HomeMy WebLinkAboutPR 18740: CHANGE ORDER NO. 1 EDC, EXCAVATORS & CONSTRUCTORS, LTD FOR WATER, SANITARY SEWER, PAVING, DRAINAGE FACILITIES Interoffice MEMORANDUM To: Mayor, City Council, City Manager From: Floyd Batiste, CEO Date: November 19, 2014 Subject: P. R. No. 18740; Council Meeting of November 25, 2014 ATTACHED IS PROPOSED RESOLUTION 18740 APPROVING CHANGE ORDER NO. 1 TO THE AGREEMENT BETWEEN THE CITY OF PORT ARTHUR SECTION 4A ECONOMIC DEVELOPMENT CORPORATION AND EXCAVATORS & CONSTRUCTIONS, LLC, FOR THE WATER, SANITARY SEWER, PAVING, DRAINAGE FACILITIES AND SITE GRADING TO SERVE PROPOSED KAPRINA FRANK DRIVE IN THE SPUR 93 BUSINESS PARK P.R. No. 18740 11/18/2014 RESOLUTION NO. A RESOLUTION APPROVING CHANGE ORDER NO. 1 TO THE CONTRACT BETWEEN THE CITY OF PORT ARTHUR SECTION 4A ECONOMIC DEVELOPMENT CORPORATION AND EXCAVATORS & CONSTRUCTORS, LTD. FOR THE WATER, SANITARY SEWER, PAVING, DRAINAGE FACILITIES AND SITE GRADING TO SERVE PROPOSED KAPRINA FRANK DRIVE IN THE SPUR 93 BUSINESS PARK WHEREAS, on July 22nd 2014, per Resolution 14-326, the City Council of the City of Port Arthur approved a contract between the City of Port Arthur Section 4A Economic Development Corporation (the "PAEDC") and Excavators & Constructors, Ltd. for water, sanitary sewer, paving and drainage facilities to serve proposed Kaprina Frank Drive in the Spur 93 Business Park; and WHEREAS, on October 6, 2014, the PAEDC Board of Directors approved the extension of the proposed 8" sanitary sewer line to the north side of the proposed Kaprina Frank Drive to serve future development; and WHEREAS,the contractor, Excavators & Constructors, Ltd. is requesting to increase the contract time by 23 days due to weather delays, moving the completion date from February 11, 2015 to March 6, 2015; and WHEREAS, the cost of this Change Order will increase the contract amount by $7,290.40, which increases the total contract from $482,767.95 to $490,058.35 as shown in Exhibit"A". NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF PORT ARTHUR: Section 1. That the facts and opinions in the preamble are true and correct. Section 2. That the City Council approves Change Order No. 1 to increase the contract time by 23 days due to weather delays moving the completion date from February 11, 2015 to March 6, 2015, for a total of 173 days, and increases the contract amount by $7,290.40 which increases the total contract amount from $482,767.95 to $490,058.35 as shown in Exhibit"A". Section 3. That a copy of the caption of this Resolution be spread upon the Minutes of the City Council. READ,ADOPTED AND APPROVED on this day of A.D., 2014, at a Meeting of the City Council of the City of Port Arthur, Texas, by the following vote: AYES: Mayor Councilmembers NOES: Deloris "Bobbie" Prince, Mayor ATTEST: Sherri Bellard, City Secretary #1131595 Pate 2 APPROVED: Floyd Batiste, PAEDC CEO APPROVED AS TO FORM: Guy N. Goodson, PAEDC Attorney APPROVED AS TO FORM: Valecia Tizeno` ity Attorn W #1131598 Page 3 EXHIBIT "A" EXHIBIT "A" • ARCENEAUX WILSON & COLE LLC Arceneaux Wilson & Cole AWCEngineering • Surveying • Planning November 10, 2014 Mr. Floyd Batiste, CEO Port Arthur Economic Development Corporation 4173 39th Street Port Arthur, Texas 77642 RE; CHANGE ORDER NO. I Water, Sanitary Sewer, Paving, Drainage Facilities and Site Grading to serve Proposed"Kaprina Frank Drive" A&G Job No. EDC-180 Dear Mr. Batiste: Attached is Change Order No. 1 for the Water, Sanitary Sewer, Paving, Drainage Facilities and Site Grading to serve Proposed "Kaprina Frank Drive" project. This change order is for the extension of the proposed 8" sanitary sewer line to the north side of the proposed Kaprina Frank Drive to serve future development. The extension of this line will serve future development on the north side of the proposed roadway. Also, this change order is a request to increase the contract time by 23 days. The contractor has requested a time extension of 23 days due to weather delays. The total cost for this change order will increase the contract amount $ 7,290.40. I recommend that the City of Port Arthur authorize this change to the contract. I have attached Change Order No. 1 which modifies the contract to reflect this change for your consideration and action. Should you have any questions or require additional information, please contact our office. Very truly yours, Arceneaux Wilson & Cole LLC TEXAS REGISTERED ENGINEERING FIRM F-16194 /ve Keestan Cole, PE Vice-President (409) 724-7888 • 2901 Turtle Creek Drive • Suite 320 • Port Arthur, Texas 77642 www.awceng.com ArCenea, Wilson & Coie--- -'�;,y „ginre»nT AWC • ,an, m .i, ar»„ CHANGE ORDER No. 1 DATE: November 10, 2014 JOB NO. EDC-180 AGREEMENT DATE: September 15, 2014 NAME OF PROJECT: Water, Sanitary Sewer, Paving, Drainage Facilities and Site Grading OWNER: CITY of PORT ARTHUR CONTRACTOR: Excavators & Constructors, LTD. The following changes are hereby made to the CONTRACT DOCUMENTS: 1. Add to Adjust the following Items to the Contract and Scope of Work: a. Extend contract time by 23 days b. Bid Item No. 29, Increase 8" PVC Sewer (112 L.F./ $44.80) $ 5,017.60 c. Bid Item No. 30, Increase Trench Safety (112 L.F./ $0.65) $ 72.80 d. Bid Item No. 41, Extra-Cement Stabilized Sand (44 C.Y./ $50.00) $ 2,200.00 SUBTOTAL $ 7,290.40 CHANGE ORDER NO. 1 November 10, 2014 Job No. EDC-180, Contract No. 1 AWC Engineering Suneying Planning CHANGE TO CONTRACT PRICE: ORIGINAL CONTRACT PRICE: $482,767.95 CURRENT CONTRACT PRICE adjusted by previous CHANGE ORDER(S): $482,767.95 The CONTRACT PRICE due to this CHANGE ORDER will be [increased] [decreased] by: $7,290.40 Dollars The new CONTRACT PRICE, including this CHANGE ORDER, will be $490,058.35 CHANGE TO CONTRACT TIME: ORIGINAL CONTRACT TIME: 150 Calendar Days CURRENT CONTRACT TIME adjusted by previous CHANGE ORDER: 0 Calendars Days CURRENT DATE OF COMPLETION: February 11, 2015 CONTRACT TIME due to this CHANGE ORDER will be increased by 23 Days The New DATE OF COMPLETION: March 6, 2015 No other Terms and Conditions of the Contract are changed as a result of this Change Order. Contractor's acceptance of Change Order relieves OWNER of any liability for additional costs incurred by Contractor in his performance of the work covered by the Change Order. RECOMMENDED BY ENGINEER: ACCEPTED BY: ARCENEAUX WILSON & COLE LLC [CONTRAC ,OFF?ER OR OWNER] EXC ATORS & CONSTRUCTORS, LTD. ACCEPTED BY: CITY of PORT ARTHUR Eccnlo,..ic ►` vat°Q,. ----+ Core°("A+°• 2 of 2