HomeMy WebLinkAboutPR 18901: CHANGE ORDER NO. 10 ALLCO, L.L.C. 24" WATERLINE 19TH STREET MEMORANDUM
CITY OF PORT ARTHUR
UTILITY OPERATIONS DEPARTMENT
TO: Brian McDougal, City Manager
FROM: Jimmie Johnson, Ph.D., Director of Utility Operation
DATE: March 26, 2015
RE: Proposed Resolution No. 18901
RECOMMENDATION
I recommend that the City Council approve Proposed Resolution No. 18901 authorizing
the execution of Change Order No. 10 for the 24" Waterline from 19th Street to the
Sabine Neches Canal Project with ALLCO, L.L.C., of Beaumont, Texas. This change
order is for time extension of eight (8) days due to weather delays during the month of
February.
BACKGROUND
This project will extend a 24" water transmission main from the old Water Purification
Plant to W. 7th Street and SH 82.
BUDGET/FISCAL EFFECT
Pursuant to Resolution No. 12-597, funding for this project will be charged through a
City Account No. 429-1258-532.59-00, Project No. WSI003; the recommendation does
not affect account.
SUMMARY
I recommend that the City Council approve Proposed Resolution No.18901 authorizing
the City Manager to execute Change Order No. 10 for a time extension of eight (8) days
due to weather delays during the month of February, to the contract for the installation
of a Waterline from 19th Street to the Sabine Neches Canal, to a new contract time of
437 days.
P. R. No. 18901
03/26/15 jj
RESOLUTION NO.
A RESOLUTION AUTHORIZING THE CITY MANAGER TO EXECUTE
CHANGE ORDER NO. 10 BETWEEN THE CITY OF PORT ARTHUR
AND ALLCO, L.L.C.; FOR THE 24" WATERLINE FROM 19TH STREET
TO THE SABINE NECHES CANAL, FOR A TIME EXTENSION OF
EIGHT (8) DAYS DUE TO WEATHER DELAYS DURING THE MONTH
OF FEBRUARY, TO A NEW CONTRACT TIME OF 437 DAYS.
WHEREAS, per Resolution No. 13-503, the City entered into a contract for the
installation of a Waterline from 19th Street to the Sabine Neches Canal, in the amount of
$3,114,960.00, with a contract term of 365 calendar days; and
WHEREAS, per Resolution No. 14-210, Change Order 1 authorized an
additional $40,486.00 to add storm water pollution prevention measures required by the
City of Port Arthur that was not included in the original contract, bringing the contract
price for the project to $3,155,446.00 accepted by Allco; and
WHEREAS, per Resolution No. 14-300, Change Order 2 authorized a credit of
$21,980.00 for the use of 24" Certa-Loc restrained joint C900 PVC pipe in lieu of the 24"
cement lined restrained joint gasket ductile iron pipe in the original bid to a new contract
total of $3,133,466, and a time extension of six (6) days due to inclement weather bring
the date of completion to January 25, 2015; and
WHEREAS, per Resolution No. 14-342, Change Order 3 authorized an
additional $12,072.00 for the relocation of an existing 6" waterline that was discovered
during construction on Charleston Ave, the re-route of the 24" waterline to miss an
existing storm sewer, and one foot of extra cover added to the 24" waterline approx.
2,100 L.F. to ensure protection of the line during the 18th Street construction project to a
new contract total of $3,145,538.00, and a time extension of six (6) days due to
inclement weather, bringing the date of completion to January 31, 2015; and,
P. R. No. 18901
03126/15jj
Page 2 of 4
WHEREAS, per Resolution No. 14-389, Change Order 4, authorized a time
extension of 3 days due to weather delays, to a new completion date of February 3,
2015; and,
WHEREAS, per Resolution No. 14-449, Change Order 5, authorized the
relocation of the proposed 24" waterline to avoid an existing structure at the intersection
of 18th Street and Railroad Ave. in the amount not to exceed $53,100.00 to a new
contract total of $3,198,638.00 and a time extension of three (3) days due to inclement
weather bring the date of completion to February 6, 2015; and,
WHEREAS, per Resolution No. 14-554, Change Order 6, authorized the
relocation of an existing 12" waterline at Railroad Ave. in the amount not to exceed
$52,659.00, and a time extension of eight (8) days due to inclement weather; and,
WHEREAS, per Resolution No. 14-607, Change Order 7, authorized the
performing a 20-inch hot tap on an existing 20-inch waterline on Atlanta Street and an
additional 250 feet of 30-inch, DR-11 HDPE of directional drilling in an amount not to
exceed $141,090.00, and a time extension of four (4) days due to inclement weather;
and,
WHEREAS, per Resolution No. 14-645, Change Order 8, authorized a time
extension of four (4) days due to weather delays to a new contract time of 399 days and
a contract price increase of $53,614.40 for additional HDPE footage needed to clear the
existing underground structure that was unknown; and,
WHEREAS, per Resolution No. 15-076, Change Order No. 9 authorized a time
extension of thirty (30) days for a new contract time of 429 days with a new completion
P. R. No. 18901
03/26/15jj
Page 3 of 4
WHEREAS, per Resolution No. 15-076, Change Order No. 9 authorized a time
extension of thirty (30) days for a new contract time of 429 days with a new completion
date of March 24, 2015, and increased the contract price to $3,518,973.40 for the
installation of two 24" tees, 24" valves, foster adapters and solid sleeves to serve the
proposed Terminal Road Elevated Storage Tank project. This change order allowed
there to be water service available for the supply water to the proposed storage tank
once it is constructed. In addition this change order removed and replaced an existing
fence along Terminal Road in order to install the proposed 24" waterline; and,
WHEREAS, Arceneaux Wilson & Cole LLC, has requested and recommended
Change Order No. 10 for a time extension of eight (8) days due to weather delays, to a
new completion date of April 1, 2015, attached as Exhibit "A".
NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY
OF PORT ARTHUR:
THAT, the City Manager of the City of Port Arthur is hereby authorized and
directed to execute, on behalf of the City of Port Arthur, Change Order No. 10 between
the City of Port Arthur and AlIco L.L.C., for the increased time extension of eight (8)
days for a new contract time of 437 days, with a new completion date of April 1, 2015,
attached hereto as Exhibit "A"; and,
THAT a copy of the caption of this resolution be spread upon the minutes of the
City Council.
READ, ADOPTED AND APPROVED THIS day of
2015 at a Regular Meeting of the City Council of the City of Port Arthur, Texas, by the
following vote:
P. R. No. 18901
03/26/15jj
Page 4 of 4
YES: Mayor
Councilmembers:
NOES:
Deloris Prince
Mayor
ATTEST: APPROVED AS TO FORM:
Sherri Bellard Valecia Tizeno
City Secretary City Attorney
APPROVED FOR ADMINISTRATION:
5/c,i_LAfft.ailid
Brian McDougal Shawna Tubbs, PPB, CPPO
City Managed Purchasing Manager
Jimmie Johnson, Ph.D.
Director of Utility Operations
Exhibit "A"
(AW&C Change Order No.10)
Exhibit "A"
(AW&C Change Order No.10)
AWC Engineering
Surveying
Planning Arceneaux Wilson & Cole LLC
Consulting Engineers
2901 Turtle Creek Drive, Suite#320 Port Arthur, TX 77642
Phone: 409-724-7888 Fax: 409-724-1447
www.awceng.com
LETTER OF TRANSMITTAL
DATE: March 9, 2015 PROJECT NO.: CPA-650
TO: City of Port Arthur ATTENTION: Dr.Jimmie Johnson
444 4th Street
Port Arthur,TX 77640 RE: City of Port Arthur Water Systems
Improvements, Port Arthur Water Line
WE ARE SENDING YOU ❑ Attached ❑ Under Separate Cover Via: Hand Delivery The following items:
❑ Memo ❑ Monthly Invoice ❑ Plans ❑ Construction Documents
❑ Letter ❑✓ Change Order No. 10 ❑ Form ❑ Other
COPIES DATE DESCRIPTION
4 3-9-15 Change Order No. 10
THESE ARE TRANSMITTED as checked below:
❑✓ For approval ❑ Approved as submitted ❑ Resubmit copies for approval
❑ For your use ❑ Approved as noted ❑ Submit copies for distribution
❑ As requested ❑ Returned for corrections ❑Submit corrected prints
,
❑ For review and comment Execute and return original RECEIVED
ED
RECEIVED BY:
MAR 1 0 2015
COMMENTS:
UTILITY OPERATIONS
Admin.-City Hall
COPY TO: SIGNED: Stephanie Morrell
REQUEST FOR EXTENSION OF TIME DUE TO WEATHER OR SUPPLIES
CITY OF PORT ARTHUR
DA lb: 3 '"S� , 20 /r
MONTH OF: led/Zdii4-/f7 , 20
CITY of PORT ARTHUR, i'hXAS
WATER UTILITIES DEPARTMENT
P.O.BOX 1089
CITY of PORT ARTHUR,TEXAS 77641-1089
A ITENTION: John Tomplait
Interim Utilities Director
Gentlemen:
We request extension of completion time on our Contract due to the days of work lost as
specified(list dates actually lost: do not include days not normally worked such as Saturdays,
Sundays, or holidays):
Dates Lost: 2/4 Z 21/6 1 I ,�
S � Z/v,
1 � j /
Days Lost( (o )/ 5 x 7+ 6 Calendar Days Requested
Reasons for Request:
M1 s
Contractor A.GLe_c,
By:
Approved for extension of calendar days.
Disapproved.
Date: , 20 CITY OF CITY OF PORT ARTHUR, 1'bXAS
BY:
City Manager
Distribution by City
Original: Water Utilities Department
xc: Engineer
Contractor
CPA Federally Funded
ARCENEAUX WILSON & COLE LLC
Arceneaux Wilson & Cole
AWCEngineering • Surveying • Planning
March 6, 2015
Dr. Jimmie Johnson
Director of Water Utilities
City of Port Arthur
444 Fourth Street
Port Arthur, Texas 77640
RE; PROPOSAL FOR CHANGE ORDER NO. 10
24"WATERLINE FROM 19TH STREET TO THE SABINE-NECHES CANAL
Job No, CPA-650
Dear Mr. Johnson:
Attached is Change Order No. 10 for the 24" Waterline from 19th Street to the Sabine-Neches
Canal. This change order is for time extension of 8 days due to weather delays during the
month of February. I recommend that the City of Port Arthur authorize this change to the
contract. I have attached Change Order No. 10 which modifies the contract to reflect this
change for your consideration and action. Should you have any questions or require additional
information, please contact our office.
Very truly yours,
Arceneaux Wilson & Cole LLC
TEXAS REGISTERED ENGINEERING FIRM F-16194
Keestan Cole, PE
Vice-President
(409) 724-7888 • 2901 Turtle Creek Drive • Suite 320 • Port Arthur, Texas 77642
www.awceng.com
Arceneaux Wilson A Cole----•
A w F
C
CHANGE ORDER No. 10
DATE: March 6, 2015 JOB NO. CPA-650
AGREEMENT DATE: November 5, 2013
NAME OF PROJECT: 24" Waterline from 19th Street to the Sabine-Neches Canal
OWNER: CITY of PORT ARTHUR
CONTRACTOR: ALLCO
The following changes are hereby made to the CONTRACT DOCUMENTS:
1. Add the following Items to the Contract and Scope of Work:
a. Extend contract time by 8 days
ir•
CHANGE ORDER NO. 10
March 6, 2015
ArcCne5UZ Wilson & Cole
AWCJob No. CPA-650, Contract No. 1
CHANGE TO CONTRACT PRICE:
ORIGINAL CONTRACT PRICE: $3,114,960.00
CURRENT CONTRACT PRICE adjusted by previous CHANGE ORDER(S): $ 3,518,973.40
The CONTRACT PRICE due to this CHANGE ORDER will be [increased] [decreased]
by: $ 0.00 Dollars
The new CONTRACT PRICE, including this CHANGE ORDER,will be $ 3,518,973.40
CHANGE TO CONTRACT TIME:
ORIGINAL CONTRACT TIME: 365 Calendar Days
CURRENT CONTRACT TIME adjusted by previous CHANGE ORDER: 64 Calendar Days
CURRENT DATE OF COMPLETION: March 24, 2015
CONTRACT TIME due to this CHANGE ORDER will be increased by 8 Days
The New DATE OF COMPLETION: April 1, 2015
No other Terms and Conditions of the Contract are changed as a result of this Change Order.
Contractor's acceptance of Change Order relieves OWNER of any liability for additional costs
incurred by Contractor in his performance of the work covered by the Change Order.
RECOMMENDED BY ENGINEER: ACCEPTED BY:
0/
ARCENEAUX WILSON & COLE LLC [C TRACTOR,OFFICER OR OW R]
ALLCO
ACCEPTED BY:
CITY of PORT ARTHUR
2 of 2