MEMORANDUM
To: Mayor, City Council, City Manager
From: Floyd Batiste, CEO
Date: November 19, 2014
Subject: P. R. No. 18740; Council Meeting of November 25, 2014
ATTACHED IS PROPOSED RESOLUTION 18740
APPROVING CHANGE ORDER NO. 1 TO THE
AGREEMENT BETWEEN THE CITY OF PORT ARTHUR
SECTION 4A ECONOMIC DEVELOPMENT
CORPORATION AND EXCAVATORS &
CONSTRUCTIONS, LLC, FOR THE WATER, SANITARY
SEWER, PAVING, DRAINAGE FACILITIES AND SITE
GRADING TO SERVE PROPOSED KAPRINA FRANK
DRIVE IN THE SPUR 93 BUSINESS PARK
P.R. No. 18740
11/18/2014
RESOLUTION NO.
A RESOLUTION APPROVING CHANGE ORDER NO. 1
TO THE CONTRACT BETWEEN THE CITY OF PORT
ARTHUR SECTION 4A ECONOMIC DEVELOPMENT
CORPORATION AND EXCAVATORS &
CONSTRUCTORS, LTD. FOR THE WATER, SANITARY
SEWER, PAVING, DRAINAGE FACILITIES AND SITE
GRADING TO SERVE PROPOSED KAPRINA FRANK
DRIVE IN THE SPUR 93 BUSINESS PARK
WHEREAS, on July 22nd 2014, per Resolution 14-326, the City Council of the City of
Port Arthur approved a contract between the City of Port Arthur Section 4A Economic
Development Corporation (the "PAEDC") and Excavators & Constructors, Ltd. for water,
sanitary sewer, paving and drainage facilities to serve proposed Kaprina Frank Drive in the Spur
93 Business Park; and
WHEREAS, on October 6, 2014, the PAEDC Board of Directors approved the extension
of the proposed 8" sanitary sewer line to the north side of the proposed Kaprina Frank Drive to
serve future development; and
WHEREAS,the contractor, Excavators & Constructors, Ltd. is requesting to increase the
contract time by 23 days due to weather delays, moving the completion date from February 11,
2015 to March 6, 2015; and
WHEREAS, the cost of this Change Order will increase the contract amount by
$7,290.40, which increases the total contract from $482,767.95 to $490,058.35 as shown in
Exhibit"A".
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE
CITY OF PORT ARTHUR:
Section 1. That the facts and opinions in the preamble are true and correct.
Section 2. That the City Council approves Change Order No. 1 to increase the contract
time by 23 days due to weather delays moving the completion date from February 11, 2015 to
March 6, 2015, for a total of 173 days, and increases the contract amount by $7,290.40 which
increases the total contract amount from $482,767.95 to $490,058.35 as shown in Exhibit"A".
Section 3. That a copy of the caption of this Resolution be spread upon the Minutes of
the City Council.
READ,ADOPTED AND APPROVED on this day of A.D., 2014,
at a Meeting of the City Council of the City of Port Arthur, Texas, by the following vote:
AYES:
Mayor
Councilmembers
NOES:
Deloris "Bobbie" Prince, Mayor
ATTEST:
Sherri Bellard, City Secretary
#1131595 Pate 2
APPROVED:
Floyd Batiste, PAEDC CEO
APPROVED AS TO FORM:
Guy N. Goodson, PAEDC Attorney
APPROVED AS TO FORM:
Valecia Tizeno` ity Attorn W
#1131598 Page 3
EXHIBIT "A"
EXHIBIT "A"
•
ARCENEAUX WILSON & COLE LLC
Arceneaux Wilson & Cole
AWCEngineering • Surveying • Planning
November 10, 2014
Mr. Floyd Batiste, CEO
Port Arthur Economic Development Corporation
4173 39th Street
Port Arthur, Texas 77642
RE; CHANGE ORDER NO. I
Water, Sanitary Sewer, Paving, Drainage Facilities and Site Grading to
serve Proposed"Kaprina Frank Drive"
A&G Job No. EDC-180
Dear Mr. Batiste:
Attached is Change Order No. 1 for the Water, Sanitary Sewer, Paving, Drainage
Facilities and Site Grading to serve Proposed "Kaprina Frank Drive" project. This change order
is for the extension of the proposed 8" sanitary sewer line to the north side of the proposed
Kaprina Frank Drive to serve future development. The extension of this line will serve future
development on the north side of the proposed roadway. Also, this change order is a request to
increase the contract time by 23 days. The contractor has requested a time extension of 23
days due to weather delays. The total cost for this change order will increase the contract
amount $ 7,290.40. I recommend that the City of Port Arthur authorize this change to the
contract. I have attached Change Order No. 1 which modifies the contract to reflect this change
for your consideration and action. Should you have any questions or require additional
information, please contact our office.
Very truly yours,
Arceneaux Wilson & Cole LLC
TEXAS REGISTERED ENGINEERING FIRM F-16194
/ve
Keestan Cole, PE
Vice-President
(409) 724-7888 • 2901 Turtle Creek Drive • Suite 320 • Port Arthur, Texas 77642
www.awceng.com
ArCenea, Wilson & Coie--- -'�;,y
„ginre»nT
AWC •
,an,
m .i,
ar»„
CHANGE ORDER No. 1
DATE: November 10, 2014 JOB NO. EDC-180
AGREEMENT DATE: September 15, 2014
NAME OF PROJECT: Water, Sanitary Sewer, Paving, Drainage Facilities and Site Grading
OWNER: CITY of PORT ARTHUR
CONTRACTOR: Excavators & Constructors, LTD.
The following changes are hereby made to the CONTRACT DOCUMENTS:
1. Add to Adjust the following Items to the Contract and Scope of Work:
a. Extend contract time by 23 days
b. Bid Item No. 29, Increase 8" PVC Sewer
(112 L.F./ $44.80) $ 5,017.60
c. Bid Item No. 30, Increase Trench Safety
(112 L.F./ $0.65) $ 72.80
d. Bid Item No. 41, Extra-Cement Stabilized Sand
(44 C.Y./ $50.00) $ 2,200.00
SUBTOTAL $ 7,290.40
CHANGE ORDER NO. 1
November 10, 2014
Job No. EDC-180, Contract No. 1
AWC Engineering
Suneying
Planning
CHANGE TO CONTRACT PRICE:
ORIGINAL CONTRACT PRICE: $482,767.95
CURRENT CONTRACT PRICE adjusted by previous CHANGE ORDER(S): $482,767.95
The CONTRACT PRICE due to this CHANGE ORDER will be [increased] [decreased]
by: $7,290.40 Dollars
The new CONTRACT PRICE, including this CHANGE ORDER, will be $490,058.35
CHANGE TO CONTRACT TIME:
ORIGINAL CONTRACT TIME: 150 Calendar Days
CURRENT CONTRACT TIME adjusted by previous CHANGE ORDER: 0 Calendars Days
CURRENT DATE OF COMPLETION: February 11, 2015
CONTRACT TIME due to this CHANGE ORDER will be increased by 23 Days
The New DATE OF COMPLETION: March 6, 2015
No other Terms and Conditions of the Contract are changed as a result of this Change Order.
Contractor's acceptance of Change Order relieves OWNER of any liability for additional costs
incurred by Contractor in his performance of the work covered by the Change Order.
RECOMMENDED BY ENGINEER: ACCEPTED BY:
ARCENEAUX WILSON & COLE LLC [CONTRAC ,OFF?ER OR OWNER]
EXC ATORS & CONSTRUCTORS, LTD.
ACCEPTED BY:
CITY of PORT ARTHUR Eccnlo,..ic ►` vat°Q,. ----+ Core°("A+°•
2 of 2