INTEROFFICE MEMORANDUM
UTILITY OPERATIONS DEPARTMENT-ADMINISTRATION
Date: October 07, 2015
To: Brian McDougal, City Manager
From: Jimmie Johnson,Ph.D.,Director of Utility Operations
RE: Proposed Resolution No. 19179
Nature of the Request:
The City Council awarded a contract for the construction of the 24”waterline from 19th Street
to the Sabine-Neches Canal ALLCO, L.L.C., in the amount of $3,114,960.00. Current
contract price adjusted by previous change orders is $3,518,973.40.
The project engineer, Arceneaux Wilson & Cole LLC, recommends Change Order No. 11 is
the final change order that will remove all items not used in the project. It is also to increase
bid item numbers 5, and 13 for additional pipe, and one (1) 4" air release valve with a
manhole for this project. This change order is a deductive change order in the amount of
$127,421.60, decreasing the total contract to $3,391,551.80.
Staff Analysis, Considerations:
Existing staff will monitor the contractor's performance.
Recommendation:
I recommend that the City Council approve Proposed Resolution No. 19179 authorizing the
City Manager to execute Change Order No. 11 to the contract between the City of Port Arthur
and ALLCO, L.L.C. of Beaumont, Texas, for the 24"waterline from 19th Street to the Sabine-
Neches Canal. This change order is a deductive change order in the amount of$127,421.60.
Budjiet Considerations:
Account No. 429-1258-532.59-00, Project No. WSI003
P. R. No. 19179
10/07/15 jt
RESOLUTION NO.
A RESOLUTION AUTHORIZING THE CITY MANAGER
TO EXECUTE CHANGE ORDER NO. 11 BETWEEN THE
CITY OF PORT ARTHUR AND ALLCO, L.L.C.; FOR
THE 24" WATERLINE FROM 19TH STREET TO THE
SABINE NECHES CANAL FOR THE REMOVAL OF
ITEMS NOT USED DECREASING THE TOTAL
CONTRACT AMOUNT BY $127,421.60 TO A NEW
CONTRACT AMOUNT OF $3,391,551.80.
WHEREAS, per Resolution No. 13-503, the City entered into a contract for the
installation of a Waterline from 19th Street to the Sabine Neches Canal, in the amount of
$3,114,960.00, with a contract term of 365 calendar days; and
WHEREAS, per Resolution No. 14-210, Change Order 1 authorized an additional
$40,486.00 to add storm water pollution prevention measures required by the City of Port Arthur
that was not included in the original contract, bringing the contract price for the project to
$3,155,446.00 accepted by Allco; and
WHEREAS, per Resolution No. 14-300, Change Order 2 authorized a credit of
$21,980.00 for the use of 24" Certa-Loc restrained joint C900 PVC pipe in lieu of the 24"
cement lined restrained joint gasket ductile iron pipe in the original bid to a new contract total of
$3,133,466, and a time extension of six (6) days due to inclement weather bring the date of
completion to January 25, 2015; and
WHEREAS, per Resolution No. 14-342, Change Order 3 authorized an additional
$12,072.00 for the relocation of an existing 6" waterline that was discovered during construction
on Charleston Ave, the re-route of the 24" waterline to miss an existing storm sewer, and one
foot of extra cover added to the 24" waterline approx. 2,100 L.F. to ensure protection of the line
during the 18th Street construction project to a new contract total of$3,145,538.00, and a time
P. R. No. 19179
10/07/15jt
Page 2 of 4
extension of six (6) days due to inclement weather, bringing the date of completion to January
31, 2015; and,
WHEREAS, per Resolution No. 14-389, Change Order 4, authorized a time extension
of 3 days due to weather delays,to a new completion date of February 3, 2015; and,
WHEREAS, per Resolution No. 14-449, Change Order 5, authorized the relocation of
the proposed 24" waterline to avoid an existing structure at the intersection of 18th Street and
Railroad Ave. in the amount not to exceed $53,100.00 to a new contract total of$3,198,638.00
and a time extension of three (3) days due to inclement weather bringing the date of completion
to February 6, 2015; and,
WHEREAS, per Resolution No. 14-554, Change Order 6, authorized the relocation of an
existing 12" waterline at Railroad Ave. in the amount not to exceed $52,659.00, and a time
extension of eight(8) days due to inclement weather; and,
WHEREAS, per Resolution No. 14-607, Change Order 7, authorized the performing a
20-inch hot tap on an existing 20-inch waterline on Atlanta Street and an additional 250 feet of
30-inch, DR-11 HDPE of directional drilling in an amount not to exceed 5141,090.00, and a time
extension of four(4) days due to inclement weather; and,
WHEREAS,per Resolution No. 14-645, Change Order 8, authorized a time extension of
four (4) days due to weather delays to a new contract time of 399 days and a contract price
increase of $53,614.40 for additional HDPE footage needed to clear the existing underground
structure that was unknown; and,
WHEREAS, per Resolution No. 15-076, Change Order No. 9 authorized a time
extension of thirty (30) days for a new contract time of 429 days with a new completion
P. R. No. 19179
10/07/15jt
Page 3 of 4
date of March 24, 2015, and increased the contract price to $3,518,973.40 for the installation of
two 24" tees, 24" valves, foster adapters and solid sleeves to serve the proposed Terminal Road
Elevated Storage Tank project. This change order allowed there to be water service available for
the supply water to the proposed storage tank once it is constructed. In addition this change order
removed and replaced an existing fence along Terminal Road in order to install the proposed 24"
waterline; and,
WHEREAS, per Resolution No. 15-132, Change Order No. 10 a time extension of eight
(8) days due to weather delays,to a new completion date of April 1, 2015: and,
WHEREAS, Arceneaux Wilson & Cole LLC, has requested and recommended the final
Change Order No. 11 that will remove all items not used in the project. It is also to increase bid
item numbers 5, and 13 for additional pipe, and one (1)4" air release valve with a manhole. This
change order is a deductive change order in the amount of $127,421.60, decreasing the total
contract to $3,391,551.80, attached as Exhibit"A".
NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE
CITY OF PORT ARTHUR:
THAT, the City Manager of the City of Port Arthur is hereby authorized and directed to
execute, on behalf of the City of Port Arthur, Change Order No. 11 between the City of Port
Arthur and Allco L.L.C., for the removal of all items not used in the project. It is also to increase
bid item numbers 5, and 13 for additional pipe, and one (1) 4" air release valve with a manhole.
This change order is a deductive change order in the amount of$127,421.60, decreasing the total
contract to $3,391,551.80, attached hereto as Exhibit"A"; and,
THAT a copy of the caption of this resolution be spread upon the minutes of the City
Council.
P. R. No. 19179
10/07/15jt
Page 4 of 4
READ, ADOPTED AND APPROVED THIS day of , 2015
at a Regular Meeting of the City Council of the City of Port Arthur, Texas, by the following
vote: AYES:
Mayor
Councilmembers:
•
NOES:
Deloris Prince
Mayor
ATTEST: APPRO ED AS TO FORM:
Sherri Bellard Valeci./Tizeno
City Secretary City Attorney
APPROVED FOR ADMINISTRATION:
i Lute
Brian McDougal Clifton Williams, CPPB
City Manager Acting Purchasing Manager
Jimmie Johnson, Ph.D.
Director of Utility Operations
APPROVED AS TO AVAILABILITY OF FUNDS:
Jerry Dare,—CPA/CGFO
Interim Director of Finance
Exhibit "A"
(AW&C Change Order No.11)
ARCENEAUX WILSON & COLE LLC
Arc wiaon 6 Cola- - -AWC Engineering • Surveying • Planning
September 23, 2015
Dr. Jimmie Johnson
Director of Water Utilities
City of Port Arthur
444 Fourth Street
Port Arthur, Texas 77640
RE; PROPOSAL FOR CHANGE ORDER NO. 11
24"WATERLINE FROM 19TH STREET TO THE SABINE-NECHES CANAL
Job No. CPA-650
Dear Mr. Johnson:
Attached is Change Order No. 11 for the 24" Waterline from 19th Street to the Sabine-Neches
Canal. This change order is the final change order for the 24" Waterline from 19th Street to the
Sabine-Neches Canal that will add additional items and remove all items not used in the project.
Change Order No. 11 will be a deductive change order in the amount of $127,421.60. I have
attached Change Order No. 11 which modifies the contract to reflect this change for your
consideration and action. Should you have any questions or require additional information,
please contact our office.
Very truly yours,
Arceneaux Wilson & Cole LLC
TEXAS REGISTERED ENGINEERING FIRM F-16194
Keestan Cole, PE
Vice-President
(409) 724-7888 • 2901 Turtle Creek Drive • Suite 320 • Port Arthur, Texas 77642
www.awceng.com
AWC
CHANGE ORDER No. 11
DATE: September 14, 2015 JOB NO. CPA-650
AGREEMENT DATE: November 5, 2013
NAME OF PROJECT: 24" Waterline from 19th Street to the Sabine-Neches Canal
OWNER: CITY of PORT ARTHUR
CONTRACTOR: ALLCO
The following changes are hereby made to the CONTRACT DOCUMENTS:
1. Add the following Items to the Contract and Scope of Work:
a. Increase 280 L.F., 24" C-905 PVC
(Bid Item No. 5/$109.00 L.F.) [+] $ 30,520.00
b. Increase 1 Ea., 4"Air Release w/Manhole
(Bid Item No. 13/$6,700.00) [+] $ 6,700.00
c. Decrease 10 L.F., 20" C-905 PVC
(Bid Item No. 7/$195.00) [-] $ 1,950.00
d. Decrease 1 Ea., 20" Gate Valve and Box
(Bid Item No. 8/$14,200.00) [-] $ 14,200.00
e. Decrease 1 Ea., Design of Trench Safety System
(Bid Item No. 15/$500.00) [-] $ 500.00
f. Decrease 500 Lb., Extra Reinforcing
(Bid Item No. 19/$0.75) [-] $ 375.00
g. Decrease 10 C.Y., Extra Class "A" Concrete
(Bid Item No. 20/$150.00) [-] $ 1,500.00
h. Decrease 10 C.Y., Extra Cement Stabilized Sand
(Bid Item No. 21/$500.00) [-] $ 400.00
i. Decrease 1470.60 L.F., Well Point
(Bid Item No. 22/$30.00) [-] $ 44,118.00
j. Decrease 2 Ea., 12" Gate Valve and Box
(Bid Item No. 23/$2,500.00) [-] $ 5,000.00
CHANGE ORDER NO. 11
September 14, 2015
AWCJob No. CPA-650, Contract No. 1
k. Decrease 2 Ea., 12" Ductile Iron Tee
(Bid Item No. 24/$700.00) [-] $ 1,400.00
I. Decrease 3 Ea., 12" Compact Ductile Iron
900 Fitting
(Bid Item No. 25/$450.00) [-] $ ___ 1,350,00
m. Decrease 3 Ea., 12" Compact Ductile Iron
45° Fitting
(Bid Item No. 26/$400.00) [-] �_ 1,200.00
n. Decrease 2 Ea., 20" Gate Valve and Box
(Bid Item No. 27/$15,000.00) [-] $ 30,000.00
o. Decrease 2 Ea., 20" Ductile Iron Tee
(Bid Item No. 28/$1,500.00) [-] $ 3,000.00
p. Decrease 3 Ea., 20" Compact Ductile Iron
90° Fitting
(Bid Item No. 29/$1,200.00) [-] $ 3,600.00
q. Decrease 3 Ea., 20" Compact Ductile Iron
45° Fitting
(Bid Item No. 30/$1,000.00) [-] $ 3,000.00
r. Decrease 2 Ea., 24" Gate Valve and Box
(Bid Item No. 31/$19,000.00) [-] $ 38,000.00
s. Decrease 2 Ea., 24" Ductile Iron Tee
(Bid Item No. 32/$2,500.00) [-] $ 5,000.00
t. Decrease 3 Ea., 24" Compact Ductile Iron
90° Fitting
(Bid Item No. 33/$2,000.00) [-] $ 6,000.00
u. Decrease 0.10 L.S., Storm Water Pollution Prevention
(Bid Item No. 35/$40,486.00) [-] $ 4,048.60
TOTAL $ 127,421.60
2 of 3
CHANGE ORDER NO. 11
Arca noaux Wlison & Cole- - - ..
September 14, 2015
AWCJob No. CPA-650, Contract No. 1
CHANGE TO CONTRACT PRICE:
ORIGINAL CONTRACT PRICE: $3.114,960.00
CURRENT CONTRACT PRICE adjusted by previous CHANGE ORDER(S): $3,518,973.40
The CONTRACT PRICE due to this CHANGE ORDER will be fwd] [decreased]
by: $ 127,421.60 Dollars
The new CONTRACT PRICE, including this CHANGE ORDER,will be $ 3,391,551.80
CHANGE TO CONTRACT TIME:
ORIGINAL CONTRACT TIME: 365 Calendar Days
CURRENT CONTRACT TIME adjusted by previous CHANGE ORDER: 72 Calendar Days
CURRENT DATE OF COMPLETION: April 1.2015
CONTRACT TIME due to this CHANGE ORDER will be increased by 0 Days
The New DATE OF COMPLETION: April 1,2015
No other Terms and Conditions of the Contract are changed as a result of this Change Order.
Contractor's acceptance of Change Order relieves OWNER of any liability for additional costs
incurred by Contractor in his performance of the work covered by the Change Order.
RECOMMENDED BY ENGINEER: ACCEPTED BY:
e-s-17e
RCENEAUX WILSON & COLE LLC I NTRACTOR,OFFICEROROW R]
ALLCO
ACCEPTED BY:
CITY of PORT ARTHUR
3 of 3