HomeMy WebLinkAboutPR 18839: CHANGE ORDERS NOS. 1 AND 2 CONTACT WITH APAC-TEXAS, INC., THE PLEASURE ISLAND MARINA PAVING P.R. No. 18839
1/28/15 jd/gt
RESOLUTION NO.
A RESOLUTION AUTHORIZING THE CITY MANAGER TO EXECUTE
CHANGE ORDER NOS. 1 AND 2 TO THE CONTRACT BETWEEN THE CITY
OF PORT ARTHUR AND APAC-TEXAS, INC., OF BEAUMONT, TEXAS, FOR
THE PLEASURE ISLAND MARINA PAVING REHABILITATION,
INCREASING THE CONTRACT AMOUNT BY $4,966.88, TO A NEW
TOTAL OF $410,255.88, AND THE TIME OF THE CONTRACT TERM BY
EIGHTEEN (18) CALENDAR DAYS, DUE TO WEATHER DELAYS, TO A
NEW TERM OF 138 DAYS. FUNDS AVAILABLE IN PLEASURE ISLAND
ACCOUNT NO. 450-1293-549.89-00.
WHEREAS, per Resolution No. 14-405, the City Council awarded a contract for the
Pleasure Island Marina paving rehabilitation project to APAC-Texas, Inc., of Beaumont, Texas;
and,
WHEREAS, APAC-Texas, Inc. has requested Change Order No. 1 increasing the
contract amount by $4,966.88 for additional work items, not included in the original contract,
as follows: 1) Install Gate Control Loop (Area #1 — Item 130); 2) Removal of broken concrete
at driveway entrance (Area #7 — Item 140); 3) Removal of concrete pad (old boat ramp) (Area
#7 — Item 150); 4) ADA (Truncated Domed Panels) (Areas #3, 4 & 7 — Item 170); and 5)
Water Valve Boxes (Round Metal) (Areas #3, 4 & 7 — Item 180), see attached Exhibit "A";
and,
WHEREAS, APAC-Texas, Inc., has also requested Change Order No. 2 for a time
extension of eighteen (18) calendars days due to weather delays, see attached Exhibit "B";
and,
s.pr18839
P.R. No. 18839
1/28/15 jd/gt
Page 2 of 3
WHEREAS, the project engineer, Soutex Surveyors & Engineers, has examined the
requests and recommends proposed Change Order Nos. 1 and 2, attached as Exhibits "A" and
"B", respectively.
NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF
PORT ARTHUR:
THAT, the City Manager of the City of Port Arthur is hereby authorized and directed to
execute, on behalf of the City of Port Arthur, Change Order No. 1, attached as Exhibit "A",
increasing the contract amount by $4,966.88 for additional work not included in the original
contract, to a new total of $410,255.88.
THAT, the City Manager of the City of Port Arthur is hereby authorized and directed to
execute, on behalf of the City of Port Arthur, Change Order No. 2, attached as Exhibit "B", to
the contract between the City of Port Arthur and APAC-Texas, Inc., for the extension of said
contract by eighteen (18) calendar days due to weather delays, to a new term of 138 days,
with the new ending date of the contract being March 13, 2015, at no additional cost.
THAT, a copy of the caption of this resolution be spread upon the minutes of the City
Council.
READ, ADOPTED AND APPROVED THIS day of February, A.D., 2015, at a
Regular Meeting of the City Council of the City of Port Arthur, Texas, by the following vote:
AYES:
s.pr18839
P.R. No. 18839
1/28/15 jd/gt
Page 3 of 3
Mayor:
Councilmembers:
NOES:
Deloris Prince
Mayor
ATTEST: APPROVED AS TO FORM:
Sherri Bellard alecia Tize
City Secretary City Attorne
APPROVED FOR ADMINISTRATION:
%� A
Brian McDougal Shawna Tubbs, CPPO, CPPB
City Manager Purchasing Manager
m' Dike
Director of Pleasure Island
APPROVED AS TO AVAILABILITY OF FUNDS:
Idatet
Deborah Echols, CPA / 0 `
Director of Finance
s.pr18839
Exhibit "A"
s.pr18839
•
S°UTEX TBPE Firm No. 5755
TBPLS Firm No.10123800
3737 Doctors Drive
G A , x ', Port Arthur,TX 77642
(409) 983.2004
SURVEYORS&ENGINEERS Office Fax (409) 983.2005
January 28, 2015
Mr. Jimmy Dike
Pleasure Island
City of Port Arthur
520 Pleasure Pier Blvd
Port Arthur,Texas 77640
Re: Change Order No. 1—Additional Work
Pleasure Island Marina Paving Rehabilitation Project
(APAC Change Order No. 1) Soutex Project No. 13-0209
Mr. Dike,
Transmitted herewith is Change Order No. 1 for the above referenced project. We have
reviewed the proposal for additional work items submitted by APAC-Texas, Inc. and found
them to be reasonable for an amount of$4,966.88. We have attached their proposal and a
complete description of the additional work. Please contact us if you have any questions
concerning this change order.
Respectfully Submitted,
-��/r f
Sta I G. Newsom-,Jr. P.E.
Attachments
Cc: Shawna Tubbs— Purchasing Manager
Legal Department
Change Order No. 1
This Change Order is for work to be performed on Pleasure Island Paving Project for approval as listed
below. Item numbers are listed on APAC-Texas, Inc.'s Proposal.
1. Area#1 (Item 130) --Install Gate Control Loop (4'x8' Preformed).The Existing Loop Control
was inserted and sealed with silicone in the small saw cut of the existing asphalt.The dark
discoloration of the silicone sealant was the primary reason why the loop was not found nor
included in the original design bid items. The Loop was found prior to removal of driveway.
2. Area#7 (Item 140)--Removal of broken Concrete at driveway entrance. The existing broken
concrete was to the southwest of the existing gate entrance of Area #7. It was covered with
soil and grass and this was the primary reason why the existing broken concrete was not
located nor included in the original design bid items. The broken concrete was discovered
when grading the new gate location.
3. Area#7 (Item 150) --Removal of Concrete Pad (Old Boat Ramp Pad). The existing concrete
pad was near the northeast quadrant of Area #7. The concrete pad was covered with soil and
grass and this was the primary reason why the existing concrete pad was not discovered prior
to construction nor included in the original design bid items for removal. The concrete pad was
discovered when grading the subgrade area in that location.
4. Areas#3,4&7 (Item 170)--ADA(Truncated Domed Panels). In the original plans of the City
Sidewalk and Driveway Detail Sheet did not specify which option is preferred (Grooves or
Truncated Dome)for this project. The city expressed the desired preference of Truncated
Dome.
5. Areas#3,4&7 (Item 180)—Water Valve Boxes(Round Metal). On the project there exist
square concrete water meter boxes over the existing water valves to the fire hydrants. These
boxes and valves were covered beneath the grass and the existence of these valves and boxes
were discovered during the removal of the soil top layer and grass during the process of
grading for constructing the ADA sidewalks. The primary reason is due to the existing
damaged and/or missing boxes that are in need of replacement. The valves are located in the
paths of the proposed ADA sidewalks in these areas.
Estimate#
bi'M
Safety First Always P R 0 P O SA L 5358CO#2
APAC-Texas, Inc. January 23, 2015
PO Box 20779
Beaumont, Texas, 77720
(0) 409-866-1444
(F) 409-866-1032
QUOTE Stanley Newsome
TO Soutex
JOB` WORKING DAPS DIANHOURS
Port Arthur Pleasure Island Additional Work I 5
M T,EM DESCRIPTION -, s �UNIIT CE .- :
130 Install Gate Control Loop 1.00 : EA $ 397.50 ` $ 397.50
140 Concrete Removal at Area 7
Driveway 1 1.00 LS $ 1,200.00 $ 1,200 00
150 Concrete Pad Removal at Area ,
7i 1.00 LS $ 1,600.00 $ 1,600.00
170 ADA Truncated Dome Panels I 1.00 LS $ 1,569 38 $ 1,569.38
180 Additional Type A Meter Boxes 1.00 ti LS
' $ 200.00 $ 200.00
( E
EI TOTAL I $ 4,966.88
i e i
I
THIS PROPOSAL DOES NOT INCLUDE ANY TAXES
Page 1 of 4
Exhibit "B"
s.pr18839
TBE Firm No.5755
` TBPLS Firm No.10123800
3737 Doctors Drive
, Port Arthur,TX 77642
SURVEYORS&ENGINEERS Office Fax (409) 983 2005
January 28, 2015
Mr. Jimmy Dike
Pleasure Island
City of Port Arthur
520 Pleasure Pier Blvd
Port Arthur, Texas 77640
Re: Change Order No. 2—Time Extension
Pleasure Island Marina Paving Rehabilitation Project
(APAC Change Order No. 2) Soutex Project No. 13-0209
Mr. Dike,
Transmitted herewith is Change Order No. 2 for the above referenced project. We are
requesting an extension for the completion of the project as our Contract due date is
approaching. As noted in the attached document, we are requesting an additional 18
calendar days to be added to their Contract, bringing the completion date to March 13, 2015.
These lost days are due to inclement weather. This Change Order does not increase the cost
of the contract. If you have any questions concerning this request, please call.
Respectfully/Submitted,
11%Sta . ewso e,Jr. P.E. f
Attachment
Cc: Shawna Tubbs— Purchasing Manager
Legal Department
REQUEST FOR EXTENSION OF TIME DUE TO WEATHER OR SUPPLIES
CITY OF PORT ARTHUR
PLEASURE ISLAND MARINA
PAVING REHABILITATION
CITY OF PORT ARTHUR, TEXAS
DATE: January 28, 2015
MONTHS OF: Nov. 2014 -Jan. 28, 2015
CITY of PORT ARTHUR, TEXAS
PLEASURE ISLAND
P.O. BOX 1089
CITY of PORT ARTHUR, TEXAS 77641-1089
ATTENTION: Jimmy Dike
Director
Gentlemen:
We request extension of completion time on our Contract due to the days of work lost as
specified(list dates actually lost: do not include days not normally worked such as Saturdays,
Sundays, or holidays):
Dates Lost: Nov. 6, 7, 13, 17, Dec. 19,22 &23, 2014 and Jan. 2, 9, 12, 15, 22 & 23, 2015.
Days Lost( 13 )/ 5 x 7= 18 Calendar Days Requested
Reasons for Request: Wet Weather
Contractor APAC -Texas, Inc. `
By: Soutex Surveyors& Engineers - l4��nL tit
Approved for extension of calendar days.
Disapproved.
Date: , 20CITY OF CITY OF PORT ARTHUR, TEXAS
BY:
City Manager
Distribution by City
Original: Water Utilities Department
xc: Engineer
Contractor
CPA Non Federally Funded
APP-1
CPA Federally Funded