HomeMy WebLinkAboutPR 18782: ALLCO, L.L.C., FOR HWY 87 WATER SYSTEM IMPROVEMENTS FROM KEITH LAKE TO SABINE PASS STANDPIPE MEMORANDUM
CITY OF PORT ARTHUR
Utility Operations Department
TO: John A. Comeaux, P.E., Interim City Manager
FROM: Jimmie Johnson, PhD., Director of Utility Ope ins
DATE: December 16, 2014
RE: Proposed Resolution No. 18782
RECOMMENDATION
I recommend that the City Council approve Proposed Resolution No. 18782 authorizing
the City Manager to execute Change Order No. 6 to the contract with ALLCO, L.L.C., of
Beaumont, Texas, for construction of the Highway 87 Water Transmission Line project
from Keith Lake to the Sabine Pass standpipe, this Change Order is for a time
extension of eleven (11) days due to weather delays and a contact increase of
$79, 675.00. This change order is for the extension of three directional drills due to soil
conditions in the working area. The extension of these drills will remove open cut
installation that is not feasible due to the intrusion of water in the working area during
tidal influxes.
BACKGROUND
On October 29, 2013, City Council approved the award of a contract in the amount of
$3,373,385.00 to ALLCO, L.L.C. for the construction of the Highway 87 Water
Transmission Line from the cut at Keith Lake to the new standpipe in Sabine Pass.
BUDGET/FISCAL EFFECT
Pursuant to Resolution No. 12-597, funding for this project is through City Account No.
429-1258-532.59-00, Project No. WSI002.
SUMMARY
I recommend that the City Council approve Proposed Resolution No. 18782 authorizing
the City Manager to execute Change Order No. 6 for a time extension of 11 days due to
weather delays and a contract increase of $79,675.00, to the Highway 87 Water
Transmission project contract with ALLCO, L.L.C.
P.R. No. 18782
11/19/14 jj
RESOLUTION NO.
A RESOLUTION AUTHORIZING THE CITY MANAGER
TO EXECUTE CHANGE ORDER NO. 6 TO THE
CONTRACT BETWEEN THE CITY OF PORT ARTHUR
AND ALLCO, L.L.C., OF BEAUMONT, TEXAS, FOR THE
HIGHWAY 87 WATER SYSTEM IMPROVEMENTS
FROM KEITH LAKE TO SABINE PASS STANDPIPE, IN
AN AMOUNT NOT TO EXCEED $79,675.00,
INCREASING THE CONTRACT AMOUNT TO
$3,597,522.89 AND CONTRACT TIME BY 11 DAYS, TO A
NEW CONTRACT TIME OF 305 DAYS, PROJECT NO.
WSI002, ACCOUNT NO. 429-1258-532.59-00.
WHEREAS, per Resolution No. 13-492 dated October 29, 2013, the City Council
awarded a contract for the construction of the Highway 87 Water Transmission Line for Keith
Lake to the Sabine Pass Standpipe to ALLCO, L.L.C., in the amount of$3,373,385.00; and,
WHEREAS, per Resolution No. 14-224, Change Order No. 1 authorized the increase in
pipe material costs from October 29, 2013, and the increased cost to purchase the pipe material
for the project in the amount of$144,462.89 to a new contract total of$3,517,847.89; and,
WHEREAS, per Resolution No. 14-388, Change Order No. 2 authorized a time extension
of 4 days due to weather delays to a new contract time of 274 days; and
WHEREAS, per Resolution No. 14-450, Change Order No. 3 authorized a time
extension of six (6) days due to weather delays to a new contract time of 280 days; and
WHEREAS,per Resolution No. 14-555, Change Order No. 4 authorized a time extension
of seven(7) days due to weather delays to a new contract time of 287 days; and
WHEREAS, per Resolution No. 14-608, Change Order No. 5 authorized a time
extension of seven (7) days due to weather delays to a new contract time of 294 days; and
P.R. No. 18782
12/16/14 jj
Page 2 of 3
WHEREAS, Allco, LLC of Beaumont, Texas has requested a time extension of eleven
(11) days due to weather delays to a new contract time of 305 days and a contract price increase
of $79, 675.00 due to the extension of three directional drills due to soil conditions in the
working area. The extension of these drills will remove open cut installation that is not feasible
due to the intrusion of water in the working area during tidal influxes.
WHEREAS, the project engineer, Arceneaux Wilson & Cole LLC, recommends
proposed Change Order No. 6 for a time extension of eleven (11) days and a contract price
increase of $79, 675.00, attached as Exhibit"A",to accomplish this work.
NOW THEREFORE,BE IT RESOLVED BY THE CITY COUNCIL OF THE
CITY OF PORT ARTHUR:
THAT, the City Manager of the City of Port Arthur is hereby authorized and directed to
execute, on behalf of the City of Port Arthur, Change Order No. 6 (attached as Exhibit "A") to
the contract between the City of Port Arthur and ALLCO, L.L.C. of Beaumont, Texas, for the
work described therein, increasing the total contract time by eleven(11)days; and,
THAT, Change Order No. 6 increases the contract time to 305 days with a new
completion date of April 2, 2015; and,
THAT, Change Order No. 6 will require additional funding of$79,675.00 by the Project
No. WSI002, City Account No. 429-1258-532.59-00; and,
THAT, a copy of the caption of this resolution be spread upon the minutes of the City
Council.
READ, ADOPTED AND APPROVED THIS day of , 2014 at a
Regular Meeting of the City Council of the City of Port Arthur, Texas, by the following vote:
P.R. No. 18782
12-16-14
Page 3 of 3
AYES: Mayor:
Councilmembers:
NOES:
Debris Prince
Mayor
ATTEST: APPROVED AS TO FORM:
Y�
Sherri Bellard Valecia Tizeno
City Secretary City Attorney
APPROVED FOR ADMINISTRATION:
i a,t,14t C1 -„..J
John A. Comeaux, P.E. Shawna Tubbs, CPPO, CPPB
Inte '2ianager Purchasing Manager
Jimmie Johnson, PhD
Director of Utilities
APP' I VED AS TO AVAILABILITY OF FUNDS:
i / / - y
Deborah Echols
Director of Finance
Account No. 429-1258-532.59-00
Project No. WSI002
Exhibit "A"
(AW&C Change Order No. 6)
ARCENEAUX WILSON & COLE LL ;
Ar“ncaux Wilson & Cole ..
AWCEngineering • Surveying • Planning
December 11 , 2014
Mr. Jimmie Johnson
Director of Water Utilities
City of Port Arthur
444 Fourth Street
Port Arthur, Texas 77640
RE: PROPOSAL FOR CHANGE ORDER NO 6
STATE HIGHWAY 87 WATER SYSTEM IMPROVEMENTS FROM KEITH
LAKE TO SABINE PASS STANDPIPE
Job No. CPA-705
Dear Mr. Johnson:
Attached is Change Order No. 6 for the State Highway 87 Water System Improvements from
Keith Lake to Sabine Pass Standpipe. This change order is for the extension of three
directional drills due to soil conditions in the working area. The extension of these drills will
remove open cut installation that is not feasible due to the intrusion of water in the working area
during tidal influxes. This change order is also for time extension of 11 days due to weather
delays. I recommend that the City of Port Arthur authorize this change to the contract. The total
cost for this change order will increase the contract amount $79,675.00. I recommend that the
City of Port Arthur authorize this change to the contract. I have attached Change Order No. 6
which modifies the contract to reflect this change for your consideration and action. Should you
have any questions or require additional information, please contact our office.
Very truly yours,
ARCENEAUX WILSON & COLE LLC
TEXAS REGISTERED ENGINEERING FIRM F-16194
eestan Cole, PE
Vice President
2901 Turtle Creek Dr.,Suite 320 Port Arthur,TX 77642 Phone: 409/724-7888 Fax: 409/724-1447
Arc¢neau: WUson 8 Col¢---
Ingincenng
I'tartnir{k
CHANGE ORDER No. 6
DATE: December 9, 2014 JOB NO. CPA-705
AGREEMENT DATE: November 5, 2013
NAME OF PROJECT: State Highway 87 Water System Improvements
OWNER: CITY of PORT ARTHUR
CONTRACTOR: ALLCO
The following changes are hereby made to the CONTRACT DOCUMENTS:
1. Add the following Items to the Contract and Scope of Work:
a. Increase 420 L.F., 20-Inch, DR-11 HDPE
(Bid Item No. 4/$178.00 L.F.) [+] $ 74,760.00
b. Increase in Cost of 30-Inch, DR-11 HDPE
($27.00 L.F.) [+] $ 11,340.00
c. Decrease in Cost Fire Hydrant Assembly
($1,285.00 L.F.) [-I $ 6,425.00
d. Extend contract time by 11 days
TOTAL $ 79,675.00
CHANGE ORDER NO. 6
December 9, 2014
Job No CPA-705
AWC
CHANGE TO CONTRACT PRICE:
ORIGINAL CONTRACT PRICE: $3,373,385.00
CURRENT CONTRACT PRICE adjusted by previous CHANGE ORDER:S): 3,517,847.89
The CONTRACT PRICE due to this CHANGE ORDER will be [increased] [decreased]
by: $79,675.00 Dollars
The new CONTRACT PRICE, including this CHANGE ORDER, will be $3,597,522.89
CHANGE TO CONTRACT TIME:
ORIGINAL CONTRACT TIME: 270 Calendar Days
CURRENT CONTRACT TIME adjusted by previous CHANGE ORDER: 24 Calendar Days
CURRENT DATE OF COMPLETION: March 22, 2015
CONTRACT TIME due to this CHANGE ORDER will be increased by 11 Days
The New DATE OF COMPLETION: April 2, 2015
No other Terms and Conditions of the Contract are changed as a result of this Change Order.
Contractor's acceptance of Change Order relieves OWNER of any liability for additional costs
incurred by Contractor in his performance of the work covered by the Change Order.
RECOMMENDED BY ENGINEER: ACCEPTED BY:
AR ENEAU WILSON & COLE LLC [C TRACTOR,OFFICE OR OWNE
ALLCO
ACCEPTED BY:
CITY of PORT ARTHUR
2 of 2
CHANGE ORDER NO. 6
December 9, 2014
Job No. CPA-705
AWC
CHANGE TO CONTRACT PRICE:
ORIGINAL CONTRACT PRICE: $3,373,385.00
CURRENT CONTRACT PRICE adjusted by previous CHANGE ORDER(S): 3,517,847.89
The CONTRACT PRICE due to this CHANGE ORDER will be [increased] [decreased]
by: $79,675.00 Dollars
The new CONTRACT PRICE, including this CHANGE ORDER, will be $3,597,522.89
CHANGE TO CONTRACT TIME:
ORIGINAL CONTRACT TIME: 270 Calendar Days
CURRENT CONTRACT TIME adjusted by previous CHANGE ORDER: 24 Calendar Days
CURRENT DATE OF COMPLETION: March 22, 2015
CONTRACT TIME due to this CHANGE ORDER will be increased by 11 Days
New DATE OF COMPLETION: Aril 2 2015
The Ne O CO O p ,
No other Terms and Conditions of the Contract are changed as a result of this Change Order.
Contractor's acceptance of Change Order relieves OWNER of any liability for additional costs
incurred by Contractor in his performance of the work covered by the Change Order.
RECOMMENDED BY ENGINEER: ACCEPTED BY:
ARCENEAUX WILSON & COLE LLC [CONTRACTOR,OFFICER OR OWNER
ALLCO
ACCEPTED BY:
CITY of PORT ARTHUR
2 of 2
•
CHANGE ORDER NO. 6
December 9, 2014
Job No. CPA-705
AWC
CHANGE TO CONTRACT PRICE:
ORIGINAL CONTRACT PRICE: $3,373,385.00
CURRENT CONTRACT PRICE adjusted by previous CHANGE ORDER'S): 3,517,847.89
The CONTRACT PRICE due to this CHANGE ORDER will be [increased] [decreased]
by: $79,675.00 Dollars
The new CONTRACT PRICE, including this CHANGE ORDER, will be S3,597,522.89
CHANGE TO CONTRACT TIME:
ORIGINAL CONTRACT TIME: 270 Calendar Days
CURRENT CONTRACT TIME adjusted by previous CHANGE ORDER: 24 Calendar Days
CURRENT DATE OF COMPLETION: March 22, 2015
CONTRACT TIME due to this CHANGE ORDER will be increased by 11 Days
The New DATE OF COMPLETION: April 2, 2015
No other Terms and Conditions of the Contract are changed as a result of this Change Order.
Contractor's acceptance of Change Order relieves OWNER of any liability for additional costs
incurred by Contractor in his performance of the work covered by the Change Order.
RECOMMENDED BY ENGINEER: ACCEPTED BY:
_ _ mo.
RCENEAUX WILSON & COLE LLC [CI TRACTOR,OFFICER OR OWN ']
ALLCO
ACCEPTED BY:
CITY of PORT ARTHUR
2 of 2
CHANGE ORDER NO. 6
December 9, 2014
Job No. CPA-705
AWC
CHANGE TO CONTRACT PRICE:
ORIGINAL CONTRACT PRICE: $3,373,385.00
CURRENT CONTRACT PRICE adjusted by previous CHANGE ORDER.;S): 3,517,847.89
The CONTRACT PRICE due to this CHANGE ORDER will be [increased] [decreased]
by: $79,675.00 Dollars
The new CONTRACT PRICE, including this CHANGE ORDER, will be $3,597,522.89
CHANGE TO CONTRACT TIME:
ORIGINAL CONTRACT TIME: 270 Calendar Days
CURRENT CONTRACT TIME adjusted by previous CHANGE ORDER: 24 Calendar Days
CURRENT DATE OF COMPLETION: March 22, 2015
CONTRACT TIME due to this CHANGE ORDER will be increased by 11 Days
The New DATE OF COMPLETION: April 2, 2015
No other Terms and Conditions of the Contract are changed as a result of this Change Order.
Contractor's acceptance of Change Order relieves OWNER of any liability for additional costs
incurred by Contractor in his performance of the work covered by the Change Order.
RECOMMENDED BY ENGINEER: ACCEPTED BY:
ARCENEAUX WILSON & COLE LLC [C NTRACTOR,OFFICER OR OWNEfj:
ALLCO
ACCEPTED BY:
CITY of PORT ARTHUR
2 of 2
(04(/(04-
REQUEST FOR EXTENSION OF TEVIE DUE TO WEATHER OR SUPPLIES
CITY OF PORT ARTHUR
DATE: Dee• 3 , 20 Z,b/SG
MONTH OF: /41/6//1 064-- , 20 /li'
CITY of PORT ARTHUR, TEXAS
PUBLIC WORKS DEPARTMENT
P.O. BOX 1089
CITY of PORT ARTHUR,TEXAS 77641-1089
ATTENTION: Ross Blackketter, P.E.,
Public Works Director
Gentlemen:
We request extension of completion time on our Contract due to the days of work lost as
specified(list dates actually lost: do not include days not normally worked such as Saturdays,
Sundays, or holidays):
Dates Lost: i//G ,/ 7 /03 /1/1 6/ l n Iv/ '/ j '/f 2-s
Days Lost( 0 ), 5 x 7 + 1/ Calendar Days Requested
Reasons for Request:
Contractor /4we--o
By: g,
Approved for extension of calendar days.
Disapproved.
Date: , 20 CITY OF CITY OF PORT ARTHUR,
TEXAS
BY:
City Manager
Distribution by City
Original: Public Works Department
xc: Engineer
Contractor
CPA Federally Funded
I