HomeMy WebLinkAboutPR 18783: ALLCO, L.L.C., FOR THE 24" WATERLINE FORM 19TH STREET TO SABINE NECHES CANAL MEMORANDUM CITY OF PORT ARTHUR UTILITY OPERATIONS DEPARTMENT TO: John A. Comeaux P.E., City Manager Mana 9 FROM: Jimmie Johnson, Director of Utility Operatio s/c DATE: December 16, 2014 RE: Proposed Resolution No. 18783 RECOMMENDATION I recommend that the City Council approve Proposed Resolution No. 18783 authorizing the execution of Change Order No. 8 for the 24" Waterline from 19th Street to the Sabine Neches Canal Project with ALLCO, L.L.C., of Beaumont, Texas. This change order is for additional HDPE footage is needed to clear existing underground structure that was unknown. Also, included in this change order is a time extension of four (4) days due to weather delays. This change order is in the amount of $53,614.40. BACKGROUND This project will extend a 24" water transmission main from the old Water Purification Plant to W. 7th Street and SH 82. BUDGET/FISCAL EFFECT Pursuant to Resolution No. 12-597, funding for this project will be charged through a City Account No. 429-1258-532.59-00, Project No. WS1003. SUMMARY I recommend that the City Council approve Proposed Resolution No.18783. P. R. No. 18783 12/16/14j j RESOLUTION NO. A RESOLUTION AUTHORIZING THE CITY MANAGER TO EXECUTE CHANGE ORDER NO. 8 BETWEEN THE CITY OF PORT ARTHUR AND ALLCO, L.L.C.; FOR THE 24" WATERLINE FROM 19TH STREET TO THE SABINE NECHES CANAL, IN AN AMOUNT NOT-TO- EXCEED $53,614.40, INCREASING THE CONTRACT AMOUNT TO $3,446,001.40, AND A TIME EXTENSION OF FOUR (4) DAYS, INCREASING THE CONTRACT TIME TO 399 DAYS. UTILITY OPERATIONS ACCOUNT NO. 429-1258-532.59-00, PROJECT NO. WSI003. WHEREAS, per Resolution No. 13-503, the City entered into a contract for the installation of a Waterline from 19th Street to the Sabine Neches Canal, in the amount of $3,114,960.00,with a contract term of 365 calendar days; and WHEREAS, per Resolution No. 14-210, Change Order 1 authorized an additional $40,486.00 to add storm water pollution prevention measures required by the City of Port Arthur that was not included in the original contract, bringing the contract price for the project to $3,155,446.00 accepted by Allco; and WHEREAS, per Resolution No. 14-300, Change Order 2 authorized a credit of $21,980.00 for the use of 24" Certa-Loc restrained joint C900 PVC pipe in lieu of the 24" cement lined restrained joint gasket ductile iron pipe in the original bid to a new contract total of $3,133,466, and a time extension of six (6) days due to inclement weather bring the date of completion to January 25, 2015; and WHEREAS, per Resolution No. 14-342, Change Order 3 authorized an additional $12,072.00 for the relocation of an existing 6"waterline that was discovered during construction on Charleston Ave, the re-route of the 24" waterline to miss an existing storm sewer, and one foot of extra cover added to the 24" waterline approx. 2,100 L.F. to ensure protection of the line during the 18th Street construction project to a new contract total of$3,145,538.00,and a time l II P. R. No. 18783 12/16/14jj Page 2 of 4 extension of six (6) days due to inclement weather, bringing the date of completion to January 31, 2015; and, WHEREAS, per Resolution No. 14-389, Change Order 4, authorized a time extension of 3 days due to weather delays,to a new completion date of February 3, 2015; and, WHEREAS, per Resolution No. 14-449, Change Order 5, authorized the relocation of the proposed 24"waterline to avoid an existing structure at the intersection of 18th Street and Railroad Ave. in the amount not to exceed $53,100.00 to a new contract total of$3,198,638.00 and a time extension of three(3)days due to inclement weather bring the date of completion to February 6,2015; and, WHEREAS,per Resolution No. 14-554, Change Order 6, authorized the relocation of an existing 12"waterline at Railroad Ave. in the amount not to exceed$52,659.00,and a time extension of eight(8) days due to inclement weather; and, WHEREAS, per Resolution No. 14-607, Change Order 7, authorized the performing a 20-inch hot tap on an existing 20-inch waterline on Atlanta Street and an additional 250 feet of 30-inch, DR-11 HDPE of directional drilling in an amount not to exceed$141,090.00, and a time extension of four(4) days due to inclement weather; and, WHEREAS, Allco, LLC of Beaumont, Texas has requested a time extension of four (4) days due to weather delays to a new contract time of 399 days and a contract price increase of $53,614.40 for additional HDPE footage needed to clear the existing underground structure that was unknown; and, WHEREAS, Arceneaux Wilson & Cole LLC, has requested and recommended Change Order No. 8 increasing the time by four (4) days for a new contract time of 399 days with a new completion date of February 22, 2015, and increasing the contract price to $3,446,001.40; this change order has been evaluated by Arceneaux Wilson & Cole LLC, and the Utility Operations Department (attached hereto as Exhibit"A"). P. R. No. 18783 12/16/14jj Page 3 of 4 NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF PORT ARTHUR: THAT, the City Manager of the City of Port Arthur is hereby authorized and directed to execute, on behalf of the City of Port Arthur, Change Order No. 8 between the City of Port Arthur and Allco L.L.C., for the increased time extension of four (4) days for a new contract time of 399 days, with a new completion date of February 22, 2015, and increasing the contract price by $53,614.40 to a new contract price of$3,446,001.40, attached hereto as Exhibit "A"; and, THAT a copy of the caption of this resolution be spread upon the minutes of the City Council. READ, ADOPTED AND APPROVED THIS day of , 2014 at a Regular Meeting of the City Council of the City of Port Arthur, Texas, by the following vote: AYES: Mayor Councilmembers: NOES: Deloris Prince Mayor P. R. No. 18783 12/16/14jj Page 4 of 4 ATTEST: APPROVED AS TO FORM: \raj, Sherri Bellard Valecia Tizeno City Secretary City Attorney APPROVED FOR ADMINISTRATION: �l John A. Comeaux,PE Shawna Tubbs, CPPB Interim City Manager Purchasing Manager J. e Johnson, PhD. Director of Utilities APPROVED AS TO AVAILABILITY OF FUNDS: Deborah Echols Director of Finance Account No.: 429-1258-532.59-00 Project No.: WSI003 Exhibit "A" (AW&C Change Order No.8) /I ARCENEAUX WILSON & COLE LLC Arceneaux Wilson b Cole- AWCEngineering • Surveying • Planning December 11, 2014 Mr. Jimmie Johnson Director of Water Utilities City of Port Arthur 444 Fourth Street Port Arthur, Texas 77640 RE: PROPOSAL FOR CHANGE ORDER NO. 8 24"WATERLINE FROM 19TH STREET TO THE SABINE-NECHES CANAL Job No CPA-650 Dear Mr. Johnson: Attached is Change Order No. 8 for the 24" Waterline from 19th Street to the Sabine-Neches Canal. This change order is for additional HDPE footage is needed to clear existing underground structure that was unknown. Also, included in this change order is a time extension of 4 days due to weather delays. The total cost for this change order will increase the contract amount $53,614.40. I recommend that the City of Port Arthur authorize this change to the contract. I have attached Change Order No. 8 which modifies the contract to reflect this change for your consideration and action. Should you have any questiois or require additional information, please contact our office. Very truly yours, Arceneaux Wilson & Cole LLC TEXAS REGISTERED ENGINEERING FIRM F-16194 Keestan Cole, PE Vice-President (409) 724-7888 • 2901 Turtle Creek Drive • Suite 320 • Port Arthur, Texas 77642 www.awceng.com Arcen cau: Wilson 8 Cole--- ...__.. AWC CHANGE ORDER No. 8 DATE: December 11, 2014 JOB NO. CPA-650 AGREEMENT DATE: November 5, 2013 NAME OF PROJECT: 24" Waterline from 19th Street to the Sabine-Neches Cana OWNER: CITY of PORT ARTHUR CONTRACTOR: ALLCO The following changes are hereby made to the CONTRACT DOCUMENTS: 1. Add the following Items to the Contract and Scope of Work: a. Increase 112 L.F., 30-Inch, DR-11 HDPE (Bid Item No. 3/$435.00 L.F.) [-] $ 48,720.00 b. Increase in Cost of 30-Inch, DR-11 HDPE ($43.70 L.F.) [+] $ 4,894.40 c. Extend contract time by 4 days TOTAL $ 53,614.40 CHANGE ORDER NO. 8 December 11, 2014 AWCJob No. CPA-650, Contract No. 1 CHANGE TO CONTRACT PRICE: ORIGINAL CONTRACT PRICE: $3,114,960.00 CURRENT CONTRACT PRICE adjusted by previous CHANGE ORDER(S): $3,392,387.00 The CONTRACT PRICE due to this CHANGE ORDER will be [increased] [decreased] by: $ 53,614.40 Dollars The new CONTRACT PRICE, including this CHANGE ORDER, will be $ 3,446,001.40 CHANGE TO CONTRACT TIME: ORIGINAL CONTRACT TIME: 365 Calendar Days CURRENT CONTRACT TIME adjusted by previous CHANGE ORDER: 30 Calendar Days CURRENT DATE OF COMPLETION: February 18, 2015 CONTRACT TIME due to this CHANGE ORDER will be increased by 4 Days The New DATE OF COMPLETION: February 22, 2015 No other Terms and Conditions of the Contract are changed as a result of this Change Order. Contractor's acceptance of Change Order relieves OWNER of any liability for additional costs incurred by Contractor in his performance of the work covered by the Change Order. RECOMMENDED BY ENGINEER: ACCEPTED BY: ARCENEAUX WILSON & COLE LLC [CONTRACTOR,OFFICER OR OWNE' ALLCO ACCEPTED BY: CITY of PORT ARTHUR 2 of 2 REQUEST FOR EXTENSION OF TIME DUE TO WEATHER OR SUPPLIES CITY OF PORT ARTHUR DA'T'E: ���. 3 ,20 / " MONTH OF: Akilec t , 20 17 CITY of PORT ARTHUR,'TEXAS WATER UTILITIES DEPARTMENT P.O. BOX 1089 CITY of PORT ARTHUR,TEXAS 77641-1089 ATTENTION: John Tomplait Interim Utilities Director Gentlemen: We request extension of completion time on our Contract due to the days of work lost as specified(list dates actually lost: do not include days not normally worked such as Saturdays, Sundays, or holidays): Dates Lost: it G , /1/13� /1/7 Days Lost( 3 )15 x 7+ 174 Calendar Days Requested Reasons for Request: Contractor /44Lt-D By: t6-! Approved for extension of calendar days. Disapproved. Date: , 20 CITY OF CITY OF PORT ARTHUR,TEXAS BY: City Manager Distribution by City Original: Water Utilities Department xc: Engineer Contractor CPA Federally Funded