HomeMy WebLinkAboutPR 18915: CHANGE ORDER NO. 2 APAC-TEXAS, INC. MEMORANDUM
CITY OF PORT ARTHUR
PUBLIC WORKS - ENGINEERING DIVISION
TO: Brian McDougal, City Manager
FROM: Susan Polka, P.E., Public Works Director/City Engineer
DATE: March 25, 2015
RE: Proposed Resolution No. 18915
RECOMMENDATION
I recommend that the City Council approve Proposed Resolution No. 18915 that would
authorize the City Manager to execute Change Order No. 2 to the contract with APAC-
TEXAS, Inc., for construction of street paving improvements along 10th Street between
Stadium Road and Duff Drive, extending the duration of the contract by 11 calendar
days.
BACKGROUND
By Resolution 14-318 dated July 22, 2014, the City Council awarded a contract to APAC-
TEXAS, Inc., of Beaumont, Texas, in the amount of $686,131.50, for the construction of
street paving improvements along 10th Street between Stadium Road and Duff Drive.
Per Resolution No. 14-627, the City Council authorized Change Order No. 1 to the
contract for modification to the existing brick inlets to retrofit concrete tops and
manholes, which increased the contract amount by $4,876.00, to a new contract total of
$691,007.50. The current contract completion date is April 4, 2015. Change Order No.
2 is a request for a time extension of 11 calendar days due to weather delays during the
month of February.
BUDGET/FISCAL EFFECT
Approval of Change Order No. 2 will have no effect on the approved budget for the
project.
SUMMARY
I recommend that the City Council approve Proposed Resolution No. 18915 that would
authorize the City Manager to execute Change Order No. 2 to the construction contract
with APAC-TEXAS, Inc., extending the contract completion date by 11 calendar days,
resulting in a new completion date of April 15, 2015.
P.R. No. 18915
3/25/15 sjp
RESOLUTION NO.
A RESOLUTION AUTHORIZING THE CITY MANAGER TO
EXECUTE CHANGE ORDER NO. 2 TO THE CONTRACT BETWEEN
THE CITY OF PORT ARTHUR AND APAC-TEXAS, INC., OF
BEAUMONT, TEXAS, AND GLO, FOR THE 10TH STREET PAVING
IMPROVEMENTS, INCREASING THE TIME OF THE CONTRACT
BY 11 CALENDAR DAYS DUE TO WEATHER DELAYS, TO A NEW
TERM OF 191 CALENDAR DAYS, AT NO ADDITIONAL COST.
WHEREAS, on July 22, 2014, per Resolution No. 14-318, the City Council
awarded a contract for the 10th Street Improvements to APAC-TEXAS, Inc., of
Beaumont, Texas, in the amount of $686,131.50 with a contract time of 180 calendar
days, said project being from Stadium Road to Duff Drive; and,
WHEREAS, on per Resolution No. 14-627, the City Council approved Change
Order No. 1 for the modification of the existing brick inlets to retrofit concrete tops and
manholes, which increased the contract amount by $4,876.00, to a new contract total
of $691,007.50; and,
WHEREAS, during construction of the project, it was determined that an
eleven (11) calendar day time extension was needed due to weather delays; and,
WHEREAS, APAC-TEXAS, Inc., has submitted Change Order No. 2 for the
project, and the Public Works Director/City Engineer and the Project Engineer
recommend approval of Change Order No. 2 extending the contract time by 11
calendar days due to weather delays, attached as Exhibit"A"; NOW THEREFORE,
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF PORT
ARTHUR:
P.R. No. 18915
3/25/15 sjp
Page 2 of 3
THAT, the City Manager of the City of Port Arthur is hereby authorized and
directed to execute, on behalf of the City of Port Arthur, Change Order No. 2 (attached
as Exhibit "A") to the contract between the City of Port Arthur and APAC-TEXAS, Inc.,
extending the contract time by eleven (11) calendar days due to weather delays; and,
THAT, Change Order No. 2 extends the new contract date of completion to
April 15, 2015; and,
THAT, a copy of the caption of this resolution be spread upon the minutes of
the City Council.
READ, ADOPTED AND APPROVED THIS day of , 2015
at a Regular Meeting of the City Council of the City of Port Arthur, Texas, by the
following vote:
AYES: Mayor ,
Councilmembers:
NOES:
Deloris Prince
Mayor
P.R. No. 18915
3/25/15 sjp
Page 3 of 3
ATTEST: APPROVED AS TO FORM:
I I I I r.4114 :
Sherri Bellard V ecia Tizeno /
City Secretary City Attorney
APPROVED FOR ADMINISTRATION:
[14:z1
Brian McDougal Shawna Tubbs, CPPO, CPPB
City Manager Purchasing Manager
Susan Polka, P.E.
Public Works Director/City Engineer
EXHIBIT "A"
P.R. No. 18915
ARCENEAUX WILSON & COLE LLC
Ar<en raux Wilson & Cole---
AWCEngineering • Surveying • Planning
March 16, 2015
Ms. Sue Polka, PE
Director of Public Works/City Engineer
City of Port Arthur
444 Fourth Street
Port Arthur, Texas 77640
RE; PROPOSAL FOR CHANGE ORDER NO 2
Wm STREET IMPROVEMENTS
Job No. CPA-790
Dear Ms. Polka:
Attached is Change Order No. 2 for the 10th Street Improvements. This change order is for time
extension of 11 days due to weather delays during the month of February. I recommend that
the City of Port Arthur authorize this change to the contract. I have attached Change Order No.
2 which modifies the contract to reflect this change for your consideration and action. Should
you have any questions or require additional information, please contact our office.
Very truly yours,
ARCENEAUX WILSON & COLE LLC
TEXAS REGISTERED ENGINEERING FIRM F-16194
eestan Cole, PE
Vice President
2901 Turtle Creek Dr.,Suite 320 Port Arthur,TX 77642 Phone: 409/724-7888 Fax: 409/724-1447
/r
Ar ceneau. Wilson & Cole
AwcF.R('!rlrFr7rr('
$0
Ytat,tr:irr�wig
CHANGE ORDER No. 2
DATE: March 16, 2015 JOB NO. CPA-790
AGREEMENT DATE: July 23, 2014
NAME OF PROJECT: 10th Street Improvements
OWNER: CITY of PORT ARTHUR
CONTRACTOR: APAC — TEXAS, INC.
The following changes are hereby made to the CONTRACT DOCUMENTS:
1. Add the following Items to the Contract and Scope of Work:
a. Extend contract time by 11 days
CHANGE ORDER NO. 2
J %! March 16, 2015
Arceneau. Wilson & tolAWce--"w`n?.__`."`
:n ;nt;T;rK Job No. CPA-790, Contract No. 1
Planning
CHANGE TO CONTRACT PRICE:
ORIGINAL CONTRACT PRICE: $686,131.50
CURRENT CONTRACT PRICE adjusted by previous CHANGE ORDER(S): $691,007.50
The CONTRACT PRICE due to this CHANGE ORDER will be [increased] [decreased]
by: $0.00 Dollars
The new CONTRACT PRICE, including this CHANGE ORDER, will be $691,007.50
CHANGE TO CONTRACT TIME:
ORIGINAL CONTRACT TIME: 180 Calendar Days
CURRENT CONTRACT TIME adjusted by previous CHANGE ORDER: 0 Calendar Days
CURRENT DATE OF COMPLETION: April 4, 2015
CONTRACT TIME due to this CHANGE ORDER will be increased by 11 Days
The New DATE OF COMPLETION: April 15, 2015
No other Terms and Conditions of the Contract are changed as a result of this Change Order.
Contractor's acceptance of Change Order relieves OWNER of any liability for additional costs
incurred by Contractor in his performance of the work covered by the Change Order.
RECOMMENDED BY ENGINEER: ACCEPTED BY:
vim' 7j/e
A-CENEAUX WILSON & COLE LLC [CONTRACTOR,OFFICER OR OWNER]
APAC-TEXAS, INC.
ACCEPTED BY:
CITY of PORT ARTHUR
2 of 2
C
AL (-9
\tl% ° Texas General Land Office
>. Disaster Recovery
r 36is HED ,a
Construction Contract Change Order Request Form
Engineer: Owner (Contractor Locality): Contractor:
APAC-TEXAS, INC. CITY OF PORT ARTHUR ARCENEAUX
12907 US HWY 90 444 4TH STREET WILSON & COLE LLC
BEAUMONT, TX 77713 PORT ARTHUR, TX 77642 2901 TURTLE CREEEK DR.
Phone No.: 409-866-1444 SUITE 320
PORT ARTHUR, TX 77642
Phone No.: 409-983-8296
Agreement Date:
July 23, 2014
Phone No.: 409-724-7888
Date: March 16, 2015 Contract For (Project Description): GLO Contract No.:
Project Code No.: P2107 12-305-025-6542
10th Street Improvements
Bid Package No.: 9 Change Order No.: 2
You are hereby requested to comply with the following changes from the contract plans and specifications:
Item Description of Changes: Quantities, Units, Unit Prices, Decrease in Increase in
No. Change in Completion Scheduled, Etc. Contract Price Contract Price
Construction Contract Change Order Request Form Page 1 of 3
CDBG Disaster Recovery Program May 2012
Change in Contract Price Change in Contract Time (Calendar Days)
Original Contract Price: $ 686, 131.50 Original Contract Time: 180 days
Previous Change Order(s): Net Change From Previous
No. 1 to No. 2 $ 4,876.00 Change Orders: 0 days
Contract Price Prior to Contract Time Prior to
this Change Order: $ 691,007.50 this Change Order: 11 days
Net Increase/Decrease of Net IIncrease/Decrease of
this Change Order: $ 0.00 this Change Order: 11 days
Contract Price With all Contract Time With all
Approved Change Orders: $ 691,007.50 Change Orders: 191 days
Cumulative Percent Change in Contract Price (+/-): Grantee Contract End Date:
0.7 % (mm/dd/yy) 12 / 31 /2015
Construction Contract Start Date: Construction Contract End Date:
(mm/dd/yy) 10/6/2014 (mm/dd/yy) 4 / 15 / 2015
Reimbursements of costs included in this change order are subject to review by the GLO-DR program.
This document may be executed prior to submission for GLO-DR program review, but all parties
involved will be held responsible if the change order or the amendment warranted as a result of
this change order is not in compliance with CDBG or HUD requirements.
RECOMMEND APPROVED: ACCEPTS il
By: By: By:
ENGINEER OWNER CONTRACTOR
Date: "VS-- Date: Date:
Construction Contract Change Order Request Form Page 2 of 3
CDBG Disaster Recovery Program May 2012
JUSTIFICATION FOR CHANGE
1. Will this Change Order increase or decrease
the number of beneficiaries? 0 Increase 0 Decrease ✓ No Change
If there is a change, how many beneficiaries will be affected? Total L/M
2. Effect of this change on scope of work: 0 Increase 0 Decrease ✓ No Change
3. Effect on operation and maintenance costs: 0 Increase 0 Decrease ✓ No Change
4. Are all prices in the change order dependent upon unit prices
found in the original bid? ✓ Yes 0 No
If"No", explain:
5. Has this change created new circumstances or environmental
conditions which may affect the project's impact, such as
concealed or unexpected conditions discovered during actual
construction? 0 Yes ✓ No
If"Yes", is an Environmental Re-assessment required?
6. Is the Texas Commission on Environmental Quality (TCEQ)
clearance still valid? (if applicable) ✓ Yes 0 No
7. Is the TCEQ permit approval still valid? (sewer projects only) ✓ Yes 0 No
8. Are the handicapped access requirements/approval
still valid? (if applicable) ✓ Yes 0 No
9. Are other Disaster Recovery contractual special condition clearance
still valid? ✓ Yes 0 No
(If no, specify):
NOTE:
* Generally, a cumulative change in the contract price in excess of 25% cannot
be reviewed (18% decrease for counties).