HomeMy WebLinkAboutPR 18827: CHANGE ORDER NO. 7 ALLCO, L.L.C., HWY 87 WATER SYSTEM IMPROVEMENTS FROM KEITH LAKE TO SABINE PASS STANDPIPE MEMORANDUM
CITY OF PORT ARTHUR
Utility Operations Department
TO: Brian McDougal, City Manager
FROM: Jimmie Johnson, PhD., Director of Utility Operations dr:. .
DATE: March 17, 2015
RE: Proposed Resolution No. 18827
RECOMMENDATION
I recommend that the City Council approve Proposed Resolution No. 18827 authorizing
the City Manager to execute Change Order No. 7 to the contract with ALLCO, L.L.C., of
Beaumont, Texas, for construction of the Highway 87 Water Transmission Line project
from Keith Lake to the Sabine Pass Standpipe. This Change Order is for a time
extension of twenty-four (24) days due to weather delays during the months of
December, January and February.
BACKGROUND
On October 29, 2013, City Council approved the award of a contract in the amount of
$3,373,385.00 to ALLCO, L.L.C. for the construction of the Highway 87 Water
Transmission Line from the cut at Keith Lake to the new standpipe in Sabine Pass.
BUDGET/FISCAL EFFECT
Pursuant to Resolution No. 12-597, funding for this project is through City Account No.
429-1258-532.59-00, Project No. WSI002; the recommendation does not effect account.
SUMMARY
I recommend that the City Council approve Proposed Resolution No. 18827 authorizing
the City Manager to execute Change Order No. 7 for a time extension of 24 days due to
weather delays during the months of December, January and February, to the Highway
87 Water Transmission project contract with ALLCO, L.L.C, to a new contract time of
329 days.
P.R. No. 18827
03/17/15 j j
RESOLUTION NO.
A RESOLUTION AUTHORIZING THE CITY MANAGER
TO EXECUTE CHANGE ORDER NO. 7 TO THE
CONTRACT BETWEEN THE CITY OF PORT ARTHUR
AND ALLCO, L.L.C., OF BEAUMONT, TEXAS, FOR THE
HIGHWAY 87 WATER SYSTEM IMPROVEMENTS
FROM KEITH LAKE TO SABINE PASS STANDPIPE,
FOR TIME EXTENSION OF 24 DAYS, DUE TO
WEATHER DELAYS, TO A NEW CONTRACT TERM OF
329 DAYS.
WHEREAS, per Resolution No. 13-492 dated October 29, 2013, the City Council
awarded a contract for the construction of the Highway 87 Water Transmission Line for Keith
Lake to the Sabine Pass Standpipe to ALLCO, L.L.C., in the amount of$3,373,385.00; and,
WHEREAS, per Resolution No. 14-224, Change Order No. 1 authorized the increase in
pipe material costs from October 29, 2013, and the increased cost to purchase the pipe material
for the project in the amount of$144,462.89 to a new contract total of$3,517,847.89; and,
WHEREAS, per Resolution No. 14-388, Change Order No. 2 authorized a time extension
of 4 days due to weather delays to a new contract time of 274 days; and,
WHEREAS, per Resolution No. 14-450, Change Order No. 3 authorized a time
extension of six (6) days due to weather delays to a new contract time of 280 days; and
WHEREAS, per Resolution No. 14-555, Change Order No. 4 authorized a time extension
of seven(7) days due to weather delays to a new contract time of 287 days; and,
WHEREAS, per Resolution No. 14-608, Change Order No. 5 authorized a time
extension of seven(7) days due to weather delays to a new contract time of 294 days; and,
WHEREAS, per Resolution No. 14-644, Change Order No. 6 authorized a time
extension of eleven(11) days due to weather delays to a new contract time of and 305 days and a
P.R. No. 18827
3/17/15 jj
Page 2 of 3
contract price increase of$79,675.00 due to the extension of three directional drills due to soil
conditions in the working area.
WHEREAS, the project engineer, Arceneaux Wilson & Cole LLC, recommends
proposed Change Order No. 7 for a time extension of twenty-four (24) days, attached as Exhibit
"A",to accomplish this work.
NOW THEREFORE,BE IT RESOLVED BY THE CITY COUNCIL OF THE
CITY OF PORT ARTHUR:
THAT, the City Manager of the City of Port Arthur is hereby authorized and directed to
execute, on behalf of the City of Port Arthur, Change Order No. 7 (attached as Exhibit "A") to
the contract between the City of Port Arthur and ALLCO, L.L.C. of Beaumont, Texas, increasing
the total contract time by twenty-four(24) days due to weather delays; and,
THAT, Change Order No. 7 increases the contract time to 329 days with a new
completion date of April 26, 2015; and,
THAT, Change Order No. 7 will require no additional funding by the Project No.
WSI002, City Account No. 429-1258-532.59-00; and,
THAT, a copy of the caption of this resolution be spread upon the minutes of the City
Council.
READ, ADOPTED AND APPROVED THIS day of , 2015 at a
Regular Meeting of the City Council of the City of Port Arthur, Texas, by the following vote:
AYES: Mayor:
Councilmembers:
P.R. No. 18827
3-17-15
Page 3 of 3
NOES:
Deloris Prince
Mayor
ATTEST: APPROVED AS TO FORM:
2
Sherri Bellard Valecia Tizen
City Secretary City Attorney
APPROVED FOR ADMINISTRATION:
51rl tw�!Z/ L �__L -LCL/
Brian McDougal Shawna Tubbs, CPPO, CPPB
City Manager Purchasing Manager
Jimmie Johnson, Ph.D.
Director of Utility Operations
Exhibit "A"
(AW&C Change Order No. 7)
AWC Engineering
Surveying
Planning Arceneaux Wilson & Cole LLC
Consulting Engineers
2901 Turtle Creek Drive, Suite #320 Port Arthur, TX 77642
Phone: 409-724-7888 Fax: 409-724-1447
www.awceng.com
LETTER OF TRANSMITTAL
DATE: March 9, 2015 PROJECT NO.: CPA-705
TO: City of Port Arthur ATTENTION: Mr. Jimmie Johnson
444 4th Street
Port Arthur, TX 77640 RE: SH. 87 Water Improvements from Keith
Lake to Sabine Pass Standpipe
WE ARE SENDING YOU ❑ Attached ❑ Under Separate Cover Via: Hand Delivery The following items:
❑ Memo ❑ Monthly Invoice ❑ Plans ❑ Construction Documents
❑ Letter ❑✓ Change Order No._Z_ ❑ Form ❑ Other
COPIES DATE DESCRIPTION
4 3-9-14 Change Order No. 7
THESE ARE TRANSMITTED as checked below:
Z✓ For approval ❑ Approved as submitted ❑ Resubmit copies for approval
❑ For your use ❑ Approved as noted ❑ Submit copies for distribution
❑ As requested ❑ Returned for corrections ❑Submit corrected prints
❑ For review and comment Execute and return original
RECEIVED
RECEIVED BY:
MAR 1 0 2015
COMMENTS:
UTILITY OPERATIONS
Admin.-City Hall
COPY TO: SIGNED: Stephanie Morrell
REQUEST FOR EXTENSION OF TIME DUE TO WEATHER OR SUPPLIES
CITY OF PORT ARTHUR
DATE: 3 -3 ,20 i`C
MONTH OF: A:/SY24).471-47 ,20 a-
CITY of PORT ARTHUR,TEXAS
PUBLIC WORKS DEPARTMENT
P.O.BOX 1089
CITY of PORT ARTHUR, l'EXAS 77641-1089
ATTENTION: Ross Blackketter,P.E.,
Public Works Director
Gentlemen:
We request extension of completion time on our Contract due to the days of work lost as
specified(list dates actually lost: do not include days not normally worked such as Saturdays,
Sundays, or holidays):
Dates Lost: / 1 Z ((. Z 17 Z/L$ 2--(234 2/74.-
Days Lost( L )/ 5 x 7+ Calendar Days Requested
Reasons for Request:
LJ cfA1 1/Z 741/
Contractor /1/..4..-40
By47.5-/il."
l ciAgerc _
Approved for extension of calendar days.
Disapproved.
Date: , 20 CITY OF CITY OF PORT ARTHUR,
TEXAS
BY:
City Manager
Distribution by City
Original: Public Works Department
xc: Engineer
Contractor
CPA Federally Funded
REQUEST FOR EX IIiNSION OF TIME DUE TO WEATHER OR SUPPLIES
CITY OF PORT ARTHUR
DATE: 2 �J' , 20 /5-
MONTH OF: J , 20 1 S.--
CITY of PORT ARTHUR,TEXA
PUBLIC WORKS DEPARTMENT
P.O. BOX 1089
CITY of PORT ARTHUR, 1'hXAS 77641-1089
AFIENTION: Ross Blackketter,P.E.,
Public Works Director
Gentlemen:
We request extension of completion time on our Contract due to the days of work lost as
specified(list dates actually lost: do not include days not normally worked such as Saturdays,
Sundays, or holidays):
Dates Lost: ( /y i /^ ' Z Z3
r` i ( � 1/13 1 /2-2— r
Days Lost( )/ 5 x 7+ O Calendar Days Requested
Reasons for Request: , 1 G/ ,2
Contractor
By: 41114- 1, v t24.1. lr�
Approved for extension of calendar days.
Disapproved.
Date: , 20 CITY OF CITY OF PORT ARTHUR,
TEXAS
BY:
City Manager
Distribution by City
Original: Public Works Department
xc: Engineer
Contractor
CPA Federally Funded
Ce
REQUEST FOR EXTENSION OF TIME DUE TO WEATHER OR SUPPLIES
CITY OF PORT ARTHUR
DATE: 13 ,20 1 Jr
MONTH OF: rbELg- R_ , 20 14
CITY of PORT ARTHUR, TEXAS
PUBLIC WORKS DEPARTMENT
P.O. BOX 1089
CITY of PORT ARTHUR, l'EXAS 77641-1089
ATTENTION: Ross Blackketter,P.E.,
Public Works Director
Gentlemen:
We request extension of completion time on our Contract due to the days of work lost as
specified(list dates actually lost: do not include days not normally worked such as Saturdays,
Sundays,or holidays):
Dates Lost: 2-11i
! 11 1 1 L(Z�- � ( 2413) l �-f Uo 1 t 1-12-1 I
Days Lost( )/ 5 x 7 + § Calendar Days Requested
Reasons for Request:
Contractor Az-C.,
By: 6/T, �v/2/ZcLC_
Approved for extension of calendar days.
Disapproved.
Date: , 20 CITY OF CITY OF PORT ARTHUR,
TEXAS
BY:
City Manager
Distribution by City
Original: Public Works Department
xc: Engineer
Contractor
CPA Federally Funded
ARCENEAUX WILSON & COLE LLC
Arcencaux Wilson & Cole---
AWCEngineering • Surveying • Planning
March 5, 2015
Dr. Jimmie Johnson
Director of Water Utilities
City of Port Arthur
444 Fourth Street
Port Arthur, Texas 77640
RE: PROPOSAL FOR CHANGE ORDER NO 7
STATE HIGHWAY 87 WATER SYSTEM IMPROVEMENTS FROM KEITH
LAKE TO SABINE PASS STANDPIPE
Job No. CPA-705
Dear Dr. Johnson:
Attached is Change Order No. 7 for the State Highway 87 Water System Improvements from
Keith Lake to Sabine Pass Standpipe. This change order is for time extension of 24 days due to
weather delays during the months of December, January and February. I recommend that the
City of Port Arthur authorize this change to the contract. I have attached Change Order No. 7
which modifies the contract to reflect this change for your consideration and action. Should you
have any questions or require additional information, please contact our office.
Very truly yours,
ARCENEAUX WILSON& COLE LLC
TEXAS REGISTERED ENGINEERING FIRM F-16194
'Keestan Cole, PE
Vice President
2901 Turtle Creek Dr.,Suite 320 Port Arthur, TX 77642 Phone: 409/724-7888 Fax: 409/724-1447
tonneaus Wilson F Cole
AWC 1:""'"
CHANGE ORDER No. 7
DATE: February 24, 2015 JOB NO. CPA-705
AGREEMENT DATE: November 5, 2013
NAME OF PROJECT: State Highway 87 Water System Improvements
OWNER: CITY of PORT ARTHUR
CONTRACTOR: ALLCO
The following changes are hereby made to the CONTRACT DOCUMENTS:
1. Add the following Items to the Contract and Scope of Work:
a. Extend contract time by 24 days
CHANGE ORDER NO. 7
February 24, 2015
Arceneauxon ede.Q- ---. Job No. CPA-705
AWC
CHANGE TO CONTRACT PRICE:
ORIGINAL CONTRACT PRICE: $3,373,385.00
CURRENT CONTRACT PRICE adjusted by previous CHANGE ORDER(S): $ 3,597,522.89
The CONTRACT PRICE due to this CHANGE ORDER will be [increased] [decreased]
by: $0.00 Dollars
The new CONTRACT PRICE, including this CHANGE ORDER, will be $3,597,522.89
CHANGE TO CONTRACT TIME:
ORIGINAL CONTRACT TIME: 270 Calendar Days
CURRENT CONTRACT TIME adjusted by previous CHANGE ORDER: 35 Calendar Days
CURRENT DATE OF COMPLETION: April 2,2015
CONTRACT TIME due to this CHANGE ORDER will be increased by 24 Days
The New DATE OF COMPLETION: April 26,2015
No other Terms and Conditions of the Contract are changed as a result of this Change Order.
Contractor's acceptance of Change Order relieves OWNER of any liability for additional costs
incurred by Contractor in his performance of the work covered by the Change Order.
RECOMMENDED BY ENGINEER: ACCEPTED BY:
ARCENEAUX WILSON & COLE LLC [ ONTRACTOR,OFFICER OROW' R]
ALLCO
ACCEPTED BY:
CITY of PORT ARTHUR
2 of 2