HomeMy WebLinkAboutPR 18908: TEMPORARY CONTRACT DELAY FOR ALLCO, L.L.C. FOR WORK BEING PERFORMED 24" WATERLINE MEMORANDUM
CITY OF PORT ARTHUR
UTILITY OPERATIONS DEPARTMENT
TO: Brian McDougal, City Manager
FROM: Jimmie Johnson, Director of Utility Operations61)
DATE: March 17, 2015
RE: Proposed Resolution No. 18908
RECOMMENDATION
I recommend that the City Council approve Proposed Resolution No. 18908 authorizing
a temporary contract delay for the 24" Waterline from 19th Street to the Sabine Neches
Canal Project with ALLCO, L.L.C., of Beaumont, Texas. The request is necessary as
another contractor has started working on a City of Port Arthur project, which does not
allow ALLCO, L.L.C. to finish this contract. The work will resume once contractor
completes assignment.
BACKGROUND
This project will extend a 24" water transmission main from the old Water Purification
Plant to W. 7th Street and SH 82.
BUDGET/FISCAL EFFECT
None.
SUMMARY
I recommend that the City Council approve Proposed Resolution No.18908, authorizing
the City Manager to enforce a temporary contract delay for the 24" Waterline from 19t
Street to the Sabine Neches Canal Project with ALLCO, L.L.C., of Beaumont, Texas, as
a result of another contractor working on a City of Port Arthur project, which does not
allow ALLCO, L.L.C. to finish this contract.
P. R. No. 18908
03/17/15 jj
RESOLUTION NO.
A RESOLUTION AUTHORIZING THE CITY MANAGER
TO EXECUTE A TEMPORARY CONTRACT DELAY
FOR ALLCO, L.L.C., FOR WORK BEING PERFORMED
ON THE CITY OF PORT ARTHUR 24" WATERLINE
FROM 19TH STREET TO THE SABINE NECHES CANAL
PROJECT, AS ANOTHER CONTRACTOR IS WORKING
ON A CITY OF PORT ARTHUR PROJECT, WHICH
DOES NOT ALLOW ALLCO, L.L.C. TO FINISH THIS
PROJECT (TO RESUME ONCE OTHER CONTRACTOR
COMPLETES ASSIGNMENT)
WHEREAS, per Resolution No. 13-5037 the City entered into a contract for the
installation of a Waterline from 19th Street to the Sabine Neches Canal, in the amount of
$3,114,960.00, with a contract term of 365 calendar days; and
WHEREAS, per Resolution No. 14-210, Change Order 1 authorized an additional
$40,486.00 to add storm water pollution prevention measures required by the City of Port Arthur
that was not included in the original contract, bringing the contract price for the project to
$3,155,446.00 accepted by Allco; and
WHEREAS, per Resolution No. 14-300, Change Order 2 authorized a credit of
$21,980.00 for the use of 24" Certa-Loc restrained joint C900 PVC pipe in lieu of the 24"
cement lined restrained joint gasket ductile iron pipe in the original bid to a new contract total of
$3,133,466, and a time extension of six (6) days due to inclement weather bring the date of
completion to January 25, 2015; and
WHEREAS, per Resolution No. 14-342, Change Order 3 authorized an additional
$12,072.00 for the relocation of an existing 6" waterline that was discovered during construction
on Charleston Ave, the re-route of the 24" waterline to miss an existing storm sewer, and one
foot of extra cover added to the 24" waterline approx. 2,100 L.F. to ensure protection of the line
during the 18th Street construction project to a new contract total of$3,145,538.00, and a time
P. R. No. 18908
03/17/15jj
Page 2 of 4
extension of six (6) days due to inclement weather, bringing the date of completion to January
31, 2015; and,
WHEREAS, per Resolution No. 14-389, Change Order 4, authorized a time extension
of 3 days due to weather delays, to a new completion date of February 3, 2015; and,
WHEREAS, per Resolution No. 14-449, Change Order 5, authorized the relocation of
the proposed 24" waterline to avoid an existing structure at the intersection of 18th Street and
Railroad Ave. in the amount not to exceed $53,100.00 to a new contract total of$3,198,638.00
and a time extension of three (3)days due to inclement weather bring the date of completion to
February 6, 2015; and,
WHEREAS, per Resolution No. 14-554, Change Order 6, authorized the relocation of
an existing 12" waterline at Railroad Ave. in the amount not to exceed$52,659.00, and a time
extension of eight(8) days due to inclement weather; and,
WHEREAS, per Resolution No. 14-607, Change Order 7, authorized the performing a
20-inch hot tap on an existing 20-inch waterline on Atlanta Street and an additional 250 feet of
30-inch, DR-11 HDPE of directional drilling in an amount not to exceed $141,090.00, and a time
extension of four(4) days due to inclement weather; and,
WHEREAS, per Resolution No. 14-645, Change Order 8, authorized a time extension of
four (4) days due to weather delays to a new contract time of 399 days and a contract price
increase of $53,614.40 for additional HDPE footage needed to clear the existing underground
structure that was unknown; and,
WHEREAS, per Resolution No. 15-076, Change Order 9, authorized a time extension of
thirty (30) days for a new contract time of 429 days with a new completion date of March 24,
2015, and an increase of the contract price to $3,518,973.40 for the installation of two 24"tees,
P. R. No. 18908
03/17/15jj
Page 3 of 4
24" valves, foster adapters and solid sleeves to serve the proposed Terminal Road Elevated
Storage Tank Project. This change order will allow there to be water service available for the
supply water to the proposed storage tank once it is constructed. In addition this change order is
to remove and replace an existing fence along Terminal Road in order to install the proposed 24"
waterline; this change order has been evaluated by Arceneaux Wilson & Cole LLC, and the
Utility Operations Department (attached hereto as Exhibit"A"); and,
WHEREAS, Arceneaux Wilson & Cole LLC, has requested and recommended a
temporary contract delay for the 24" Waterline from 19th Street to the Sabine Neches Canal
Project with ALLCO, L.L.C., of Beaumont, Texas. The request is necessary as another
contractor has started working on a City of Port Arthur project, which does not allow ALLCO to
finish this contract. The work will resume once contractor completes assignment.
NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE
CITY OF PORT ARTHUR:
THAT, the City Council hereby authorizes a temporary contract delay for the 24"
Waterline from 19th Street to the Sabine Neches Canal Project with ALLCO, L.L.C., as a result
of another contractor working on a City of Port Arthur project (see Exhibit "A"), which does not
allow ALLCO, L.L.C., to finish this contract. The work will resume once contractor completes
assignment; and,
THAT, an authorized representative of ALLCO, L.L.0 will sign this resolution agreeing
to the terms thereof.
THAT, a copy of the caption of this resolution be spread upon the minutes of the City
Council.
P. R. No. 18908
03/17/15jj
Page 4 of 4
READ, ADOPTED AND APPROVED THIS day of , 2015
at a Regular Meeting of the City Council of the City of Port Arthur, Texas, by the following
vote:
AYES: Mayor ,
Councilmembers:
NOES:
Deloris Prince
Mayor
ATTEST: APPROVED AS TO FORM:
.\ij ,
Sherri Bellard Valecia Tizeno,
City Secretary City Attorney
APPROVED FOR ADMINISTRATION:
o n l
L
/
f , L ISI J-'L /�✓
2l
Brian McDougal Shawna Tubbs, CPPB,
City Manager Purchasing Manager
/ L By:
Jimmie Johnson, Ph.D. Agreed to: ALLCO, L.L.C.
Director of Utility Operations
Exhibit "A"
(AW&C Letter Requesting Suspension)
ARCENEAUX WILSON & COLE LLC
AWCEngineering • Surveying • Planning
March 10, 2015
Dr. Jimmie Johnson
City of Port Arthur
Water Utilities Director
PO Box 1089
Port Arthur, TX 77641
RE: Waterline Projects
Jimmie,
Please see attached request from ALLCO requesting a suspension of their contract on CPA-
650, the 24 inch waterline from 19th St. to the Sabine Neches Canal project. I recommend that
the City grant this request and begin the contract suspension effective March 1, 2015 and
remain in effect until ALLCO is able to resume work on the project. Please contact me if you
have any questions or concerns I can be reached by email at Joe.Wilson(a�awcenq.com or by
phone (409) 724-7888.
Sincerely,
111
Joe M.j'son, Jr., PE
Presid-nt
(409) 724-7888 • 2901 Turtle Creek Drive • Suite 320 • Port Arthur, Texas 77642
www.awceng.com
Registered Engineering Firm F-16194 Registered Survey Firm 10194049
AI ' DESIGN BUILD
CONSTRUCTION MANAGEMENT
GENERAL CONTRACTOR
MEM
P. O. Box 3684, Beaumont, Texas 77704 Phone: 409-860-4459 Fax: 409-860-3857
Email: allco@allco.com
March 10,2015
Attn: Joe Wilson,P.E.
Arceneaux Wilson& Cole
2901 Turtle Creek Drive, Suite 320
Port Arthur,Texas 77642
Re: 24" Waterline from 19th Street to Sabine-Neches Canal
City of Port Arthur
ALLCO Project TX-733
Dear Joe:
Please let this letter serve as our request for a suspension of time on the above referenced project.
Another contractor has started working on a City of Port Arthur project, which does not allow
ALLCO to finish this contract. Once the other contractor is finished and our work area is
restored to us,we will remobilize and finish this project.
Let me know if you have any questions.
Sincerely,
ALLCO LLC
Keith Burrell