HomeMy WebLinkAboutPR 18944: CHANGE ORDER NO. 8 ALLCO, L.L.C., CHAIN LINK FENCE MEMORANDUM
CITY OF PORT ARTHUR
Utility Operations Department
TO: Brian McDougal, City Manager
FROM: Jimmie Johnson, Ph.D., Director of Utility Operations `
DATE: April 7, 2015
RE: Proposed Resolution No. 18944
RECOMMENDATION
I recommend that the City Council approve Proposed Resolution No. 18944 authorizing
the City Manager to execute Change Order No. 8 to the contract with ALLCO, L.L.C., of
Beaumont, Texas, for construction of the Highway 87 Water Transmission Line project
from Keith Lake to the Sabine Pass Standpipe. This Change Order is to modify the
existing chain link fence around Sabine Pass Standpipe and for a time extension of
seventeen (17) days, due to weather delays in the month of March.
BACKGROUND
On October 29, 2013, City Council approved the award of a contract in the amount of
$3,373,385.00 to ALLCO, L.L.C. for the construction of the Highway 87 Water
Transmission Line from the cut at Keith Lake to the new standpipe in Sabine Pass.
BUDGET/FISCAL EFFECT
Pursuant to Resolution No. 12-597, funding for this project is through City Account No.
429-1258-532.59-00, Project No. WSI002. This account will be affected by an increase
of $10,880, which is available.
SUMMARY
I recommend that the City Council approve Proposed Resolution No. 18944 authorizing
the City Manager to execute Change Order No. 8 for construction of the Highway 87
Water Transmission Line project from Keith Lake to the Sabine Pass Standpipe, to
modify the existing chain link fence around Sabine Pass Standpipe and for a time
extension of seventeen (17) days, due to weather delays in the month of March.
P.R. No. 18944
4/7/15 jj
RESOLUTION NO.
A RESOLUTION AUTHORIZING THE CITY MANAGER
TO EXECUTE CHANGE ORDER NO. 8 TO THE
CONTRACT BETWEEN THE CITY OF PORT ARTHUR
AND ALLCO, L.L.C., OF BEAUMONT, TEXAS, FOR THE
HIGHWAY 87 WATER SYSTEM IMPROVEMENTS
FROM KEITH LAKE TO SABINE PASS STANDPIPE, TO
MODIFY THE EXISTING CHAIN LINK FENCE
AROUND SABINE PASS STANDPIPE, INCREASING THE
CONTRACT AMOUNT BY $10,880.00, TO A NEW
CONTRACT AMOUNT OF $3,608,402.89, AND FOR A
TIME EXTENSION OF SEVENTEEN (17) DAYS, DUE TO
WEATHER DELAYS IN THE MONTH OF MARCH, FOR
A NEW DATE OF COMPLETION, MAY 13, 2015;
FUNDING AVAILABLE IN CITY ACCOUNT NO. 429-
1258-532.59-00, PROJECT NO. WSI002.
WHEREAS, per Resolution No. 13-492 dated October 29, 2013, the City Council
awarded a contract for the construction of the Highway 87 Water Transmission Line for Keith
Lake to the Sabine Pass Standpipe to ALLCO, L.L.C., in the amount of$3,373,385.00; and,
WHEREAS, per Resolution No. 14-224, Change Order No. 1 authorized the increase in
pipe material costs from October 29, 2013, and the increased cost to purchase the pipe material
for the project in the amount of$144,462.89 to a new contract total of$3,517,847.89; and,
WHEREAS, per Resolution No. 14-388, Change Order No. 2 authorized a time extension
of 4 days due to weather delays to a new contract time of 274 days; and,
WHEREAS, per Resolution No. 14-450, Change Order No. 3 authorized a time
extension of six (6) days due to weather delays to a new contract time of 280 days; and
WHEREAS,per Resolution No. 14-555, Change Order No. 4 authorized a time extension
of seven (7) days due to weather delays to a new contract time of 287 days; and,
WHEREAS, per Resolution No. 14-608, Change Order No. 5 authorized a time
extension of seven (7) days due to weather delays to a new contract time of 294 days; and,
P.R. No. 18944
4/7/15 jj
Page 2 of 4
WHEREAS, per Resolution No. 14-644, Change Order No. 6 authorized a time
extension of eleven (11) days due to weather delays to a new contract time of and 305 days and a
contract price increase of$79,675.00 due to the extension of three directional drills due to soil
conditions in the working area; and,
WHEREAS, per Resolution No. 15-086, Change Order No. 7 authorized a time
extension of 24 days, due to weather delays, to a new contract term of 329 days; and,
WHEREAS, the project engineer, Arceneaux Wilson & Cole LLC, recommends
proposed Change Order No. 8 to modify the existing chain link fence around the Sabine Pass
Standpipe in Sabine Pass, increasing the contract amount $10,800, to a new contract total of
$3,608,402.89 and for time extension of seventeen (17) days, due to weather delays for the
month of March, for a new date of completion, May 13, 2015 (attached as Exhibit "A") to
accomplish this work.
NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE
CITY OF PORT ARTHUR:
THAT, the City Manager of the City of Port Arthur is hereby authorized and directed to
execute, on behalf of the City of Port Arthur, Change Order No. 8 (attached as Exhibit "A") to
the contract between the City of Port Arthur and ALLCO, L.L.C. of Beaumont, Texas, increasing
the contract by $10,880, and increasing the total contract by seventeen (17) days, to a new
completion date of May 13, 2015; and,
THAT, Change Order No. 8 is to modify the existing chain link fence around Sabine
Pass Standpipe, increasing the contract by $10,880, to a new contract amount of$3,608,402.89;
and,
P.R. No. 18944
4-7-15
Page 3 of 4
THAT, Change Order No. 8 increases the contract time to seventeen (17) days, with a
new completion date of May 13, 2015; and,
THAT, Change Order No. 8 will require $10,880 of additional funding by the Project
No. WSI002, City Account No. 429-1258-532.59-00; and,
THAT, a copy of the caption of this resolution be spread upon the minutes of the City
Council.
READ, ADOPTED AND APPROVED THIS day of , 2015 at a
Regular Meeting of the City Council of the City of Port Arthur, Texas, by the following vote:
AYES: Mayor:
Councilmembers:
NOES:
Deloris Prince
Mayor
ATTEST: APPROVE 1 AS TO FORM:
Sherri Bellard Valecia eno
City Secretary City Attorney
P.R. No. 18944
4-7-15
Page 4 of 4
APPROVED FOR ADMINISTRATION:
,/
.-I _ - L ,
Brian McDougal Shawna Tubbs, CPPO, CPPB
City Manager Purchasing Manager
Jimmie Johnson, Ph.D.
Director of Utility Operations
APPROVED AS TO AVAILABILITY OF FUNDS:
iebori k-L-AL /1(Ajt.‘..,
ah Echols, CPA
Director of Finance
Account No. 429-1258-532.59-00,
(Project No. WSI002)
Exhibit "A"
(AW&C Change Order No. 8)
Tessa Artis
From: Keestan Cole <Keestan.Cole@awceng.com>
Sent: Tuesday, April 07, 2015 7:15 AM
To: Dr. Jimmie Johnson; Tessa Artis
Cc: Joe Wilson
Subject: S.H. 87 Water System Improvements from Keith Lake to Sabine Pass Standpipe Change
Order No. 8
Attachments: CO COVER LETTER.doc; CHANGE ORDER NO. 8.doc
All,
Attached is the word documents for Change Order No. 8 on the S.H. 87 Water System Improvements from Keith
Lake to Sabine Pass Standpipe project.This is to modify the existing chain link fence at the site to enclose the entire
property that the standpipe is located on.The existing chain link fence that was installed years ago when the standpipe
was constructed does not provide adequate security to protect the existing water valves, meters and electrical systems
at the site. Cheniere has made the request to add this to the contract for this project since the contractor is already
there working in the area.We will be sending the signed hard copies of these documents this morning as soon as the
contractor signs them.
Keestan Cole, P.E.
Vice President
Keestan.Cole@awceng.com
AWC
Arceneaux Wilson & Cole LLC
409.724.7888 : Office
409.724.1447 : Fax
409.749.0439 : Mobile
2901 Turtle Creek Dr., Suite 320
Port Arthur TX, 77642
www.awceng.com
CONFIDENTIALITY NOTICE:
The contents of this email message and any attachments are intended solely for the addressee(s)and may contain confidential and/or privileged information and
may be legally protected from disclosure. If you are not the intended recipient of this message or their agent,or if this message has been addressed to you in
error,please immediately alert the sender by reply email and then delete this message and any attachments.If you are not the intended recipient,you are hereby
notified that any use,dissemination,copying,or storage of this message or its attachments is strictly prohibited.
1
AWC Engineering
Surveying
Planning Arceneaux Wilson & Cole LLC
Consulting Engineers
2901 Turtle Creek Drive, Suite#320 Port Arthur,TX 77642
Phone: 409-724-7888 Fax: 409-724-1447
www.awceng.com
LETTER OF TRANSMITTAL
DATE: April 7, 2015 PROJECT NO.: CPA-705
TO: City of Port Arthur ATTENTION: Mr. Jimmie Johnson
444 4th Street
Port Arthur, TX 77640 RE: SH. 87 Water Improvements from Keith
Lake to Sabine Pass Standpipe
WE ARE SENDING YOU ❑ Attached ❑ Under Separate Cover Via: Hand Delivery The following items:
n Memo ❑ Monthly Invoice ❑ Plans ❑ Construction Documents
Letter I Change Order No. 8 ❑ Form Other
COPIES DATE DESCRIPTION
4 4-7-15 Change Order No. 8
THESE ARE TRANSMITTED as checked below:
nFor approval n Approved as submitted ❑ Resubmit copies for approval
❑ For your use ❑ Approved as noted ❑ Submit copies for distribution
nAs requested ❑ Returned for corrections ❑Submit corrected prints
❑ For review and comment Execute and return original
RECEIVED BY:
COMMENTS:
COPY TO: SIGNED: Stephanie Morrell
ARCENEAUX WILSON & COLE LLC
r it .n . .I AWC Engineering • Surveying • Planning
April 6, 2015
Dr. Jimmie Johnson
Director of Water Utilities
City of Port Arthur
444 Fourth Street
Port Arthur, Texas 77640
RE; PROPOSAL FOR CHANGE ORDER NO 8
STATE HIGHWAY 87 WATER SYSTEM IMPROVEMENTS FROM KEITH
LAKE TO SABINE PASS STANDPIPE
Job No. CPA-705
Dear Dr. Johnson:
Attached is Change Order No. 8 for the State Highway 87 Water System Improvements from
Keith Lake to Sabine Pass Standpipe. This change order is modify the existing chain link fence
around the Sabine Pass Standpipe in Sabine Pass. Also, this change order is for time
extension of 17 days due to weather delays for the month of March. I recommend that the City
of Port Arthur authorize this change to the contract. The total cost for this change order will
increase the contract amount $10,880.00. I recommend that the City of Port Arthur authorize
this change to the contract. I have attached Change Order No. 8 which modifies the contract to
reflect this change for your consideration and action. Should you have any questions or require
additional information, please contact our office.
Very truly yours,
ARCENEAUX WILSON& COLE LLC
TEXAS REGISTERED ENGINEERING FIRM F-16194
7 CJ�
Keestan Cole, PE
Vice President
2901 Turtle Creek Dr.,Suite 320 Port Arthur,TX 77642 Phone: 409/724-7888 Fax: 409/724-1447
Arceneaua Wllzon & Cole
AWC r„V/W n„
Cu'Irving
Manning
CHANGE ORDER No. 8
DATE: April 6, 2015 JOB NO. CPA-705
AGREEMENT DATE: November 5, 2013
NAME OF PROJECT: State Highway 87 Water System Improvements
OWNER: CITY of PORT ARTHUR
CONTRACTOR: ALLCO
The following changes are hereby made to the CONTRACT DOCUMENTS:
1. Add the following Items to the Contract and Scope of Work:
a. Modify Existing Chan Link Fence at the
Standpipe in Sabine Pass
[+] $ 10,880.00
b. Extend contract time by 17 days
TOTAL $ 10,880.00
CHANGE ORDER NO. 8
April 6, 2015
Ar •� .....M. Job No. CPA-705
AWC
CHANGE TO CONTRACT PRICE:
ORIGINAL CONTRACT PRICE: $3,373,385.00
CURRENT CONTRACT PRICE adjusted by previous CHANGE ORDER(S): $3,597,522.89
The CONTRACT PRICE due to this CHANGE ORDER will be [increased] {decreased]
by: $10,880.00 Dollars
The new CONTRACT PRICE, including this CHANGE ORDER, will be $3,608,402.89
CHANGE TO CONTRACT TIME:
ORIGINAL CONTRACT TIME: 270 Calendar Days
CURRENT CONTRACT TIME adjusted by previous CHANGE ORDER: 59 Calendar Days
CURRENT DATE OF COMPLETION: April 26, 2015
CONTRACT TIME due to this CHANGE ORDER will be increased by 17 Days
The New DATE OF COMPLETION: May 13, 2015
No other Terms and Conditions of the Contract are changed as a result of this Change Order.
Contractor's acceptance of Change Order relieves OWNER of any liability for additional costs
incurred by Contractor in his performance of the work covered by the Change Order.
RECOMMENDED BY ENGINEER: ACCEPTED BY:
-.1/1,14
ARCENEAUX WILSON & COLE LLC [C TRA TOR,OFFICER OR OWNER]
ALLCO
ACCEPTED BY:
CITY of PORT ARTHUR
2 of 2
REQUEST FOR EXTENSION OF TIME DUE TO WEATHER OR SUPPLIES
CITY OF PORT ARTHUR
DATE: AP/1-4 L._ 3 , 20 /
MONTH OF: f\-2-04 , 20 I S
CITY of PORT ARTHUR, TEXAS
PUBLIC WORKS DEPARTMENT
P.O. BOX 1089
CITY of PORT ARTHUR, TEXAS 77641-1089
ATTENTION: Ross Blackketter, P.E.,
Public Works Director
Gentlemen:
We request extension of completion time on our Contract due to the days of work lost as
specified (list dates actually lost: do not include days not normally worked such as Saturdays,
Sundays, or holidays):
Dates Lost: 4z 13 3 f S 3) 9 3 1 . I l k , 3, IS 3/ 19,
3 � Igo 3I2"' � 3 ) 2_3 312
Days Lost( (L- )15 x 7 + 1 '7 Calendar Days Requested
Reasons for Request:
Contractor AT 1-1--
By: 46, ��,212LL
Approved for extension of calendar days.
Disapproved.
Date: , 20 CITY OF CITY OF PORT ARTHUR,
TEXAS
BY:
City Manager
Distribution by City
Original: Public Works Department
xc: Engineer
Contractor
CPA Federally Funded