HomeMy WebLinkAboutPR 18505: ALLCO CHANGE ORDER NO. 4 MEMORANDUM
CITY OF PORT ARTHUR
UTILITY OPERATIONS DEPARTMENT
TO: John A. Comeaux P.E., City Manager
FROM: John A. Tomplait, Assistant Director of Utility Operations
DATE: August 22, 2014
RE: Proposed Resolution No. 18505
RECOMMENDATION
I recommend that the City Council approve Proposed Resolution No. 18505 authorizing
the execution of Change Order No.4 for the 24"Waterline from 19th Street to the Sabine
Neches Canal Project with ALLCO, L.L.C., of Beaumont, Texas, this change order is a
time extension of three (3) days due to inclement weather.
BACKGROUND
This project will extend a 24" water transmission main from the old Water Purification
Plant to W. 7th Street and SH 82.
•
BUDGET/FISCAL EFFECT
This project will be funded by Sabine Pass Liquefaction, and charged through a City
Account No. 429-1258-532.59-00, and Project No. WSI003.
SUMMARY
I recommend that the City Council approve Proposed Resolution No.18505.
P.R.No. 18505
08/22/14 jt
RESOLUTION NO.
A RESOLUTION AUTHORIZING THE CITY MANAGER
TO EXECUTE CHANGE ORDER NO. 4 BETWEEN THE
CITY OF PORT ARTHUR AND ALLCO, L.L.C.; FOR
THE WATERLINE FROM 19TH STREET TO THE
SABINE NECHES CANAL, FOR A TIME EXTENSION
OF THREE (3) DAYS, INCREASING THE CONTRACT
TIME TO 380 DAYS, ACCOUNT NO. 429-1258-532.59-00,
PROJECT NO WSI003.
WHEREAS, per Resolution No. 13-503, the City entered into a contract for the
installation of a Waterline from 19th Street to the Sabine Neches Canal, to supply water for the
Sabine Pass Liquefaction LNG facility in the amount of$3,114,960.00 with a contract term of
365 calendar days; and
WHEREAS, per Resolution No. 14-210, Change Order 1 authorized an additional
$40,486.00 was needed to add storm water pollution prevention measures required by the City of
Port Arthur that was not included in the original contract, bringing the contract price for the
project to $3,155,446.00 accepted by Allco; and
WHEREAS, per Resolution No. 14-300, Change Order 2 authorized a credit of
$21,980.00 for the use of 24" Certa-Loc restrained joint C900 pvc pipe in lieu of the 24" cement
lined restrained joint gasket ductile iron pipe in the original bid, also a time extension of six (6)
days due to inclement weather bring the date of completion to January 25,2015; and
WHEREAS, per Resolution No. 14-342, Change Order 3 authorized an additional
$12,072.00 for the relocation of an existing 6"waterline that was discovered during construction
on Charleston Ave, the re-route of the 24" waterline to miss an existing storm sewer, and one
foot of extra cover added to the 24" waterline approx. 2,100 L.F. to ensure protection of the line
during the 18th Street construction project, also a time extension of six (6) days due to inclement
weather bringing the date of completion to January 31,2015; and,
P.R. No. 18505
08/22/14 jt
Page 2 of 3
WHEREAS, Allco, Inc has requested a time extension of 3 days due to weather delays;
and,
WHEREAS,Arceneaux& Gates Consulting Engineers,has requested and recommended
Change Order No. 4 increasing the time extension of three (3) days for a new contract time of
380 days with a new completion date of February 3, 2015, the change order has been evaluated
by Arceneaux & Gates Consulting Engineers, and the Utility Operations Department (attached
hereto as Exhibit"A");NOW THEREFORE,
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF PORT
ARTHUR:
THAT, the City Manager of the City of Port Arthur is hereby authorized and directed to
execute, on behalf of the City of Port Arthur, Change Order No. 4 between the City of Port
Arthur and Allco L.L.C., for the increased time extension of three (3) days for a new contract
time of 380 days with a new completion date of February 3, 2015, attached hereto as Exhibit
"A"; and
THAT, Change Order No. 4 will not require any funding in Project No. WSI003, 429-
1258-532.59-00; and,
THAT a copy of the caption of this resolution be spread upon the minutes of the City
Council.
READ,ADOPTED AND APPROVED THIS day of , 2014
at a Regular Meeting of the City Council of the City of Port Arthur, Texas, by the following
vote:
AYES: Mayor
P. R. No. 18505
08/22/14 jt
Page 3 of 3
Councilmembers:
NOES:
Deloris Prince
Mayor
ATTEST: APPROVED AS TO FORM:
Sherri Bellard Valecia Tizeno
City Secretary City Attorney
APPROVED FOR ADMINISTRATION:
(Cif:a/0-A LIA)
John A. Comeaux,PE Shawna Tubbs,CPPB
Interim City Manager Purchasing Manager
ohn . Tomplait
ant Director of Utilities
APPROVED AS TO AVAILABILITY OF
FUNDS:
gir; I 34(..-1.A. 1"-LE..)
Deborah Echols 0
Director of Finance
Account No.: 429-1258-532.59-00
Project No.: WSI003
Exhibit "A"
(A&G Change Order No.4)
ARCENEAUX
GATES
CONSULTING
ENGINEERS,INC.
CHANGE ORDER No. 4
DATE: August 15, 2014 JOB NO. CPA-650
AGREEMENT DATE: November 5, 2013
NAME OF PROJECT: 24" Waterline from 19th Street to the Sabine-Neches Canal
OWNER: CITY of PORT ARTHUR
CONTRACTOR: ALLCO
The following changes are hereby made to the CONTRACT DOCUMENTS:
1. Add the following Items to the Contract and Scope of Work:
a. Extend contract time by 3 days
•
CHANGE ORDER NO. 4
August 15, 2014
ARCENEAUX Job No. CPA-650, Contract No. 1
GATES
CONSULTING
ENGINEERS,INC.
CHANGE TO CONTRACT PRICE:
ORIGINAL CONTRACT PRICE: $3.114,960.00
CURRENT CONTRACT PRICE adjusted by previous CHANGE ORDER(S): $3,145,538.00
The CONTRACT PRICE due to this CHANGE ORDER will be [increased] [did]
by: $0.00 Dollars
The new CONTRACT PRICE, including this CHANGE ORDER, will be $3,145,538.00
CHANGE TO CONTRACT TIME:
ORIGINAL CONTRACT TIME: 365 Calendar Days
CURRENT CONTRACT TIME adjusted by previous CHANGE ORDER: 12 Calendar Days
CURRENT DATE OF COMPLETION: January 31, 2015
CONTRACT TIME due to this CHANGE ORDER will be increased by 3 Days
The New DATE OF COMPLETION: February 3, 2015
No other Terms and Conditions of the Contract are changed as a result of this Change Order.
Contractor's acceptance of Change Order relieves OWNER of any liability for additional costs
incurred by Contractor in his performance of the work covered by the Change Order.
RECOMMENDED BY ENGINEER: ACCEPTED BY:
ARCENEAUX & GATES [CONTRACTOR,OFFICER OR OWNER]
CONSULTING ENGINEERS, INC. ALLCO
ACCEPTED BY:
CITY of PORT ARTHUR
2 of 2
ARCENEAUX
GATES
CONSULTING
ENGINEERS,INC.
CHANGE ORDER No. 4
DATE: August 15, 2014 JOB NO. CPA-650
AGREEMENT DATE: November 5, 2013
NAME OF PROJECT: 24" Waterline from 19th Street to the Sabine-Neches Canal
OWNER: CITY of PORT ARTHUR
CONTRACTOR: ALLCO
The following changes are hereby made to the CONTRACT DOCUMENTS:
1. Add the following Items to the Contract and Scope of Work:
a. Extend contract time by 3 days
CHANGE ORDER NO. 4
E::, August 15, 2014
ARCENEAUX Job No. CPA-650, Contract No. 1
GATES
CONSULTING
ENGINEERS,INC.
CHANGE TO CONTRACT PRICE:
ORIGINAL CONTRACT PRICE: $3,114,960.00
CURRENT CONTRACT PRICE adjusted by previous CHANGE ORDER(S): $3,145,538.00
The CONTRACT PRICE due to this CHANGE ORDER will be [increased] [decreased]
by: $0.00 Dollars
The new CONTRACT PRICE, including this CHANGE ORDER, will be $3,145,538.00
CHANGE TO CONTRACT TIME:
ORIGINAL CONTRACT TIME: 365 Calendar Days
CURRENT CONTRACT TIME adjusted by previous CHANGE ORDER: 12 Calendar Days
CURRENT DATE OF COMPLETION: January 31, 2015
CONTRACT TIME due to this CHANGE ORDER will be increased by 3 Days
The New DATE OF COMPLETION: February 3, 2015
No other Terms and Conditions of the Contract are changed as a result of this Change Order.
Contractor's acceptance of Change Order relieves OWNER of any liability for additional costs
incurred by Contractor in his performance of the work covered by the Change Order.
RECOMMENDED BY ENGINEER: ACCEPTED BY:
RCENEAUX & GATES [CONTRACTOR,OF ER OR OWNER]
CONSULTING ENGINEERS, INC. ALLCO
ACCEPTED BY:
CITY of PORT ARTHUR
2 of 2
ARCENEAUX
GATES
CONSULTING
ENGINEERS,INC.
CHANGE ORDER No. 4
DATE: August 15, 2014 JOB NO. CPA-650
AGREEMENT DATE: November 5, 2013
NAME OF PROJECT: 24" Waterline from 19th Street to the Sabine-Neches Canal
OWNER: CITY of PORT ARTHUR
CONTRACTOR: ALLCO
The following changes are hereby made to the CONTRACT DOCUMENTS:
1. Add the following Items to the Contract and Scope of Work:
a. Extend contract time by 3 days
CHANGE ORDER NO. 4
ED August 15, 2014
ARCENEAUX Job No. CPA-650, Contract No. 1
GATES
CONSULTING
ENGINEERS,INC.
CHANGE TO CONTRACT PRICE:
ORIGINAL CONTRACT PRICE: $3.114,960.00
CURRENT CONTRACT PRICE adjusted by previous CHANGE ORDER(S): $3,145,538.00
The CONTRACT PRICE due to this CHANGE ORDER will be [increased] [decreased]
by: $0.00 Dollars
The new CONTRACT PRICE, including this CHANGE ORDER, will be $3,145,538.00
CHANGE TO CONTRACT TIME:
ORIGINAL CONTRACT TIME: 365 Calendar Days
CURRENT CONTRACT TIME adjusted by previous CHANGE ORDER: 12 Calendar Days
CURRENT DATE OF COMPLETION: January 31, 2015
CONTRACT TIME due to this CHANGE ORDER will be increased by 3 Days
The New DATE OF COMPLETION: February 3, 2015
No other Terms and Conditions of the Contract are changed as a result of this Change Order.
Contractor's acceptance of Change Order relieves OWNER of any liability for additional costs
incurred by Contractor in his performance of the work covered by the Change Order.
RECOMMENDED BY ENGINEER: ACCEPTED BY:
RCENEAUX & GATES [CONTRACTOR,OFFICER OR OWNER]
CONSULTING ENGINEERS, INC. ALLCO
ACCEPTED BY:
CITY of PORT ARTHUR
2 of 2
ARCENEAUX
GATES
CONSULTING
ENGINEERS,INC.
CHANGE ORDER No. 4
DATE: August 15, 2014 JOB NO. CPA-650
AGREEMENT DATE: November 5, 2013
NAME OF PROJECT: 24" Waterline from 19th Street to the Sabine-Neches Canal
OWNER: CITY of PORT ARTHUR
CONTRACTOR: ALLCO
The following changes are hereby made to the CONTRACT DOCUMENTS:
1. Add the following Items to the Contract and Scope of Work:
a. Extend contract time by 3 days
CHANGE ORDER NO. 4
August 15, 2014
ARCENEAUX Job No. CPA-650, Contract No. 1
GATES
CONSULTING
ENGINEERS,INC.
CHANGE TO CONTRACT PRICE:
ORIGINAL CONTRACT PRICE: $3.114,960.00
CURRENT CONTRACT PRICE adjusted by previous CHANGE ORDER(S): $3,145,538.00
The CONTRACT PRICE due to this CHANGE ORDER will be [greased} [decreased]
by: $0.00 Dollars
The new CONTRACT PRICE, including this CHANGE ORDER, will be $3,145,538.00
CHANGE TO CONTRACT TIME:
ORIGINAL CONTRACT TIME: 365 Calendar Days
CURRENT CONTRACT TIME adjusted by previous CHANGE ORDER: 12 Calendar Days
CURRENT DATE OF COMPLETION: January 31, 2015
CONTRACT TIME due to this CHANGE ORDER will be increased by 3 Days
The New DATE OF COMPLETION: February 3, 2015
No other Terms and Conditions of the Contract are changed as a result of this Change Order.
Contractor's acceptance of Change Order relieves OWNER of any liability for additional costs
incurred by Contractor in his performance of the work covered by the Change Order.
RECOMMENDED BY ENGINEER: ACCEPTED BY:
ARCENEAUX & GATES [CONTRACTOR,OFFICER OR OW ER]
CONSULTING ENGINEERS, INC. ALLCO
ACCEPTED BY:
CITY of PORT ARTHUR
2 of 2