HomeMy WebLinkAboutPR 18336: CHANGE ORDER NO. 1 BASCO CONSTRUCTION, INC. MEMORANDUM CITY OF PORT ARTHUR PUBLIC WORKS - ENGINEERING DIVISION TO: John A. Comeaux, P.E., Interim City Manager FROM: Leslie E. McMahen, P.E., Interim City Engineer DATE: May 14, 2014 RE: Proposed Resolution No. 18336 RECOMMENDATION I recommend that the City Council approve Proposed Resolution No. 18336 that would authorize the Interim City Manager to execute Change Order No. 1 to the contract with Basco Construction, Inc., for construction of one (1) concession stand at Pioneer Park — Grado Field and one (1) concession stand at County Park, extending the time of said contract by fifty-five (55) calendar days. BACKGROUND By Resolution 13-463 dated October 15, 2013, the City Council awarded a contract to Basco Construction, Inc., of Nederland, Texas, in the amount of $304,654.00, for the construction of one (1) concessions stand at Pioneer Park — Grado Field and one (1) concession stand at County Park in Port Acres. The contract time per the contract was 150 calendar days, with the Notice to Proceed being November 11, 2013. Work on both concession stands is nearing completion, with the one at County Park being substantially complete, even though Basco has exceeded the contract date of completion for the project, that being April 9, 2014. Bacso has requested a time extension due to rain and ice conditions, and has supplied documentation for that request. The project engineer, Soutex Surveyors and Engineers has verified the documentation and has determined that fifty-five (55) calendars should be added to the contract time. The new completion date by the addition of the fifty-five (55) calendars days approved would be June 3, 2014. BUDGET/FISCAL EFFECT There is no change in the contract amount as a result of Change Order No. 1, though Purchase Order No. 179021 will need to be amended to reflect the new ending date of the contract. SUMMARY I recommend that the City Council approve Proposed Resolution No. 18336 that would authorize the Interim City Manager to execute Change Order No. 1 to the construction contract with Basco Construction, Inc., for a time extension to the contract by fifty-five (55) calendar days to June 3, 2014. There is not additional cost to the City. P.R. No. 18336 5/14/14 lem RESOLUTION NO. A RESOLUTION AUTHORIZING THE CITY MANAGER TO EXECUTE CHANGE ORDER NO. 1 TO THE CONTRACT BETWEEN THE CITY OF PORT ARTHUR AND BASCO CONSTRUCTION, INC., OF NEDERLAND, TEXAS, FOR THE CONSTRUCTION OF TWO (2) CONCESSION STANDS IN CITY PARKS, INCREASING THE TIME OF THE CONTRACT AMOUNT BY FIFTY- FIVE (55) CALENDAR DAYS. WHEREAS, per Resolution No. 13-463, the City Council awarded a contract for the construction of two (2) concessions stands in City parks to Basco Construction, Inc., of Nederland, Texas; and, WHEREAS, the construction of one (1) concession stand at Pioneer Park— Grado Field and one (1) concession stand at County Park began on November 11, 2013, with a contract time of 150 calendar days and an ending date of April 9, 2014; and, WHEREAS, the purchase order issued for the project has a completion date of May 31, 2014; and, WHEREAS, Basco Construction, Inc., had requested a time extension of fifty-five (55) calendars days to their contract for rain and ice conditions during the construction period; and, WHEREAS, our project engineer, Soutex Surveyors and Engineers, has examined the request and recommends proposed Change Order No. 1 in the amount of fifty-five (55) calendar days to be added to the contract time for Basco Construction, Inc, said Change Order No. 1 being attached as Exhibit"A": and, WHEREAS, the new ending date for Basco Construction, Inc.'s contract would be June 3, 2014, if the Change Order is approved; NOW THEREFORE, P.R. No. 18336 5/14/14 tern Page 2 of 3 BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF PORT ARTHUR: THAT, the City Manager of the City of Port Arthur is hereby authorized and directed to execute, on behalf of the City of Port Arthur, Change Order No. 1, attached as Exhibit "A", to the contract between the City of Port Arthur and Basco Construction, Inc., for the extension of said contract by fifty-five (55) calendar days, with the new ending date of the contract being June 3, 2014; and, THAT, Change Order No. 1 does not increase the contract amount; and, THAT, a copy of the caption of this resolution be spread upon the minutes of the City Council. READ, ADOPTED AND APPROVED THIS day of , 2014 at a Regular Meeting of the City Council of the City of Port Arthur, Texas, by the following vote: AYES: Mayor Councilmembers: NOES: Deloris Prince Mayor P.R. No. 18336 5/14/14 lem Page 3 of 3 ATTEST: APPROVED AS TO FORM: Sherri Bellard aleci Tiz no City Secretary ttorney on 6ah7i APPROVED FOR ADMINISTRATION: John A. Comeaux, P.E. S awna Tubbs, CPPO, CPPB Interim City Manager Purchasing Manager E. Leslie E. McMahen, P.E. Dr. Albert Thigpen Interim City Engineer Acting Director of Parks and Recreation APPROVED AS TO AVAILABILITY OF FUNDS: Deborah Echols Director of Finance P.R. No. 18336 Exhibit "A" Change Order No. 1 Four(4) Pages CHANGE ORDER NO. 1 APRIL 28,2014 REQUEST FOR EXTENSION OF TIME DUE TO WEATHER OR SUPPLIES CITY OF PORT ARTHUR FOR COUNTY PARK AND GRADO FIELD CONCESSION STANDS SOUTEX NUMBERS 13-0113 FOR COUNTY PAR13-0307 FOR GRADO FIELD DATE April 28, 2014 MONTHS OF: November and December, 2013 & January thru April 14, 2014 CITY of PORT ARTHUR, TEXAS PUBLIC WORKS DEPARTMENT P.O. BOX 1089 CITY of PORT ARTHUR, TEXAS 77641-1089 ATTENTION: Leslie E. McMahen, P.E. Interim City Engineer Gentlemen: We request extension of completion time on our Contract due to the days of work lost as specified(list dates actually lost: do not include days not normally worked such as Saturdays, Sundays, or holidays): Dates Lost: 50 total of which 11 were Saturdays and Sundays net= 39 days PLEASE SEE ATTACHED PAGES Days Lost(39 / 5 x 7= 55 Calendar Days Requested Reasons for Request: Rain, too wet to work, could not get fill material from the dirt pits, ice and freezing conditions Contractor Basco , onstruction r B / y ice 02Oj.-G7 g Al G //(f c6Z V Approved for extension of 55 calendar days.� '"L— Disapproved. Date: , 20 CITY OF CITY OF PORT ARTHUR, TEXAS BY: City Manager PAGE 1 Basco Construction Inc. PO Box 1025 Nederland,TX 77627 (409)722-4434 (409)722-6428 Fax RE:County Park and Grado Field Concession Stands Updated as of 4/25/14 Rain Days and Days Inaccessible to Fill Dirt Listed below are dates where either rain occurred or access to fill dirt was not possible due to excessively wet conditions. 11/16/2013 11/17/2013 11/18/2013 11/19/2013 11/20/2013 11/21/2013 11/22/2013 `11/23/2013 11/25/2013 11/26/2013 , 12/1/2013 12/2/2013 12/3/2013 �t 12/6/2013 !\ 12/7/2013 12/9/2013 X Y Sat °{SA"aj '� PAGE 2 Basco Construction Inc. PO Box 1025 Nederland,TX 77627 (409)722-4434 (409)722-6428 Fax 42/10/2013 -2/20/14 2/25/14 2/26/14 2/28/14 3/2/14 3/4/14 3/5/14 3/6/14 '1\ 3/15/14 \\.3/16/14 3/23/14 ,3/24/14 3/26/14 .3/27/14 -3/28/14 A/2/14 4/3/14 4/4/14 4/7/14 4/8/14 4/14/14 c - 3a4 5 °` PAGE 3 Basco Construction Inc. PO Box 1025 Nederland,TX 77627 (409)722-4434 (409)722-6428 Fax Days lost to Ice and Freezing Conditions 12/16/13 12/17/13 1/3/14 1/4/14 y1/s/14 1/6/14 1/23/14 1/24/14 1/29/14 1/30/14 2/12/14 2/13/14 Sgl4 . 0Y V viv? i (71 1,4 PAGE 4