proposed Resolution No. 18336
RECOMMENDATION
I recommend that the City Council approve Proposed Resolution No. 18336 that would
authorize the Interim City Manager to execute Change Order No. 1 to the contract with
Basco Construction, Inc., for construction of one (1) concession stand at Pioneer Park —
Grado Field and one (1) concession stand at County Park, extending the time of said
contract by fifty-five (55) calendar days.
BACKGROUND
By Resolution 13-463 dated October 15, 2013, the City Council awarded a contract to
Basco Construction, Inc., of Nederland, Texas, in the amount of $304,654.00, for the
construction of one (1) concessions stand at Pioneer Park — Grado Field and one (1)
concession stand at County Park in Port Acres. The contract time per the contract was
150 calendar days, with the Notice to Proceed being November 11, 2013.
Work on both concession stands is nearing completion, with the one at County Park
being substantially complete, even though Basco has exceeded the contract date of
completion for the project, that being April 9, 2014. Bacso has requested a time
extension due to rain and ice conditions, and has supplied documentation for that
request. The project engineer, Soutex Surveyors and Engineers has verified the
documentation and has determined that fifty-five (55) calendars should be added to the
contract time.
The new completion date by the addition of the fifty-five (55) calendars days approved
would be June 3, 2014.
BUDGET/FISCAL EFFECT
There is no change in the contract amount as a result of Change Order No. 1, though
Purchase Order No. 179021 will need to be amended to reflect the new ending date of
the contract.
SUMMARY
I recommend that the City Council approve Proposed Resolution No. 18336 that would
authorize the Interim City Manager to execute Change Order No. 1 to the construction
contract with Basco Construction, Inc., for a time extension to the contract by fifty-five
(55) calendar days to June 3, 2014. There is not additional cost to the City.
P.R. No. 18336
5/14/14 lem
RESOLUTION NO.
A RESOLUTION AUTHORIZING THE CITY MANAGER
TO EXECUTE CHANGE ORDER NO. 1 TO THE
CONTRACT BETWEEN THE CITY OF PORT ARTHUR
AND BASCO CONSTRUCTION, INC., OF NEDERLAND,
TEXAS, FOR THE CONSTRUCTION OF TWO (2)
CONCESSION STANDS IN CITY PARKS, INCREASING
THE TIME OF THE CONTRACT AMOUNT BY FIFTY-
FIVE (55) CALENDAR DAYS.
WHEREAS, per Resolution No. 13-463, the City Council awarded a contract for the
construction of two (2) concessions stands in City parks to Basco Construction, Inc., of
Nederland, Texas; and,
WHEREAS, the construction of one (1) concession stand at Pioneer Park— Grado Field
and one (1) concession stand at County Park began on November 11, 2013, with a contract time
of 150 calendar days and an ending date of April 9, 2014; and,
WHEREAS, the purchase order issued for the project has a completion date of May 31,
2014; and,
WHEREAS, Basco Construction, Inc., had requested a time extension of fifty-five (55)
calendars days to their contract for rain and ice conditions during the construction period; and,
WHEREAS, our project engineer, Soutex Surveyors and Engineers, has examined the
request and recommends proposed Change Order No. 1 in the amount of fifty-five (55) calendar
days to be added to the contract time for Basco Construction, Inc, said Change Order No. 1 being
attached as Exhibit"A": and,
WHEREAS, the new ending date for Basco Construction, Inc.'s contract would be June
3, 2014, if the Change Order is approved; NOW THEREFORE,
P.R. No. 18336
5/14/14 tern
Page 2 of 3
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF PORT
ARTHUR:
THAT, the City Manager of the City of Port Arthur is hereby authorized and directed to
execute, on behalf of the City of Port Arthur, Change Order No. 1, attached as Exhibit "A", to
the contract between the City of Port Arthur and Basco Construction, Inc., for the extension of
said contract by fifty-five (55) calendar days, with the new ending date of the contract being June
3, 2014; and,
THAT, Change Order No. 1 does not increase the contract amount; and,
THAT, a copy of the caption of this resolution be spread upon the minutes of the City
Council.
READ, ADOPTED AND APPROVED THIS day of , 2014 at a
Regular Meeting of the City Council of the City of Port Arthur, Texas, by the following vote:
AYES: Mayor
Councilmembers:
NOES:
Deloris Prince
Mayor
P.R. No. 18336
5/14/14 lem
Page 3 of 3
ATTEST: APPROVED AS TO FORM:
Sherri Bellard aleci Tiz no
City Secretary ttorney
on 6ah7i
APPROVED FOR ADMINISTRATION:
John A. Comeaux, P.E. S awna Tubbs, CPPO, CPPB
Interim City Manager Purchasing Manager
E.
Leslie E. McMahen, P.E. Dr. Albert Thigpen
Interim City Engineer Acting Director of Parks and Recreation
APPROVED AS TO AVAILABILITY OF FUNDS:
Deborah Echols
Director of Finance
P.R. No. 18336
Exhibit "A"
Change Order No. 1
Four(4) Pages
CHANGE ORDER NO. 1
APRIL 28,2014
REQUEST FOR EXTENSION OF TIME DUE TO WEATHER OR SUPPLIES
CITY OF PORT ARTHUR
FOR
COUNTY PARK AND GRADO FIELD CONCESSION STANDS
SOUTEX NUMBERS
13-0113 FOR COUNTY PAR13-0307 FOR GRADO FIELD
DATE April 28, 2014
MONTHS OF: November and December, 2013 & January thru April 14, 2014
CITY of PORT ARTHUR, TEXAS
PUBLIC WORKS DEPARTMENT
P.O. BOX 1089
CITY of PORT ARTHUR, TEXAS 77641-1089
ATTENTION: Leslie E. McMahen, P.E.
Interim City Engineer
Gentlemen:
We request extension of completion time on our Contract due to the days of work lost as
specified(list dates actually lost: do not include days not normally worked such as Saturdays,
Sundays, or holidays):
Dates Lost: 50 total of which 11 were Saturdays and Sundays net= 39 days
PLEASE SEE ATTACHED PAGES
Days Lost(39 / 5 x 7= 55 Calendar Days Requested
Reasons for Request:
Rain, too wet to work, could not get fill material from the dirt pits, ice and freezing conditions
Contractor Basco , onstruction
r
B / y
ice 02Oj.-G7 g Al G //(f c6Z
V Approved for extension of 55 calendar days.� '"L—
Disapproved.
Date: , 20 CITY OF CITY OF PORT ARTHUR, TEXAS
BY:
City Manager
PAGE 1
Basco Construction Inc.
PO Box 1025 Nederland,TX 77627
(409)722-4434
(409)722-6428 Fax
RE:County Park and Grado Field Concession Stands
Updated as of 4/25/14
Rain Days and Days Inaccessible to Fill Dirt
Listed below are dates where either rain occurred or access to fill dirt was not possible
due to excessively wet conditions.
11/16/2013
11/17/2013
11/18/2013
11/19/2013
11/20/2013
11/21/2013
11/22/2013
`11/23/2013
11/25/2013
11/26/2013
, 12/1/2013
12/2/2013
12/3/2013
�t 12/6/2013
!\ 12/7/2013
12/9/2013
X Y Sat °{SA"aj
'�
PAGE 2
Basco Construction Inc.
PO Box 1025 Nederland,TX 77627
(409)722-4434
(409)722-6428 Fax
42/10/2013
-2/20/14
2/25/14
2/26/14
2/28/14
3/2/14
3/4/14
3/5/14
3/6/14
'1\ 3/15/14
\\.3/16/14
3/23/14
,3/24/14
3/26/14
.3/27/14
-3/28/14
A/2/14
4/3/14
4/4/14
4/7/14
4/8/14
4/14/14
c - 3a4 5 °`
PAGE 3
Basco Construction Inc.
PO Box 1025 Nederland,TX 77627
(409)722-4434
(409)722-6428 Fax
Days lost to Ice and Freezing Conditions
12/16/13
12/17/13
1/3/14
1/4/14
y1/s/14
1/6/14
1/23/14
1/24/14
1/29/14
1/30/14
2/12/14
2/13/14
Sgl4 . 0Y V viv? i (71 1,4
PAGE 4