RECOMMENDATION:
It is recommended that the City Council approve Proposed Resolution No. 11707
authorizing the Mayor and City Manager to execute Change Orders No. 1, 2, 3, 4, 5, 6
and Final to the contract dated July 24, 2001 between the City of Port Arthur and
SeTEX Construction Corporation of Beaumont, Texas for the construction of the
Boardwalk, Phase II increasing the contract amount by $6,893 from $280,000 to a new
contract total of $286,893, authorizing the City Manager to execute a Certificate of
Acceptance for the work and authorizing final payment of $14,344.65 from FY2002
Budget Account No. 301-1601-591.89-00, ClP 101.
BACKGROUND:
Advertisements for Bids were published on June 17, 2001 and June 24, 2001, with the
contract being awarded to SeTEX Construction Corporation on July 24, 2001 in the
amount of $280,000 for the Base Bid only.
Change Order No. 1 has been issued for a time extension of six (6) days for the month
of August, 2001 for lost work days due to rain, for a new completion date of December
6, 2001.
Change Order No. 2 has been issued for planter irrigation additions, for a total increase
of $617 for a new contract amount of $280,671.
Change Order No. 3 has been issued for a time extension of 4 days for lost work days
due to rain, for a new completion date of December 10, 2001.
Change Order No. 4 has been issued for the pressure washing and application of one
(1) coat of ICl deck stain at the existing Boardwalk Phase I deck area, for a total
increase of $3,927 for a new contract amount of $284,598.
Change Order No. 5 has been issued for a time extension of 14 days for lost work days
due to rain, for a new completion date of December 24, 2001.
Change Order No. 6 has been issued for Boardwalk Phase I lamp replacement (to
match lamps on Phase II) and investigation of planter No. 2 on Boardwalk Phase I in
order to locate and repair water leak under planter box, for a total increase of, for a total
increase of $2,295 for a new contract amount of $286,893.
P.R. No. 11707
Page #2
A Certificate of Substantial Completion was issued on January 14, 2002 and the
boardwalk has been useable since that time, and no additional funds haye been
expended as a result of the contract time overruns. ~
The project is now complete, SeTEX has submitted its Final Pay request in the amount
of $14,344.65.
BUDGETARY/FISCAL EFFECT:
Funding is available in FY 2002 Account No. 301-1601-591.89-00, ClP 101.
EMPLOYEE/STAFF EFFECT:
Acceptance of this recommendation will have no effect on staffing levels at this time.
SUMMARY:
It is recommended that the City Council approve Proposed Resolution No. 11707
authorizing the Mayor and City Manager to execute Change Orders No. 1, 2, 3, 4, 5, 6
and Final to the contract dated July 24, 2001 between the City of Port Arthur and
SeTEX Construction Corporation of Beaumont, Texas for the construction of the
Boardwalk, Phase II increasing the contract amount by $6,893 from $280,000 to a new
contract total of $286,893, authorizing the City Manager to execute a Certificate of
Acceptance for the work and authorizing final payment of $14,344.65. Funding is
available in the FY 2002 Budget Account No. 301-1601-591.89-00, CIP 101.
Leslie E. McMahen, P.E.
Director of Public Works
LEM/vkl
c:~word~cams~setexbwiicJoseout
P.R. No. 11707
03/25/02-vkl
RESOLUTION NO.
A RESOLUTION AUTHORIZING THE MAYOR AND CITY MANAGER
TO EXECUTE CHANGE ORDERS NO. 1, 2, 3, 4, $, 6 AND FINAL TO
THE CONTRACT DATED JULY 24, 2001 BETWEEN THE CITY OF
PORT ARTHUR AND SETEX CONSTRUCTION CORPORATION OF
BEAUMONT, TEXAS FOR THE CONSTRUCTION OF THE
BOARDWALK PHASE II, INCREASING THE CONTRACT AMOUNT
BY $6,893 FROM $280,000 TO A NEW CONTRACT TOTAL OF
$286,893, AUTHORIZING THE CITY MANAGER TO EXECUTE A
CERTIFICATE OF ACCEPTANCE FOR THE WORK AND
AUTHORIZING FINAL PAYMENT OF $14,344.65; FUNDING BEING
AVAILABLE IN FY 2002 ACCOUNT NO. 301-1601-691.89-00, CIP
NO. 101.
WHEREAS, The LaBiche Architectural Group, Inc., has issued a Certificate of
Substantial Completion stating that construction of the Boardwalk Phase II has been
completed, copy attached hereto and made a part hereof as Exhibit "A", together with the
Contractor's Certificate and Release, copy attached and made a part hereof as Exhibit "B",
and Contractor's Certificate of Guarantee, copy attached and made a part hereof as
Exhibit "C", both having been executed on behalf of SeTEX Construction Corporation by
James R. Shell, President; and,
WHEREAS, the original Contract amount was $280,000; and,
WHEREAS, Change Order No. 1 dated September 7, 2001 increased the contract time
by six (6) days, Change Order No. 2 dated September 14, 2001 increased the contract
amount by $671, Change Order No. 3 dated October 10, 2001 increased the contract time
by four (4) days, Change Order No. 4 dated November 2, 2001 increased the contract
amount by $3,927, Change Order No. 5 dated January 2, 2002 increased the contract time
P.R. No. 11707
Page//2
by fourteen (14) days and Change Order No. 6 and Final increased the contract amount
by $2,295, copies of all Change Orders being attached hereto and made a part hbreof as
Exhibit "D"; and,
WHEREAS, the date of Substantial Completion for the work was January 14, 2002;
and,
WHEREAS, construction under said Contract is now complete; now, therefore,
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF PORT ARTHUR:
THAT the City Manager be and he is hereby authorized to execute Change Orders No.
1, 2, 3, 4, 5, 6 and Final which collectively increased the original contract amount of
$280,000 by $6,893 to the final contract amount of $286,893, and increased the contract
completion date by twenty-four (24) days to a new completion date of December 24, 2001,
as outlined in detail in said Change Orders; and,
THAT the City Manager be and he is hereby authorized to execute on behalf of the
City of Port Arthur a Certificate of Acceptance for the construction of the Boardwalk Phase
II in the City of Port Arthur, attached hereto and made a part hereof as Exhibit "E"; and,
THAT the Substantial Completion date being January 14, 2002; and,
THAT the Final Contract Amount for the subject contract is $286,893; and,
THAT Invoice No. 8 and Final in the amount of $14,344.65 from the Contractor be and
is hereby approved; copy attached hereto as Exhibit "F"; and
THAT a copy of this Resolution be s~nt to the Contractor along with the check in
FINAL payment; and,
P.R. No. 11707
Page #3
THAT a copy of the caption of this Resolution be spread upon the Minutes of the City
Council.
READ, ADOPTED, AND APPROVED this day of.
A.D., 2002, at a Meeting of the City Council of the City of Port Arthur,
Texas, by the following vote: AYES: Mayor
Coucilmembers
NOES:
ATTEST:
Acting City Secretary
APPROVED AS TO FORM:
City Attorney
APPROVED FOR ADMINIST~.~TION:
Leslie E. McMahen, P.E.
Director of Public Works
~ROVED A'~- .O AVAILAB, J,LITY OF FUNDS:
Finance Director
file c:~res~setexbwllcloseout
Mayor
CERTIFICATE OF SUBSTANTIAL COMPLETION E)~hibit'A"
P.R. No, 11707
t nfl
PROJECT: City of Port Arthur Boardwalk, Phase II
TO: City of Port Arthur
P. O. Box 1089
Port Arthur, Texas 77641-1089
DATE OF ISSUANCE: January 14, 2002
ARCHITECT: The LaBiche Architectural
Group, Inc.
PROJECT NO: 00020
CONTRACTOR: SeTEX CONSTRUCTION
CORP.
CONTRACT FOR: New Constrdction
CONTRACT DATE: July 24, 2001
PROJECT OR DESIGNATED PORTION SHALL INCLUDE: ALL WORK
The Work performed under this Contract has been reviewed and found to be substantially complete.
The Date of Substantial Completion of the Project or portion thereof designated above is hereby
established as January 14, 2002 which is also the date of commencement of applicable warranties
required by the Contract documents, except as stated below.
DEFINITION OF DATE OF SUBSTANTIAL COMPLETION
The date of Substantial Completion of the Work or designated portion thereof is the Date certified by
the Architect when construction is sufficiently complete, in accordance with the Contract Documents, so
the Owner can occupy or utilize the Work or designated portion thereof for the use for which it is
intended, as expressed in the Contract Documents.
A list of items to be completed or corrected, prepared by the Contractor and verified and amended by
the Architect, is attached hereto. The failure to include any items on such list does not alter the
responsibility of the Contractor to complete all Wo.r-k in accordance with the Contract Documents The
date of commencement of warranties for items/~,~ t,h'~a,c/oe~ st will be the date of final payment
unless o the rwise ag reed to in writing.
The LaBiche Architectural Group, Inc. ~////'~///'/~'~.~. ///7,~ ?.
ARCHITECT "By/ ' DA~'E
The Contractor will complete or correct the Wor.l~ the list of items attached hereto within fifteen (15)
days from the Date of Substantial Completion.//
t~
The Owner accepts the Work or'cr~signated portion thereof as substantially complete and will assume
full possession thereof at 8:00 a.m. on January 15, 2002.
OWNER '~" ' BY , 3~ 77-
DATE
The responsibilities of the Owner and the Contractor for security, maintenance, heat, utilities, damage to the Work
and insurance shall be as follows: Owner will assume r~sponsibility for maintenance, security, and damage to the
Work on the Date of Substantial Completion except for damage done by Contractor or Subcontractors during final
completion. Owner assumes responsibility for iesurance of the Project on January 15, 2002. The Contractor will
submit to the Owner the executed warranties, maintenance agreements, inspection certificates, record
documentation, maintenance manuals, tools, spare parts, keys and similar operational items by February 15,
2002.
CONTRACTOR'S AFFIDAVIT OF
RELEASE OF LIENS
AIA /)oct/me/t/ G7()6A
Exhibit'B'
OWNER P.R. No: 11707 []
ARC I II'I'I':CI' I of 2 [-I
CONTRACTOR ~-J
SURI'.'TY []
OTI IF.I{ I~
TO OWNI{I{:
City of Port Arthur
P. O. Box 1089
Port Arthur, Texas
I'RQJ EC'I':
Boardwalk - Phase II
Port Arthur, Texas
77641-1089
ARCHI'I'HCI"S PR~IiCI' NO.:
00020
CONTRACT FOR:
New Construction - Boardwalk Phase
CONTRACI' DATED:
July 24, 2001
II
STATE OF: Texas
COUNTY OF: Jefferson
I{XCI':PTIONS:
NONE
SUIH~ORTING I)OCt IMENTS ATI'ACI lED I ll!Rl'71'O:
rcquirc(I by thc Owner, ;Ic(.'on~p;inicd by a list thcrc()£.
CONTIOXCI'OR: SeTEX Construction Corp.
,,v,,,,,,.,,,,,/,,,~a,,.~. P. O. Box 20678
. ~aumont, Texas 77720-0678
/
ii MvCl,m, ss nl'.'xpircs: April 2, 2002
CAUIION: You should sign an original AIA document that has this caulion prinled in red. An
original assures that changes will not be obscured as may occur when documents are reproduced.
See Instruction Sheet for Limited License for Reproduction of this document.
G70GA--19q4
CONTRACTOR'S AFFIDAVIT OF
PAYMENT OF DEBTS AND" CLAIMS
AlA I)oct/meul G706
(Instructions on r,evc~o side)
OWNER Exhibit 'B'
P.R. No. 11707
ARCHI']'ECT 2 of 2
CONTI~CTOR
SURN1Y
OTHER
[]
[]
TO OWN F.R:
City of BortArthur
P. O. Box 1089
Port Arthur, Texas
PROJ F. CT:
Boardwalk Phase II
Port Arthur, Texas
77641-1089
ARCHI]~CT'SPR~E~'NO.:
00020
CONTRACTFOR:
New Construction _
CONTRACTDATED:
July 24, 2001
Boardwhlk Phase II
S'IWI'E OF: Texas
COUNTY OF: Jefferson
EXCEPTIONS:
BRC Painting
Gulf Coast Electric
Lawn Specialties, Inc.
Total Retainage Owed
SUPPORTING I)OCIIMENTS A'ITACHED HEILETO:
1. Consenl of .";urcb, to Final Payment. Whenevel' Surety is
71,t'./bllou.iltk, stq¥)ortin;4 doclt;nents shot/Id be al/ached hereto
~/'reqldred I~1' the Ouvle17
rcquirud by thc Ownc.. cc mq~anicd by u list there(ff.
~ 852.00
1,600.00
991.50
$3,443.50
CONTRACTOR:
BY:
SeTEX Construction Corp.
P. O. Box 20678
Beaumont, Texas 77720-0678
a~s R. Shell, President
,,,,,..,
i{ MvCommission Expires- April 2, 2002
CAUTION: You should sign an original AIA document that has this caution printed in red. An
original assures that changes will not be obscured as may occur when documents are reproduced,
See Instruction Sheet for Limited License for Reproduction of this document.
G706--1994
CON UO iON
CORP.
Exhibit 'C"
P.R. No. 1170g:ommercial
I o[1 Municipal
PROJECT WARRANTY FOR GENERAL CONSTRUCTION
Whereas, SeTEX Construction Corp., P.O. Box 20678, Beaumont, Texas 77720-0678,
409-842-8181, has performed general construction work on the following project:
Boardwalk Phase H
City of Port Arthur- Port Arthur~ Texas
Whereas, Contractor warrants to the Owner and Architect that materials and equipment furnished
under the Contract will be of good quality and new, unless otherwise required or permitted by the
Contract Documents, that the work will be free from defects not inherent in the quality required
or permitted, and that the work will conform to the requirements of the Contmct Documents.
Now therefore, Contractor hereby warrants said work in accordance with the terms hereof,
complying with terms of Contract with Owner dated July 24~ 2001 that:
Contractor agrees to repair or replace to the satisfaction of the Arehitect all work that may prove
defective in workmanship or materials together with all other work which may be damaged or
displaced in so doing: abuse, modifications not executed by Contractor, insufficient maintenance,
improper operation, or normal wear and tear under normal usage excepted.
All repairs or replacements shall have a correction period for nonconforming work equal to the
original correction period for nonconforming work as herein stated, dated from the final
acceptance of repaim or replacement. Nothing contained in this paragraph shall be construed to
establish a period of limitation with respect to other obligations which the Contractor might have
under the Contract Documents.
THE NONCONFORMING WORK CORRECTION PERIOD IS ONE (1) YEAR,
STARTING JANUARY 14~ 2002 THROUGH ,[ANUARY 14~ 2003.
In the event of our failure to comply with the above mentioned conditions within a reasonable
time after being notified by writing, we hereby authorize the Owner to proceed with having
defects repaired and made good at our expense, and will pay the costs and charges promptly upon
demand.
In witness thereof, this instrument has been duly executed this 24'h day,~Januar¥ for Contractor
by:
,
.... . ..
My Commission Expires: April 2, 2002
P.O. BOX 20678 ., BEAUMONT, TX 77720-0678 · OFFICE: (40§) 842-8181 · FAX: {409) 842-2274
Exhibit'D'
P.R. No. 11707
1 of 6
CHANGE ORDER
PROJECT:
CONTRACTOR:
Boardwalk Phase II
City of Port Arthur, Texas
SeTEX CONSTRUCTION CORP.
P. O. Box 20678
Beaumont, Texas 77720-0678
The Contract is changed as follows:
1. Extention of Time for the month of August 2001
CHANGE ORDERNO:
DATE:
ARCHITECT'S PROJECT
NO.:
CONTRACT DATE:
CONTRACT FOR:
1
09-07-01
00020
Extention of Time
Add 6 Days
TOTAL: 123 Days
**See attached breakdown
Not valid until signed by the Owner, Architect, and Contractor.
The original Contract Sum was ........................................................................................................ $280,000.00
Net change by prev ous y au hor zed Change Orders ..................................................................................................... $ 0.00
The Contract Sum prior to this Change Order was ................................................................................................ $280,000.00
The Contract sum will be increased by this Change Order in the amount of ................................................................... $0.00
The new Contract Sum including this Change Order will be .................................................................................. $280,000.00
The Contract Time will be increased by six (6) days.
The date of Substantial Completion as of the date of this Change Order therefore is December 6, 2001.
NOTE: The summary does not reflect changes in the Contract Sum or Contract Time which have been authorized by Construction
Change Directive.
The LaBiche Architectural Group
7999 Gladys Avenue Suit~ 1Q,1
SeTEX CONST[~I~TJON CORP. City of Port Arthur
P. O. Box 206/7'8/ P.O. Box 1089
Bea~ 77720-0678 Port Arthur, Texas 77641~,-1089
Date:
CHANGE ORDER
Exhibit'D'
P.R. No. 11707
2of6
PROJECT:
CONTRACTOR:
Boardwalk Phase II
City of Port Arthur, Texas
SeTEX CONSTRUCTION CORP.
P. O. Box 20678
Beaumont, Texas 77720-0678
The Contract is changed as follows:
I. Planter Irrigation Additions
CHANGE ORDERNO:
DATE:
ARCHITECT'S PROJECT
NO.:
CONTRACT DATE:
CONTRACT FOR:
Add'
2
09-14-01
00020
Additions
$671.00
TOTAL:
$671.00
**See attached breakdown
Not valid until signed by the Owner, Architect, and Contractor.
The original Contract Sum was .............................................................................................................................. $280,000.00
Net change by previously authorized Change Orders ..................................................................................................... $ 0.00
The Contract Sum prior to this Change Order was ................................................................................................ $280,000.00
The Contract sum will be increased by this Change Order in the amount of ............................................................... $671.00
The new Contract Sum including this Change Order will be .................................................................................. $280,671.00
The Contract Time will be increased by six (6) days.
The date of Substantial Completion as of the date of this Change Order therefore is Decereber 6, 2001.
NOTE: The suremary does not reflect changes in the Contract Sum or Contract Time which have been authorized by Construction
Change Directive.
The LaBiche Architectural Group
SeTEX CONSTRUCTION CORP.
City of Port Arthur
P.O. Box 1089
Port Arthur, Texas 77641-1089
Date: ~ ~i Date:
9/27/01
~--'~* Exhibit 'D'
~' P.R. No. 11707
3of6
CHANGE ORDER
PROJECT:
CONTRACTOR:
Boardwalk Phasell
Ci~ ofPo~ A~hur, Texas
SeTEX CONSTRUCTION CORP.
P. O. Box 20678
Beaumont, Texas 77720~0678
The Contract is changed as follows:
1. Extension of 4 Days Time
CHANGE ORDER NO: 3
DATE: 10-10-0!
ARCHITECT'S PROJECT NO.: 00020
CONTRACT DATE: 07-24-01
CONTRACT FOR: New Construction
Add 4 Days
TOTAL 127 Days
**See attached breakdown
Not valid until signed by the Owner, Architect, and Contractor.
The original Contract Sum was .......................................................................................................................................... $280,000.00
Net change by previously authorized Change Orders .............................................................................................................. $671.00
The Contract Sum prior to this Change Order was ............................................................................................................ $280,671.00
The Contract sum will be increased by this Change Order in the amount of .................................................................................. $00
The new Contract Sum including this Change Order will be .............................................................................................. $280,671.00
The Contract Time will be increased by four (4) days.
The date of Substantial Completion as of the date of this Change Order therefore is December 10, 2001.
NOTE: The summa~' does not reflect changes in the Contract Sum or Contract Time which have been authorized by Construction
Change Directive.
The LaBiche Architectural Group SeTEX CONSTRUCTION CORP. Cib/of Port Adhur
7999 Gladys Avenue, ,~it,e 10/1~ P.O. Box 20678 P.O. Box 1089
Beaum~,~?~~. Beaumont, T~_ 77720-0678 ,. Port Arthur, Texas 77641-1089
CHANGE ORDER
E~ibit 'D'
P.R. No. 11707
4of6
PROJECT:
CONTRACTOR:
Boardwalk Phase II
City of Port Arthur, Texas
SeTEX CONSTRUCTION CORP.
P. O. Box 20678
Beaumont, Texas 77720-0678
The Contract is changed as follows:
1. BRC Painting
CHANGE ORDER NO:
DATE:
ARCHITECT'S PROJECT NO.:
CONTRACT DATE:
CONTRACT FOR:
4
11-02-01
00020
07-24-01
New Construction
Add $3,927.00
TOTAL $3,927.00
**See attached breakdown
Not valid until signed by the Owner, Architect, and Contractor.
The original Contract Sum was .......................................................................................................................................... $280,000.00
Net change by previously authorized Change Orders .............................................................................................................. $671.00
The Contract Sum prior to this Change Order was ............................................................................................................ $280,671.00
The Contract sum will be increased by this Change Order in the amount of ........................................................................ $3,927.00
The new Contract Sum including this Change Order will be .............................................................................................. $284,598.00
The Contract Time will be increased by four (4) days.
The date of Substantial Completion as of the date of this Change Order therafora is December 10, 2001.
NOTE: The summary does not reflect changes in the Contract Sum or Contract Time which have been authorized by Construction
Change Directive.
The LaBiche Architectural Group
By: ~
Date:
SeTEX CONSTI~CTION CORP.
P. O. Box 206.,7,~ /
City of Port Arthur
P.O. Box 1089
Port Arthur, Texas 77641-1089
Date: 11-15-01
Exhibit 'D'
P.R. No. 11707
5of6
CHANGE ORDER
PROJECT: Boardwalk Phase II CHANGE ORDER NO: 5
City of Port Arthur, Texas
CONTRACTOR: SeTEX CONSTRUCTION CORP. DATE: 01-02-02
P. O. Box 20678
Beaumont, Texas 77720-0678
ARCHITECT'S PROJECT NO.:
CONTRACT DATE:
CONTRACT FOR:
The Contract is changed as follows:
1. Extension of Time Request
00020
07-24-01
New Construction
Add 14 Days
**See attached breakdown
Not valid until signed by the Owner, Architect, and Contractor.
The original Contract Sum was .......................................................................................................................................... $280,000.00
Net change by previously authorized Change Orders ........................................................................................................... $4,598.00
The Contract Sum prior to this Change Order was ............................................................................................................ $284,598.00
The Contract sum will be increased by this Change Order in the amount of .................................................................................. $00
The new Contract Sum including this Change Order will be .............................................................................................. $284,598.00
The Contract Time will be increased by foudeen (14) days.
The date of Substantial Completion as of the date of this Change Order therefore is December 24, 2001.
NOTE: The summary does not reflect changes in the Contract Sum or Contract Time which have been authorized by Construction
Change Directive.
The LaBiche Architectural Group
7999
Beaumont
By:
SeTEX CONSTRUCTION CORP.
P. O. Box 20678
Date:
Gladys. Avenue/Sui~e 101.
'nont,.,'~X ~77J,0~ ' ,/,~/~ Beaumont, T.e~as 77720-0678
/
City of Port Arthur
P.O. Box 1089
Port Arthur, Texas 77641-1089
Date:_
Exhibit 'D'
P.R. No. 11707
6of6
CHANGE ORDER
PROJECT:
CONTRACTOR:
Boardwalk Phase II
City of Port Arthur, Texas
SeTEX CONSTRUCTION CORP.
P. O. Box 20678
Beaumont, Texas 77720-0678
The Contract is changed as follows:
1. Boardwalk Phase I Lamp Replacement
2. Boardwalk Phase 1 Planter No. 2
CHANGE ORDERNO:
DATE:
ARCHITECT'S PROJECT NO.:
CONTRACTDATE:
CONTRACT FOR:
6
02-15-02
00020
07-24-01
New Construction
Add $375.OO
Add $1,920.00
TOTAL $2,295.00
**See attached breakdown
Not valid until signed by the Owner, Architect, and Contractor.
The odginal Contract Sum was ........................................................ i ....................................................................... $280,000.00
Net change by previously authorized Change Orders ......................................................................................................... $4,598.00
The Contract Sum pr or to th s Change Order was ............................................................................................................ $284,598.00
The Contract sum will be increased by this Change Order in the amount of ........................................................................ $2,295.00
The new Contract Sum including this Change Order will be .............................................................................................. $286,893.00
73.00
The Contract Time will be increased by fourteen (14) days·
The date of Substantial Completion as of the date of this Change Order therefore is December 24, 2001.
NOTE: The summary does not reflect changes in the Contract Sum or Contract Time wh ch have been authorized by Construction
Change Directive. · .,~_.,.,,.~ ,r".
The LaBiche Architectural Group SeTEX CONSTRUCTION CORP. City of Port Arthur
P.O. Box 1089
Port Arthur, Texas 77641-1089
7999 Gladys Avenue, Suite :101 P.O. Box 20678 ~,
By: By:
/ - ~.~, ..: :3~ / ~ ~
~/ ~. ¢~,~ .~ ~ __ Date:
Exhibit 'E'
P.R. No. 11707
1 of 1
CERTIFICATE OF ACCEPTANCE
FOR
THECONSTRUCTION OFTHE
BOARDWALK PHASEII
IN THE
ClTY OFPORTARTHUR
TO:
James R. Shell, President
SeTEX Construction Corporation
Dear Mr. Shell:
This is to certify that the City of Port Arthur, Texas, accepts the construction of the
Boardwalk Phase II south of City Hall in the City of Port Arthur as being completed on the
basis of the Certificate of Completion.
Steve Fitzgibbons
City Manager