HomeMy WebLinkAboutPR 18367: CHANGE ORDER NO. 2 BASCO CONSTRUCTION, COMPLETION FOR THE CONCESSION STANDS MEMORANDUM
CITY OF PORT ARTHUR
Public Works Department — Engineering
TO: John A. Comeaux, P.E., Interim City Manager
FROM: Leslie E. McMahen, P.E., Interim City Engineer--�
DATE: June 4, 2014
RE: Proposed Resolution No. 18367
RECOMMENDATION
I recommend that the City Council approve Proposed Resolution No. 18367 which
would authorize the City Manager to execute Change Order No. 2 to the contract
between the City and Basco Construction, Inc., for the construction of two concession
stands at City parks, and to accept the Certificates of Substantial Completion issued for
both projects by Soutex Surveyors and Engineers.
BACKGROUND
The City contracted with Basco Construction to build two concessions stands, one in
County Park and one in Pioneer Park-Grado Field in the amount of $304,654.00, with a
contract term of 150 calendar days. Change Order No. 1 to the contract was previously
approved for fifty-five (55) additional calendar days, and Change Order No. 2 would add
another seven (7) calendar days, for a new completion date of June 10, 2014. The
Certificates of Substantial Completion stop the count of days on the term of the contract
on June 2, 2014. Minor punch list items remain to be done, but they do not affect the
use of the concession stands. All punch list items must be completed to the City's
satisfaction and in accordance with the contract documents before the City will process
the contract for close-out and final payment to Basco.
BUDGET/FISCAL EFFECT
There is no change in the contract amount as a result of Change Order No. 2, though
Purchase Order 179021 should be amended to reflect a new ending date of the
Purchase Order at June 10, 2014.
SUMMARY
I recommend that the City Council approve Proposed Resolution No.18367 which would
authorize the execution of Change Order No. 2 to the Basco contract, and which would
accept the two Certificates of Substantial Completion issued by Soutex Surveyors and
Engineers for the projects.
P. R. No. 18367
06/03/141em
Page 1 of 4
RESOLUTION NO.
A RESOLUTION AUTHORIZING THE CITY MANAGER
TO EXECUTE CHANGE ORDER NO. 2 FOR A TIME
EXTENSION TO THE CONTRACT BETWEEN THE
CITY OF PORT ARTHUR AND BASCO CONSTRUTION,
INC., OF NEDERLAND, TEXAS, AND ACCEPTING
THE TWO CERTIFICATES OF SUBSTANTIAL
COMPLETION FOR THE CONCESSION STANDS
CONSTRUCTED AS PART OF SAID CONTRACT.
WHEREAS, per Resolution No. 13-463, the City entered into a contract with Basco
Construction, Inc. of Nederland, Texas, for the construction of a concession stand at County Park
and a concession stand at Pioneer Park-Grado Field, for the contract amount of$304,654.00 and
a term of 150 calendar days; and,
WHEREAS, per Resolution No. 14-329, the City Council authorized Change Order No.
1 between the City and Basco Construction, Inc., for a time extension of fifty-five (55) calendar
days, increasing the term of the contract to 205 calendar days, with a new completion date of
June 3, 2014; and,
WHEREAS, Basco Construction, Inc., has submitted Change Order No. 2 to their
contract, attached as Exhibit "A", for an additional time extension of seven (7) calendar days;
and,
WHEREAS, on May 7, 2014, the City, Soutex Surveyors and Engineers, and Basco
Construction, Inc., made a walk-through on the County Park concession stand project and
established a punch list of items to be addressed by Basco Construction, Inc.; and,
WHEREAS, on May 14, 2014, Soutex Surveyors and Engineers submitted to the City a
Certificate of Substantial Completion for the concession stand at County Park, attached as
Exhibit `B", the effective date of which was May 6, 2014, when Basco Construction, Inc. gave
permission to the Port Acres Little League permission to begin using the concession stand; and,
P. R. No. 18367
06/03/141em
Page 2 of 4
WHEREAS, there are some incidental punch list items that remain to be addressed, but
which do not prevent the use of the concession stand by the Port Acres Little League; and,
WHEREAS, on May 29, 2014, the City, Soutex Surveyors and Engineers, and Basco
Construction, Inc., made a walk-through on the Pioneer Park-Grado Field concession stand
project and established a punch list of items to be addressed by Basco Construction, Inc.; and,
WHEREAS, on June 2, 2014, Soutex Surveyors and Engineers submitted to the City a
Certificate of Substantial Completion for the concession stand at Pioneer Park-Grado Field,
attached as Exhibit"C", the effective date of which was June 2, 2014, when Basco Construction,
Inc. gave permission to the Port Arthur Little League to begin using the concession stand; and,
WHEREAS, there are some incidental punch list items that remain to be addressed, but
which do not prevent the use of the concession stand by the Port Arthur Little League; and,
WHEREAS, all incidental punch list items must be completed by Basco Construction,
Inc., to the satisfaction of the City, and in compliance with the contract documents, before the
City will process the close-out of Basco's contract and make final payment to Basco; NOW
THEREFORE,
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF PORT
ARTHUR:
THAT, the City Manager is hereby authorized to execute Change Order No. 2 to the
contract between the City and Basco Construction, Inc., for the construction of two (2)
concession stands, increasing the contract time by seven (7) calendar days to a contract term of
212 calendar days, for a new completion date of June 10, 2014; and,
THAT, the City Council hereby accepts the Certificate of Substantial Completion issued
by Soutex Surveyors and Engineers for the County Park concession stand, and dated May 14,
2014, with an effective date of May 6, 2014; and,
P. R. No. 18367
06/03/14 lem
Page 3 of 4
THAT, the City Council hereby accepts the Certificate of Substantial Completion issued
by Soutex Surveyors and Engineers for the Pioneer Park-Grado Field concession stand, and
dated June 2, 2014, with an effective date of June 2, 2014; and,
THAT, acceptance of the Certificates of Substantial Completion by the City stops the
count of days on the term of the contract as of June 2, 2014; and,
THAT, Soutex Surveyors and Engineers, and Basco Construction, Inc., will submit a
Certificate of Completion, Contractor's Certificate of Release and final payment for the contract,
after the punch lists for the concession stands have been completed, for City Council acceptance
and approval; and,
THAT, a copy of the caption of this resolution be spread upon the minutes of the City
Council.
READ, ADOPTED AND APPROVED THIS day of , 2014
at a Regular Meeting of the City Council of the City of Port Arthur, Texas, by the following
vote:
AYES: Mayor
Councilmembers:
NOES:
Deloris Prince
Mayor
P. R. No. 18367
06/03/14 lem
Page 4 of 4
ATTEST: APPROVED AS TO FORM:
Sherri Bellard Valecia Tizen
City Secretary City Attorney
APPROVED FOR ADMINISTRATION:
((341',(4).-4. a C11. (L...
John A. Comeaux P.E. S awna Tubbs, CPPO, CPPB
Interim City Manager Purchasing Manager
V`'` P.E .
Leslie E. McMahen, P.E. Dr. Albert Thigpen
Interim City Engineer Director of Parks and Recreation
APPROVED AS TO AVAILABILITY OF
FUNDS:
!v A-
Deborah Echols
Director of Finance
Exhibit "A"
to
PR No. 18367
Change Order No. 2
. r
CHANGE ORDER NO. 2
May 21, 2014
REQUEST FOR EXTENSION OF TIME DUE TO WEATHER OR SUPPLIES
CITY OF PORT ARTHUR
FOR
COUNTY PARK AND GRADO FIELD CONCESSION STANDS
SOUTEX NUMBERS
13-0113 FOR COUNTY PARK, 13-0307 FOR GRADO FIELD
DATE May 21, 2014
MONTHS OF: April thru May21, 2014
CITY of PORT ARTHUR, TEXAS
PUBLIC WORKS DEPARTMENT
P.O. BOX 1089
CITY of PORT ARTHUR, TEXAS 77641-1089
ATTENTION: Leslie E. McMahen, P.E.
Interim City Engineer
Gentlemen:
We request extension of completion time on our Contract due to the days of work lost as
specified(list dates actually lost: do not include days not normally worked such as Saturdays,
Sundays, or holidays):
Dates Lost: 5 total days PLEASE SEE ATTACHED PAGES
Days Lost(5)/5 x 7=7 Calendar Days Requested
Reasons for Request:
Rain,too wet to work
Contractor Basco onstruction
B
L 517--///4-
V Approved for extension of 7 calendar days.Z'nv\___-
Disapproved.
Date: 7uw s 10 , 201 t{- . CITY OF CITY OF PORT ARTHUR, TEXAS
BY:
City Manager
Basco Construction Inc.
PO Box 1025 Nederland,TX 77627
(409)722-443
(409)722-6428 fax
5/19/14
Rain days claimed from4J15/14 thru 5/14/14
—4/2e/14--
4//21/14
4/28/14
5/12/14 O1( 56 Ai
5/13/14
5/14/14 J
Exhibit "B"
• to
PR No. 18367
Certificate of Substantial Completion
County Park Concession Stand
111."2 3737 Doctors Drive
F,411a1.. S - Port Arthur, TX 77642
Office (409) 983.2004
SURVEYORS &ENGINEERS Fax (409) 983.2005
7BPE firm No.5755 TBPLSFom No.10123900
May 14, 2014
Dr. Albert Thigpen
444 4th Street
Port Arthur, Texas 77640
Re: County Park Concession Stand
Soutex No. 13-0113
Dear Sir:
This letter is to keep dates for record purposes. The Concession Stand at County
Park was substantially complete on May 5, 2014 and the Certificate of Occupancy was
dated May 5, 2014. The Contractor, Basco Construction, Inc., gave permission for the
Port Acres Little League to use the Stand on Tuesday May 6, 2014. We made a walk
through and established a"punch list" on May 7, 2014. Punch list items which remain to
be completed do not materially affect the use of the concession stand.
Respectfully submitted,
An`: ' *_-r, Vice P 4 ident
For Stanley G. Newsome, Jr., P.E., RPLS
Project Engineer
c.
Basco Construction, Inc.
Leslie McMahen, P.E.
Exhibit "C"
to
PR No. 18367
Certificate of Substantial Completion
Pioneer Park Grado Field Concession Stand
SOUTEX TBPE .
TBPLS Firm NoFirm. No10123800 5755
3737 Doctors Drive
G , Port Arthur,TX 77642
(409) 983.2004
SURVEYORS& GIN ERS Office Fax (409) 983.2005
June 2, 2014
Dr. Albert Thigpen
444 4th Street
Port Arthur, Texas 77640
Re: Grado Field Concession Stand
Soutex No. 13-0307
Dear Sir:
This letter is to keep dates for record purposes. The Concession Stand at Grado Field is
substantially complete on June 2, 2014, and the Certificate of Occupancy is also dated June 2,
2014. The Contractor,Basco Construction, Inc., gave permission for the Port Arthur Little League
to use the Stand on Friday, May 29, 2014. We made a walk through and established a"punch list"
also on May 29, 2014. Punch list items which remain to be completed do not materially affect the
use of the concession stand.
Respectfully submitted,
Ant .nyA Leger, 1 President
For Stanley G. - . . a=, Jr., PE, RPLS
Project Engineer
c.
Basco Construction, Inc.
Leslie McMahen, P.E.
TWO (2) ORIGINALS
For
P.R. No. 18367
Distribution of Signed Originals
One (1) to City Secretary
One (1)to Contractor via Public Works—Les McMahen