HomeMy WebLinkAboutPR 18515: BDS CONSTRUCTORS CONTRACT MEMORANDUM
CITY OF PORT ARTHUR
PUBLIC WORKS - ENGINEERING DIVISION
TO: John A. Comeaux, P.E., City Manager
FROM: Susan McDermott, Director of Public Works
DATE: August 26, 2014
RE: Proposed Resolution No. 18515
RECOMMENDATION
I recommend that the City Council approve Proposed Resolution No. 18515 awarding a
bid and authorizing the execution of a contract for the Repair of 66" RCP Storm Sewer
on Shreveport Avenue with BDS Constructors, LLC, dba MK Constructors of Vidor, Texas,
having submitted the lowest and most responsive bid in the amount of $167,419.00.
Contract time is 120 calendar days.
BACKGROUND
The project includes removing and replacing an existing 66" storm sewer pipe,
constructing two junction boxes, water line replacement, and street
reconstruction/resurfacing on Shreveport Avenue between Procter Street and 5th Street.
Bids were received from two (2) qualified bidders, with BDS Constructors, LLC, dba MK
Constructors, submitting the lowest and most responsive bid for the project. The other
bidder for the project was The Signature Group at $250,468.85.
BUDGET/FISCAL EFFECT
Funding for this project is provided in Project No. GO-805, Account 301-1601-591.84-00.
SUMMARY
I recommend that the City Council approve Proposed Resolution No. 18515.
P.R. No. 18515
8/26/14 sjm
RESOLUTION NO.
A RESOLUTION AUTHORIZING THE AWARD
OF BID AND THE EXECUTION OF A
CONTRACT FOR THE REPAIR OF 66" RCP
STORM SEWER ON SHREVEPORT AVENUE
BETWEEN PROCTER STREET AND 5TH
STREET, WITH BDS CONSTRUCTORS, LLC,
DBA MK CONSTRUCTORS OF VIDOR, TEXAS
IN THE AMOUNT OF $167,419.00, PROJECT NO.
GO-805,ACCOUNT NO.301-1601-591.84-00.
WHEREAS, the City has approved funding for the repair of 66" RCP storm
sewer on Shreveport Avenue; and,
WHEREAS,the Public Works Department, Soutex Surveyors & Engineers, and
the Purchasing Division have solicited bids for the project; and,
WHEREAS, the bids have been evaluated by Soutex Surveyors & Engineers,
and their Recommendation of Award and Bid Tabulation is attached as Exhibit "A";
and,
WHEREAS, BDS Constructors, LLC, dba MK Constructors of Vidor, Texas
has submitted the lowest responsive bid in the amount of$167,419.00; and,
WHEREAS,the contract time is 120 calendar days; NOW THEREFORE,
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF.PORT
ARTHUR:
P.R. No. 18515
8/26/14 sjm
Page 2 of 4
THAT, the award of bid for the Repair of 66" RCP Storm Sewer on Shreveport
Avenue Between Procter Street and 5th Street is hereby made by the City Council to
BDS Constructors, LLC, dba MK Constructors of Vidor, Texas in the amount of
$167,419.00 and 120 calendar days; and,
THAT, the City Manager of the City of Port Arthur is hereby authorized and
directed to execute, on behalf of the City of Port Arthur, the City's standard
construction contract between the City and BDS Constructors, LLC, dba MK
Constructors, for the Repair of 66" RCP Storm Sewer on Shreveport Avenue Between.
Procter Street and 5th Street in the amount of$167,419.00, referenced to as Exhibit `B",
a full copy of which is available for review in the City Secretary's office; and,
THAT, the project will be funded by Project No. GO-805, Account No. 301-
1601-591.84-00, and,
THAT, a copy of the caption of this resolution be spread upon the minutes of
the City Council.
READ, ADOPTED AND APPROVED THIS day of
2014 at a Regular Meeting of the City Council of the City of Port Arthur, Texas, by the
following vote:
P.R. No. 18515
8/26/14 sjm
Page 3 of 4
AYES: Mayor •
Councilmembers:
NOES:
Deloris Prince
Mayor
ATTEST: APPROVED AS TO FORM:
1\ -f
Sherri Bellard Valecia TizY IC�
City Secretary City Attorney
APPROVED FOR ADMINISTRATION:
A
John A. Comeaux,P.E. Shawna Tubbs, CPPO, CPPB
City Manager Purchasing Manager
PR. No. 18515
8/26/14 sjm
Page 4 of 4
Sue McDermott, P.E.
Director of Public Works
APPROVED AS TO AVAILABILTIY OF FUNDS:
$rijt_A A
Deborah Echols
Director of Finance
Project No. GO-805
Account No. 301-1601-591.84-00
EXHIBIT "A"
P.R. No. 18515
August 26, 2014
TBPE Firm No.5755
#7 SOUTDC TBPLS Firm No.1O1238OO
3737'Doctort•Drive
r Port Arth' rTX'71642.
.2004
SURVEYORS ORS&ENGlNJ .IL.1 S Office Fax (409)'983.2005
August 18,2014
City of Port Arthur
444 4th Street
Port Arthur,Texas 77640
Attn: Susan McDermott, Public Works Director
Ref: Repair of 66" RCP Storm Sewer on Shreveport Avenue
Between Procter and 5th Street
Please find enclosed the bid tabulation for the above referenced project. The low bid is that of BDS
Constructors LLC in the amount of$167,419.00. The time is set at 120 calendar days. We recommend
that the award be made to the low bidder, BDS Constructors LLD. Let us know if you have any
questions. A bid tabulation will be sent, under separate cover, to the bidders and AGC. We await
instructions from the City. We are ready to make and produce the contract documents for execution at
your direction.
Yours truly,
74 ) vt/` d 'y
Sta if G. Newso e, PE
c: Shawna Tubbs, Purchasing
Leslie McMahen, Engineering
EXHIBIT "B"
P.R. No. 18515
August 26, 2014
(A complete copy of Exhibit "B" is available for review in the City
Secretary's Office)
,.' REPAIR OF 66"RCP STORM SEWER ON SHREVEPORT AVENUE
'
BETWEEN PROCTER AND 5TH STREET
► CITY OF PORT ARTHUR SOUTEX 13-0646 120 CALENDAR DAYS ALLOWED
BID OPENING:3:15 PM
SOUTEX August 13,2014
SURVEYORS&ENGINEERS BDS CONSTRUCTORS LLD THE SIGNATURE GROUP
Item It Description Unit Qty Unit Price Price Unit Price Price
1 Mobilization,Bonds,Insurance Lump Sum 1 $ 11,000.00 $ 11,000.00 $ 9,890.00 $ 9,890.00
2 Barricades and Traffic Control Plan Lump Sum 1 $ 800.00 $ 800.00 $ 4,470.00 $ 4,470.00
3 Remove Existing Asphalt S.Y. 222 $ 25.00 $ 5,550.00 $ 16.36 $ 3,632.92
4 Saw Existing Concrete to Depth of 2" L.F. 290 $ 8.00 $ 2,320.00 $ 10.00 $ 2,900.00
5 Remove Existing Concrete S.Y. 140 $ 31.00 $ 4,340.00 $ 66.18 $ 9,265.20
6 Excavate Top of Existing 66"RCP L.F. 32 $ 50.00 $ 1,600.00 $ 113.53 $ 3,632.96
to Find Good Joint
I„►",!‘� ` 7 Remove and Replace 66"RCP L.F. 32 $ 993.00 $ 31,776.00 $ 616.05 $ 19,713.60
', ,�f 5 8 Concrete Collar on 66"RCP Each 2 $ 500.00 $ 1,000.00 $ 1,430.86 $ 2,861.72
0J� 1 9 Reinforced Concrete J-Box Each 1 $ 27,667.00 $ 27,667.00 $ 50,292.00 $ 50,292.00
10 Remove Existing Storm Sewer and Install Each 1 $ 2,250.00 $ 2,250.00 $ 17,101.68 $ 17,101.68
e h �w,.• Q ME�M "•fi», 15"RCP at Existing Inlet STA 2+64 RT 51'
.�i•«�'�.«'""" "JR' 11 Remove Existing Storm Sewer and Install Each 1
y0g : g $ 2,250.00 $ 2,250.00 $ 8,047.85 $ 8,047.85
/ °4 8••e « 15"RCP at Existing Inlet STA 2+76, RT 24"
4 l ' 12 Locate Existing Storm Sewer and Install Each 1 $ 3,950.00 $ 3,950.00 $ 15,630.84 $ 15,630.84
A- New Catch Basin at STA 2+51,LT 45'
81 1 611 13 Install Nub in Existing Storm Sewer Each 4 $ 525.00 $ 2,100.00 $ 4,040.00 $ 16,160.00
14 15"RCP C-76 Storm Sewer L.F. 108 $ 80.00 $ 8,640.00 $ 24.42 $ 2,637.36
15 Remove Existing 8"CI Water Line and L.F. 80 $ 104.00 $ 8,320.00 $ 71.54 $ 5,723.20
Replace with 8"PVC C-900 Class 165 psi
(Price Includes Fittings)
16 8"Quantum Coupling Each 1 $ 250.00 $ 250.00 $ 250.00 $ 250.00
17 Remove and Replace Fire Hydrant Unit Each 1 $ 5,870.00 $ 5,870.00 $ 12,285.82 $ 12,285.82
18 11/2 Sack Per CY Cement Stabilized Sand Ton 300 $ 35.00 $ 10,500.00 $ 57.16 $ 17,148.00
19 Select Backfill 60/4012 CY Truck Measure Load 35 $ 120.00 $ 4,200.00 $ 456;58 $ 15,980.30
20 6"Concrete Paving,Curb&Gutter,Alley S.Y. 170 $ 118.00 $ 20,060.00 $ 81.00 $ 13,770.00
21 Hot Mix Asphalt Ton 56 $ 196.00 $ 10,976.00 $ 167.15 $ 9,360.40
22 5'x5'x12"Thick Concrete Blockout Each 1 $ 500.00 $ 500.00 $ 1,500.00 $ 1,500.00
23 Trench Safety,Erosion Control Plans L.S. 1 $ 1,500.00 $ 1,500.00 $ 8,215.00 $ 8,215.00
TOTALS $ 167,419.00 $ 250,468.85
R.
REPAIR OF 66" RCP STORM SEWER ON SHREVEPORT AVENUE
BETWEEN PROCTER AND 5TH STREET
CITY OF PORT ARTHUR SOUTEX 13-0646 120 CALENDAR DAYS ALLOWED
BDS CONSTRUCTORS LLD THE SIGNATURE GROUP
Unit Qty Unit Price Price Unit Price Price
ce Lump Sum 1 $ 11,000.00 $ 11,000.00 $ 9,890.00 $ 9,890.00
I Plan Lump Sum 1 $ 800.00 $ 800.00 $ 4,470.00 $ 4,470.00
S.Y. 222 $ 25.00 $ 5,550.00 $ 16.36 $ 3,632.92
fffith of 2" L.F. 290 $ 8.00 $ 2,320.00 $ 10.00 $ 2,900.00
S.Y. 140 $ 31.00 $ 4,340.00 $ 66.18 $ 9,265.20
RCP L.F. 32 $ 50.00 $ 1,600.00 $ 113.53 $ 3,632.96
L.F. 32 $ 993.00 $ 31,776.00 $ 616.05 $ 19,713.60
Each 2 $ 500.00 $ 1,000.00 $ 1,430.86 $ 2,861.72
Each 1 $ 27,667.00 $ 27,667.00 $ 50,292.00 $ 50,292.00 .
r and Install Each 1 $ 2,250.00 $ 2,250.00 $ 17,101.68 $ 17,101.68
2+64 RT 51'
'r and Install Each 1 $ 2,250.00 $ 2,250.00 $ 8,047.85 $ 8,047.85
2+76, RT 24"
and Install Each 1 $ 3,950.00 $ 3,950.00 $ 15,630.84 $ 15,630.84
1, LT 45'
Sewer Each 4 $ 525.00 $ 2,100.00 $ 4,040.00 $ 16,160.00
L.F. 108 $ 80.00 $ 8,640.00 $ 24.42 $ 2,637.36
Line and L.F. 80 $ 104.00 $ 8,320.00 $ 71.54 $ 5,723.20
lass 165 psi
Each 1 $ 250.00 $ 250.00 $ 250.00 $ 250.00
drant Unit Each 1 $ 5,870.00 $ 5,870.00 $ 12,285.82 $ 12,285.82
rbilized Sand Ton 300 $ 35.00 $ 10,500.00 $ 57.16 $ 17,148.00
ruck Measure Load 35 $ 120.00 $ 4,200.00 $ 456.58 $ 15,980.30
Butter,Alley S.Y. 170 $ 118.00 $ 20,060.00 $ 81.00 $ 13,770.00
Ton 56 $ 196.00 $ 10,976.00 $ 167.15 $ 9,360.40
ckout Each 1 $ 500.00 $ 500.00 $ 1,500.00 $ 1,500.00
of Plans L.S. 1 $ 1,500.00 $ 1,500.00 $ 8,215.00 $ 8,215.00
TOTALS $ 167,419.00 $ 250,468.85