I recommend that the City Council approve Proposed Resolution No. 18805 that would
authorize the Interim City Manager to execute Change Order No. 2 to the contract with
ALLCO, Inc., for construction of street paving improvements along 19th Street between
Stillwell Boulevard and Bluebonnet Avenue, decreasing the amount of the contract by
$58,517.50.
BACKGROUND
By Resolution 14-334 dated August 5, 2014, the City Council awarded a contract to
ALLCO, Inc., of Beaumont, Texas, in the amount of $636,731.00, for the construction of
street paving improvements along 19th Street between Stillwell Boulevard and
Bluebonnet Avenue. The contract included the use of EMC Stabilization material for use
in stabilizing the subgrade. When the EMC material was applied to the first area, there
was an adverse reaction to the base material, resulting in the need to use cement
stabilization instead. The geotechnical engineer recommends eliminating the EMC
material and utilizing the existing base material for subgrade stabilization for the
remainder of the project. Change Order No. 2 is a decrease of $58,517.50 in the
contract amount which addresses approximately 1,788 SY of cement stabilization and
the elimination of the EMC Stabilization material that was bid in the project. The new
contract amount as a result of the decreased amount of $58,517.50 is $663,513.06.
BUDGET/FISCAL EFFECT
There is currently funding set up in the GLO Round 2.2 Program Account No. 145-1201-
532.59-00 for the existing contract amount. Any savings to the Round 2.2 Program
funds will be applied to other Round 2.2 projects as needed as we proceed through the
bidding and award on the remaining projects.
SUMMARY
I recommend that the City Council approve Proposed Resolution No. 18805 that would
authorize the City Manager to execute Change Order No. 2 to the construction contract
with ALLCO, Inc., decreasing the contract amount by $58,517.50.
P.R. No. 18805
12/30/14 sjp
RESOLUTION NO.
A RESOLUTION AUTHORIZING THE CITY MANAGER TO
EXECUTE CHANGE ORDER NO. 2 TO THE CONTRACT
BETWEEN THE CITY OF PORT ARTHUR AND ALLCO INC.,
OF BEAUMONT, TEXAS, AND GLO, FOR THE 19TH STREET
PAVING IMPROVEMENTS, DECREASING THE CONTRACT
AMOUNT BY $58,517.50 TO A NEW CONTRACT AMOUNT OF
$663,513.06. PROJECT NO. I2119, GLO ROUND 2.2 ACCOUNT
NO. 145-1201-532.59-00.
WHEREAS, on August 5, 2015, per Resolution No. 14-334, the City Council
awarded a contract for the 19th Street Improvements to ALLCO, Inc., of Beaumont,
Texas, in the amount of $636,731.00 with a contract time of 270 days, said project
being from Stillwell Boulevard to Bluebonnet Avenue; and,
WHEREAS, on November 25, 2014, per Resolution No. 14-604, the City
Council approved Change Order No. 1 to the contract increasing the amount by
$85,299.56 and increasing the contract time by twenty(20) days; and
WHEREAS, during construction of the project, it was determined that
approximately 1,788 SY of cement stabilization was required where the proposed EMC
Stabilization material adversely reacted with the existing subgrade and the elimination
of EMC Stabilization material is proposed; and
WHEREAS, ALLCO, Inc., has submitted Change Order No. 2 for the project,
and the Public Works Director/City Engineer and the Project Engineer recommend
approval of Change Order No. 2 in the decreased amount of $58,517.50, attached as
Exhibit "A", to accomplish this work; NOW THEREFORE,
P.R. No. 18805
12/30/14 sjp
Page 2 of 3
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF PORT
ARTHUR:
THAT, the City Manager of the City of Port Arthur is hereby authorized and
directed to execute, on behalf of the City of Port Arthur, Change Order No. 2 (attached
as Exhibit "A") to the contract between the City of Port Arthur and ALLCO, Inc., for
the work described therein, decreasing the total contract amount by $58,517.50; and,
THAT, Change Order No. 2 decreases the contract amount to a new total of
$663,513.06; and,
THAT, Change Order No. 1 will be funded by the Project No. I2119, 145-1201-
532.59-00; and,
THAT, a copy of the caption of this resolution be spread upon the minutes of
the City Council.
READ, ADOPTED AND APPROVED THIS day of
2015 at a Regular Meeting of the City Council of the City of Port Arthur, Texas, by the
following vote:
AYES: Mayor
Councilmembers:
NOES:
Deloris Prince
Mayor
P.R. No. 18805
12/30/14 sjp
Page 3 of 3
ATTEST: APPROVED AS TO FORM:
Sherri Bellard Valecia Tizeno
City Secretary City Attorney
APPROVED FOR ADMINISTRATION:
John A. Comeaux, P.E. Shawna Tubbs, CPPB
Interim City Manager Purchasing Manager
tiCai P E.
Bfisan Polka, P.E.
Public Works Director/City Engineer
APPROVED AS TO AVAILABILITY OF FUNDS:
(Subject to a budget adjustment)
Deborah Echols
Director of Finance
Account No. 145-1201-532.59-00
Project No. I2119
EXHIBIT "A"
P.R. No. 18805
ARCENEAUX WILSON & COLE LLC
Arceneaux Wilson & Cole--- -
AWCEngineering • Surveying • Planning
December 24, 2014
Ms. Susan J. Polka, P.E.
Public Works Director
City of Port Arthur
444 Fourth Street
Port Arthur, Texas 77640
RE: CHANGE ORDER NO. 2
19th Street Improvements from Silwell Blvd. to Bluebonnet Ave,
Job No, CPA-835
Dear Ms. Polka:
Attached is Change Order No. 2 for the 19th Street Improvements project. This change order is
to cement stabilize approximately 1,788 SY of subgrade that experienced an adverse reaction
between the existing soil and the EMC Stabilization material that was bid in this project. Also, to
remove this item for the remaining areas of the project and utilize the existing base material for
subgrade stabilization as recommended by the geotechnical engineer. The total cost for this
change order will decrease the contract amount $58,517.50. I recommend that the City of Port
Arthur authorize this change to the contract. I have attached Change Order No. 2 which
modifies the contract to reflect this change for your consideration and action. Should you have
any questions or require additional information, please contact our office.
Very truly yours,
Arceneaux Wilson & Cole LLC
TEXAS REGISTERED ENGINEERING FIRM F-16194
Keestan Cole, PE
Vice-President
(409) 724-7888 • 2901 Turtle Creek Drive • Suite 320 • Port Arthur, Texas 77642
www.awceng.corn
Arce nc.ua Wilso r. a Cole �C'
AWC Planning
iurrvyin.F
CHANGE ORDER No. 2
DATE: December 24, 2014 JOB NO. CPA-835
AGREEMENT DATE: October 8, 2014
NAME OF PROJECT: 19`" Street Improvements from Stilwell Boulevard to
Bluebonnet Avenue
OWNER: CITY of PORT ARTHUR
CONTRACTOR: ALLCO
The following changes are hereby made to the CONTRACT DOCUMENTS:
1. Delete to Adjust the following Bid Items to actual quantities used:
a. Cement Stabilization from STA. 0+00 to 7+00
(1,788 SY) due to adverse reactions with the existing
soil and the EMC stabilization product.
($13.95/SY) $ $24,942.60
b. Remove 12,742 SY from Bid Item #7 Manipulation of
EMC Squared Stabilizer 200/EMS Dual Component
Treatment; 1 gallon of EMC Squared Stabilizer 2000
And 2 Gallons EMS per 405 S.F. of Pavement.
($4.60/SY) ($ 58,613.20)
c. Remove 12,742 SY from Bid Item #8 EMC Squared
Stabilizer 200/EMS Dual Component Treatment for
Subgrade Stabilization.
($1.95/SY) ($ 24,846.90)
SUBTOTAL ($ 58,517.50)
CHANGE ORDER NO. 2
Arcl neaux WllsOn b COIL--� ...
ADecember��C IC7I47Kt.7i.'V,� 24, 2014
`"�'"'""" Job No. CPA-835, Contract No. 1
CHANGE TO CONTRACT PRICE:
ORIGINAL CONTRACT PRICE: $636,731.00
CURRENT.CONTRACT PRICE adjusted by previous CHANGE ORDER(S): $722,030.56
The CONTRACT PRICE due to this CHANGE ORDER will be [increased] [decreased]
by: ($58,517.50) Dollars
The new CONTRACT PRICE, including this CHANGE ORDER, will be $ 663,513.06
CHANGE TO CONTRACT TIME:
ORIGINAL CONTRACT TIME: 270 Calendar Days
CURRENT CONTRACT TIME adjusted by previous CHANGE ORDER: 20 Calendar Days
CURRENT DATE OF COMPLETION: August 12, 2015
CONTRACT TIME due to this CHANGE ORDER will be increased by 0 Days
The New DATE OF COMPLETION: August 12, 2015
No other Terms and Conditions of the Contract are changed as a result of this Change Order.
Contractor's acceptance of Change Order relieves OWNER of any liability for additional costs
incurred by Contractor in his performance of the work covered by the Change Order.
RECOMMENDED BY ENGINEER: ACCEPTED BY:
ARCENEAUX WILSON & COLE LLC [CONTRACTOR,OFFICER OR OWNER]
ALLCO
ACCEPTED BY:
CITY of PORT ARTHUR
2 of 2
tic's AV..-
W it; �, Texas General Land Office
- Disaster Recovery PS T98LISHEO
Construction Contract Change Order Request Form
Engineer: Owner (Contractor Locality): Contractor:
ALLCO
Aceneaux&Gates Engineers, Inc., City of Port Arthur
A Burrow Global Company 4th 444 4 Street
2901 Turtle Creek Dr., Suite 320 Port Arthur, TX 77642 Agreement Date: 10-8-14
Port Arthur,TX 77642
Phone No.:409-983-8100 Phone No.: 409-860-4459
Phone No.: 409-724-7888
Date: December 1 2014 Contract For (Project Description): GLO Contract No.:
Project Code No.: P21430 12-403-008-7654
19th Street Improvements from
Bid Package No.: 5 Stilwell Blvd. to Bluebonnet Ave.
Change Order No.: 2
You are hereby requested to comply with the following changes from the contract plans and specifications:
Item Description of Changes: Quantities, Units, Unit Prices, Decrease in Increase in
No. Change in Completion Scheduled, Etc. Contract Price Contract Price
Cement Stabilization of subgrade from STA. 0+00 to
7+00 (1,788 SY) due to adverse reactions between $24,942.60
existing soil and the EMC Stabilization product
7 Remove 12,742 SY from Bid Item #7 Manipulation of $ 58,613.20
EMC Squared Stabilizer 200/EMS Dual Component
Treatment; 1 gallon of EMC Squared Stabilizer 2000
And 2 Gallons EMS per 405 S.F. of Pavement.
8 Remove 12,742 SY from Bid Item # 8 EMC Squared $ 24,846.90
Stabilizer 200/EMS Dual Component Treatment for
Subgrade Stabilization.
1
Construction Contract Change Order Request Form Page 1 of 3
CDBG Disaster Recovery Program July 2014
I
Change in Contract Price Change in Contract Time (Calendar Days)
Original Contract Price: $636,731.00 Original Contract Time: 270 days
Previous Change Order(s): Net Change From Previous
i No. 1 to No. 1 $ 85,299.56 Change Orders: 20 days
Contract Price Prior to Contract Time Prior to
this Change Order: $ 722,030.56 this Change Order: 290 days
Net 41-Grease/Decrease of Net Ise/Detee of
this Change Order: $ 58,517.50 this Change Order: 0 days
Contract Price With all Contract Time With all
Approved Change Orders: $663,513.06 Change Orders: 290 days
Cumulative Percent Change in Contract Price (+/-): Grantee Contract End Date:
4.2% (mm/dd/yy) 12 / 31 /2015
Construction Contract Start Date: Construction Contract End Date:
(mm/dd/yy) 10 / 27 /2014 (mm/dd/yy) 8/ 12 / 2015
Reimbursements of costs included in this change order are subject to review by the GLO-DR program.
* This document may be executed prior to submission for GLO-DR program review, but all parties
involved will be held responsible if the change order or the amendment warranted as a result of
this change order is not in compliance with CDBG or HUD requirements.
RECOMMEN'." 1: APPROVED: ACCEPTED:
By: - By: By: -ia
ENGINEER OWNER CONTRACTOR
Date: /2-.70/y Date: Date: 1a;30J l5/
Construction Contract Change Order Request Form Page 2 of 3
CDBG Disaster Recovery Program July 2014
__ J
I
JUSTIFICATION FOR CHANGE
1. Will this Change Order increase or decrease
the number of beneficiaries? ❑ Increase ❑ Decrease x No Change
If there is a change, how many beneficiaries will be affected? Total UM
2. Effect of this change on scope of work: ❑ Increase ❑ Decrease x No Change
3. Effect on operation and maintenance costs: ❑ Increase ❑ Decrease x No Change
4. Are all prices in the change order dependent upon unit prices
found in the original bid? x Yes ❑ No
If"No", explain:
5. Has this change created new circumstances or environmental
conditions which may affect the project's impact, such as
concealed or unexpected conditions discovered during actual
construction? ❑ Yes x No
If"Yes", is an Environmental Re-assessment required?
6. Is the Texas Commission on Environmental Quality (TCEQ)
clearance still valid?(if applicable) x Yes ❑ No
7. Is the TCEQ permit approval still valid? (sewer projects only) ❑ Yes ❑ No
8. Are the handicapped access requirements/approval
still valid? (if applicable) x Yes ❑ No
9. Are other Disaster Recovery contractual special condition clearance
still valid? x Yes ❑ No
(If no, specify):
NOTE:
* Generally, a cumulative change in the contract price in excess of 25% cannot