HomeMy WebLinkAboutPR 19005: CHANGE ORDER NO. 4 SETEX CONSTRUCTION CORP. P. R. No. 19005 05/15/15 ca RESOLUTION NO. A RESOLUTION AUTHORIZING THE CITY MANAGER TO EXECUTE CHANGE ORDER NO. 4 (INCREASING THE TIME BY 21 DAYS) TO THE CONTRACT BETWEEN THE CITY OF PORT ARTHUR AND SETEX CONSTRUCTION CORP. OF BEAUMONT, TEXAS, DUE TO UNFORESEEN WEATHER CONDITIONS, TO A NEW TERM OF 168 DAYS, AT NO ADDITIONAL COST AND TO ACCEPT THE ARCHITECT'S CERTIFICATE OF SUBSTANTIAL COMPLETION FROM THE LABICHE ARCHITECTURAL GROUP, INC. FOR THE IMPROVEMENTS TO MONTROSE PARK AND LYON'S PARK WHEREAS, per Resolution No. 14-511, the City Council awarded a contract for the improvements to Lincoln Park, Montrose Park and Lyon's Park; and, WHEREAS, the improvements began on October 28, 2014, with a contract time of 85 calendar days and an ending date of February 14, 2015; and, WHEREAS, per Resolution No. 15-041, the City Council awarded Change Order No. 1 to increase the time of the contract by 30 days; and, WHEREAS, per Resolution No. 15-157, the City Council awarded Change Order No. 2 to increase the time of the contract by 11 days and Change Order No. 3 to increase the time of the contract by 21 days the purchase order issued for the project has a completion date of March 16, 2015; and, WHEREAS, SeTEX Construction Corp. has requested a time extension of 21 calendar days to their contract for a delay due to unforeseen weather conditions which caused the area to be muddy; and,the current contract will expire on April 30, 2015; and, WHEREAS, The LaBiche Architectural Group, Inc. has examined the request and recommends proposed Change Order No. 4 in the amount of 21 calendar days to be added to the contract time for SeTEX Construction Corp., said Change Order No. 4 being attached as Exhibit "A"; and P. R. No. 19005 05/15/15 ca WHEREAS, the new ending date for SeTEX Construction Corp.'s contract would be April 30, 2015; and, WHEREAS, the improvements to Montrose Park and Lyon's Park are now substantially complete and have met all of the required building codes, zoning requirements, inspections, etc., as delineated in the Code of Ordinances of the City of Port Arthur; and, WHEREAS, the City of Port Arthur has been presented a Certificate of Substantial Completion for Montrose Park attached hereto as Exhibit "B" and a Certificate of Substantial Completion for Lyon's Park attached hereto as Exhibit"C"; and, WHEREAS, staff recommends to City Council that the City Manager be authorized to accept said Certificate of Substantial Completion as delineated herein; now therefore, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF PORT ARTHUR, TEXAS: Section 1. That the facts and opinions in the preamble are true and correct. Section 2. That the City Manager of the City of Port Arthur is hereby authorized and directed to execute, on behalf of the City of Port Arthur, Change Order No. 4, attached as Exhibit "A" in the amount of 21 calendar days, to the contract between the City of Port Arthur and SeTEX Construction Corp., with the new ending date of the contract being April 30, 2015 and execute the Certificate of Substantial Completion for Montrose in a form approximate to that of Exhibit "B" and Certificate of Substantial Completion for Lyon's Park in a form approximate to that of Exhibit"C". P. R. No. 19005 05/15/15 ca Section 3. That prior to taking full and final possession of Montrose Park and Lyon's Park, all items indicated in the Punch List (incorporated in the Certificate of Substantial Completion) shall be completed by the Contractor, SeTEX Construction Corp. Section 4. That an authorized representative of SeTEX Construction Corp. shall sign a copy of the resolution agreeing to the terms thereof. Section 5. That prior to the release of project retainage monies, the Director of Parks and Recreation must certify to the City Manager that the park improvements are complete and all items listed in the Punch List(incorporated in the Certificate of Substantial Completion) have been finished and the Director of Parks and Recreation must be in receipt of all warranties related to the parks. Section 6. That a copy of the caption of this Resolution be spread upon the Minutes of the City Council. READ, ADOPTED AND APPROVED THIS day of , A.D., 2015, at a Regular Meeting of the City Council of the City of Port Arthur, by the following vote: AYES:(Mayor) Councilmembers: NOES: Deloris "Bobbie" Prince Mayor P. R. #19005 05/15/15 ca ATTEST: Sherri Bellard City Secretary APPROVED AS TO FORM: V ' 2 )/1 Val Tizeno, Esq. City Attorney APPROVED AS TO ADMINISTRATION: Brian McDougal City Manager Albert T. Thigpen, CPRP, IPMA-CP, CAS, CPS Director of Parks and Recreation /j2d0M ,%•‘— Shawna Tubbs, CPPO, CPPB Purchasing Manager AGREED TO: SETEX CONSTRUCTION CORP. By: Print Name: Title: EXHIBIT "A" CHANGE ORDER PROJECT: City of Port Arthur Park CHANGE ORDER NO: 4 Improvements (Lincoln, Montrose, & Lion's) CONTRACTOR: SeTEX Construction Corp. DATE: 04.29.15 1660 S. 23`d Street ARCHITECT'S PROJECT NO.: 13049 Beaumont, Texas 77707 CONTRACT DATE: 11.06.14 CONTRACT FOR: Improvements The Contract is changed as follows: Time Extension due to rain/weather(month of April) Total Days: 21 **See attached Contract Time Statement Report#6 from SeTEX** Not valid until signed by the Owner,Architect, and Contractor. The original Contract Sum was $410,000.00 Net change by previously authorized Change Orders $0.00 The Contract Sum prior to this Change Order was $410,000.00 The Contract sum will be increased by this Change Order in the amount of $0.00 The new Contract Sum including this Change Order will be $410,000.00 The Contract Time will be increased by twenty-one (21) days. The date of Substantial Completion as of the date of this Change Order(Montrose Park) therefore is April 30, 2015. NOTE: The summary does not reflect changes in the Contract Sum or Contract Time which have been authorized by Construction Change Directive. The LaBiche Architectural Group SeTEX Construction City of Port Arthur 7999 Glady1Avenue, Suite 101 1660 S. 23rd Street P.O. Box 1089 Beaumont -x. 7e. Beaumont, Texas 707 Port Arthur, Texas 77641 By. // I� By: 2/ By: Date: ZDate: 5 f 1 ( 15 Date: leteir 01° -orrl LUF MOO * 4 - * (5) 4' 1 11592 'P� PORT ARTHUR PARKS IMPROVEMENTS-LINCOLN, MONTROSE&LION'S PARKS CONTRACT TIME STATEMENT PROJECT City of Port Arthur Parks Improvements REPORT NO. 6 PROJECT NO. 21436 LOCATION Lincoln,Montrose&Lion's Parks CONTRACTOR SeTEX Construction Corp. DATE WORK BEGAN: November 21,2014 DATE TIME COMPUTED FROM 4-1-15 to 4-30-15 DATE DAY LOST REASON FOR EXTENDED DAYS April 1,2015 0 April 2,2015 0 April 3,2015 0 April 4,2015 1 Rain April 5,2015 1 Rain April 6,2015 1 Too Muddy to Work April 7,2015 1 Too Muddy to Work April 8,2015 0 April 9,2015 0 April 10,2015 1 Rain April 11,2015 1 Rain&Too Muddy to Work April 12,2015 1 Rain&Too Muddy to Work April 13,2015 1 Rain&Too Muddy to Work April 14,2015 1 Rain&Too Muddy to Work April 15,2015 1 Too Muddy to Work April 16,2015 1 Rain&Too Muddy to Work April 17,2015 1 Rain&Too Muddy to Work April 18,2015 1 Rain&Too Muddy to Work April 19,2015 1 Too Muddy to Work April 20,2015 1 Too Muddy to Work April 21,2015 0 April 22,2015 0 April 23,2015 0 April 24,2015 0 April 25,2015 1 Rain April 26,2015 1 Rain April 27,2015 1 Rain&Too Muddy to Work April 28,2015 1 Too Muddy to Work April 29,2015 1 Too Muddy to Work April 30,2015 1 Too Muddy to Work 0 NUMBER EXTENDED DAYS: 21 NEW COMPLETION DATE: April 30,2015 RECOMMENDED AND APPROVED: OWNER'S REPRESENTATIVE ARCHITECT/ENGINEER A•Dril Weather for Beaumont, TX I Weather Underground Page 1 of 2 Weather History tor KEPT -April, ZO15 0 April Stets:Precipitation to date:9.38 in Normal to Date:3.65 in Normal Month Total:3.21 in Today Forecast Sunday Monday Tuesday Wednesday Thursday Friday Saturday 11/1/ ; ' 82°1 84°1 84°1 75° I Actual: Actual: Actual: Actual: 63° 69° 70° 62° 0.00 in Tin Tin 0.02 in 75°1 75°I 76°( 76°1 Average: 550 Average:5fi° Average:56° Average: 56° 0.10 in 0.09 in 0.10 in 0.10 in /wec C c ,,`r, 73°1 80°1 85°1 84° 1 85°1 83°1 Actual: 59° Actual: 65° Actual: 69° Actual: 72° Actual: 74° Actual: 65° Actual: 81°161° 0.09 in Tin 0.00 in 0.00 in 0.00 in 1.09 in 0.49 in ° 76° 1 76°1 76°1 77°I 77°1 77°1 Average 77 Average:S6° Average:57° Average:57° Average:57° Average:570 Average:58° 58° 0.10 in 0.10 in 0.10 in 0.10 in 0.09 in 0.10 in 0.10 in 7901 87°1 7601 8101 8001 8301 7801 Actual: Actual: Actual: Actual: Actual: Actual: Actual: 68° 70° 64° 62° 65° 66° 65° 0.63 in 0.26 in 0.67 in 0.00 in 4.39 in 0.90 in 0.37 in 77°1 78°1 78°1 78°1 78° I 78° I 79°I Average:58° Average:58° Average: 59° Average: Average: 5g° Average: 59° Average: 0.10 in 0.10 in 0.09 in 0.10 in 0.09 in 0.11 in 0.11 in 8501 77°1 7901 85°1 8801 86°1 8301 Actual: Actual: 59° Actual: Actual: Actual: 68° 710 Actual: Actual: 58° 59° 65° 68° 0.14 in 0.00 in 0.00 in 0.00 in 0.00 in T in 0.30 in 79°I 79°f 79°1 79°1 80°1 80°1 80°1 Average:60° Average:60° Average:60° Average:61° Average:61° Average:61° Average:62° 0.11in 0.11in 0.11 in 0.12 in 0.11 in 0.12 in 0.12 in • ///// /, // 85°1 79° ( f 69° I75°1 • 79° I Actual: 65° Forccast:66° i Forecast:51° `Forecast:S3° Forecast:5 Tin 0.23 in 0.0 in ' 0.Oin 0.0 in Average:BO° I Average:80° I Average:81°1 1 Average:81°1 Average:81°1 62 62 62 63° 63 0.12 in I 0.12 in ` 0.12 in 0.13 in 0.13 in Calendar Legend http://www.wunderground.com/history/airport/KBPT/2015/4/27/MonthlyCalendar.html?re... 4/27/2015 EXHIBIT "B" CERTIFICATE OF SUBSTANTIAL COMPLETION PROJECT: City of Port Arthur MONTROSE PARK PROJECT NO: 13049 ARCHITECT: The LaBiche Architectural Group, Inc. OWNER: City of Port Arthur CONTRACTOR: SeTEX Construction P.O. Box 1089 Port Arthur, Texas 77641 CONTRACT FOR: Renovations DATE OF ISSUANCE: May 07, 2015 CONTRACT DATE: November 06, 2014 PROJECT OR DESIGNATED PORTION SHALL INCLUDE: ALL WORK The Work performed under this Contract has been reviewed and found to be substantially complete. The Date of Substantial Completion of the Project or portion thereof designated above is hereby established as May 07, 2015 which is also the date of commencement of applicable warranties required by the Contract Documents, except as stated below. DEFINITION OF DATE OF SUBSTANTIAL COMPLETION The Date of Substantial Completion of the Work or designated portion thereof is the Date certified by the Architect when construction is sufficiently complete, in accordance with the Contract Documents, so the Owner can occupy or utilize the Work or designated portion thereof for the use for which it is intended, as expressed in the Contract Documents. A list of items to be completed or corrected, prepared by the Contractor and verified and amended by the Architect is attached hereto. The failure to include /�E D any items on such list does not alter the responsibility of the Contractor to complete Le to C� V'? t� all Work in accordance with the Contract Documents. The date of commencement off` �+ 0__ s m of warranties for items on the attached list will b- the .ate of final payment unless .o m otherwise agreed to in writing. c � !/ /f/ s 11592 The LaBiche Architectural Group, Inc. I,_� "*N,4 �-l. ARCHITECT - DA(TE , 0 F The Contractor will complete or correct the Work on e list of items attached hereto within fifteen (15) days from the Date of Substantial Completio . C SeTEX Construction ( • S I'S \'5 CONTRACTOR B DATE The Owner accepts the Work or designated portion thereof as substantially complete and will assume full possession thereof at 8:00 a.m. on May 08, 2015. City of Port Arthur OWNER BY DATE The responsibilities of the Owner and the Contractor for security, maintenance, heat, utilities, damage to the Work and insurance shall be as follows: Owner will assume responsibility for maintenance, security, and damage to the Work on the Date of Substantial Completion except for damage done by Contractor or Subcontractors during final completion. Owner assumes responsibility for insurance of the Project on May 08, 2015. The Contractor will submit to the Owner the executed warranties, maintenance agreements, inspection certificates, record documentation, maintenance manuals, tools, spare parts, keys and similar operational items by June 08, 2015. Dohn H. LaBiche, FAIA-Principal Greg Wall, AIA-Principal The LaBiche 7999 Gladys Avenue, Suite 101 Beaumont,Texas 77706 ARCHITECTURAL GROUP, INC. (409) 860-0197• Fax(409)860-0198 May 7, 2015 SETEX Construction, Inc. Mr. Nathan Rivers 1660 S. 23rd Street Beaumont, Texas 77707 Re: Montrose Park Project# 13049 Dear Mr. Rivers, On Thursday, April 2, 2015, an inspection was made of the above-mentioned project for the purpose of compiling a Punch List for Lion's Park prior to their Easter Egg Hunt. The following persons were in attendance during the inspection: Dohn LaBiche, FAIA LaBiche Architectural Group, Inc... Nathan Rivers & Danny Wood SETEX Construction, Inc. Thad Sanders, Harriet Collins ,Isaac , Dr. Albert Thigpen City of Port Arthur Punch List 1. Remove the site sign, security fence, Port-o-let and other contractor materials. 2. Install hydro sod in areas used for staging by the contractor. 3. Kill weeds growing thru new basketball court finish. 4. Remove construction equipment and debris from site. 5. Provide City with tools required to maintain new playgrounds (Sabine Pass) as discussed during the pre-construction conference. 6. Add solid sod at basketball courts to the specified distance away from all new sidewalks. 7. Remove graffiti from new light pole at basketball court. End of Punch List Please correct the above-mentioned item of work by the earliest possible date and notify our office in writing upon their completion. We have established, May 7, 2015 as the Substantial Completion date. 1 of 2 Punch List for Montrose Park Also please submit the required Close-out Documents and Warranties along with Record Drawings and Specifications for approval and transmittal to the owner. If there are questions about any of the items listed please notify my office for clarifications. Sincerely, Dohn H. LaBiche, FAIA 2 of 2 EXHIBIT "C" CERTIFICATE OF SUBSTANTIAL COMPLETION PROJECT: City of Port Arthur LION'S PARK PROJECT NO: 13049 ARCHITECT: The LaBiche Architectural Group, Inc. OWNER: City of Port Arthur CONTRACTOR: SeTEX Construction P.O. Box 1089 Port Arthur, Texas 77641 CONTRACT FOR: Renovations DATE OF ISSUANCE: April 02, 2015 CONTRACT DATE: November 06, 2014 PROJECT OR DESIGNATED PORTION SHALL INCLUDE: ALL WORK The Work performed under this Contract has been reviewed and found to be substantially complete. The Date of Substantial Completion of the Project or portion thereof designated above is hereby established as April 02, 2015 which is also the date of commencement of applicable warranties required by the Contract Documents, except as stated below. DEFINITION OF DATE OF SUBSTANTIAL COMPLETION The Date of Substantial Completion of the Work or designated portion thereof is the Date certified by the Architect when construction is sufficiently complete, in accordance with the Contract Documents, so the Owner can occupy or utilize the Work or designated portion thereof for the use for which it is intended, as expressed in the Contract Documents. A list of items to be completed or corrected, prepared by the Contractor andv verified and amended by the Architect is attached hereto. The failure to include E D ,4,4?1,14 any items on such list does not alter the responsibility of the Contractor to complete _•I µ C,3,00! 'S' if all Work in accordance with the Contract Docu ent . The date of commencement i-'-o�`� , e�C�'�, of warranties for items on the attached list will let e,d. e of final payment unless °w•o m;o •otherwise agreed to in writing. / r $ The LaBiche Architectural Group, Inc. / / , � X44- '` �+��~ ARCHITECT ' B DA E 1F OFlek The Contractor will complete or correct the Work o the list of items attached hereto within fifteen (15) days from the Date of Substantial Completio CC SeTEX Construction � ��J CONTRACTOR BY DATE The Owner accepts the Work or designated portion thereof as substantially complete and will assume full possession thereof at 8:00 a.m. on April 03, 2015. City of Port Arthur OWNER BY DATE The responsibilities of the Owner and the Contractor for security, maintenance, heat, utilities, damage to the Work and insurance shall be as follows: Owner will assume responsibility for maintenance, security, and damage to the Work on the Date of Substantial Completion except for damage done by Contractor or Subcontractors during final completion. Owner assumes responsibility for insurance of the Project on • • April 03, 2015. The Contractor will submit to the Owner the executed warranties, maintenance agreements, inspection certificates, record documentation, maintenance manuals, tools, spare parts, keys and similar operational items by May 03, 2015. ,.,itr Dohn H.LaBiche,FAIA-Principal Greg Wall,AIA-Principal The LaBiche 7999 Gladys Avenue, Suite 101 Beaumont,Texas 77706 I ARCHITECTURAL GROUP, INC. (409) 860-0197 • Fax(409) 860-0198 April 2, 2015 SETEX Construction, Inc. Mr. Nathan Rivers 1660 S. 23rd Street Beaumont, Texas 77707 Re: Lion's Park Project# 13049 Dear Mr. Rivers, On Thursday, April 2, 2015, an inspection was made of the above-mentioned project for the purpose of compiling a Punch List for Lion's Park prior to their Easter Egg Hunt. The following persons were in attendance during the inspection: Dohn LaBiche, FAIA LaBiche Architectural Group, Inc.. Nathan Rivers & Danny Wood SETEX Construction, Inc. Punch List 1. Remove the security Fence and Port-o-let. 2. Install sod in areas surrounding playground. 3. Install bond breaker tape in construction joints prior to installing sealant. 4. Remove construction equipment and debris from site. 5. Clean site and playground equipment. End of Punch List Please correct the above-mentioned item of work by the earliest possible date and notify our office in writing upon their completion. We have established, March 23, 2015 as the Substantial Completion date. Also please submit the required Close-out Documents and Warranties along with Record Drawings and Specifications for approval and transmittal to the owner. If there are questions about any of the items listed please notify my office for clarifications. Sincerely, Dohn H. LaBiche, FAIA 1 of 1