HomeMy WebLinkAboutPR 19180: CHANGE ORDER NO. 1, PHASE III , SIEMENS INDUSTRY INC. Energy
City of City W. P.R. No. 19180
10/22/15 jt
ort rth U r
Texas
INTEROFFICE MEMORANDUM
WATER UTILITIES DEPARTMENT-ADMINISTRATION DIV.
Date: October 22, 2015
To: Brian McDougal, City Manager
From: Jimmie Johnson,Ph.D., Director of Utility Operations
RE: Proposed Resolution No. 19180
Nature of the Request:
The City awarded a contract to Siemens to provide services for the following projects: 1)
Reduction of water loss through the identification and repair of hydrant leaks. 2) Large meter
replacements, and 3) Automatic metering system upgrades. Siemens has submitted Change
order No. 1 for a time extension of 90 days, due to delays, to a new contract completion date
of February 5, 2016.
StaffAnalysis, Considerations:
Existing staff will monitor the contractor's performance.
Recommendation:
I recommend that the City Council approve Proposed Resolution No. 19180 authorizing the
City Manager to execute Change Order No. 1 to the contract between the City of Port Arthur
and Siemens Industry, Inc., of Houston, Texas for time extension of 90 days, due to delays
listed in Exhibit"A"to a new contract completion date of February 5, 2016.
Budget Considerations:
None.
P. R. No. 19180
10/22/15jt
RESOLUTION NO.
A RESOLUTION AUTHORIZING THE CITY MANAGER
TO EXECUTE CHANGE ORDER NO. 1 TO THE
CONTRACT FOR PHASE III OF A PERFORMANCE
CONTRACTING AGREEMENT BETWEEN THE CITY
OF PORT ARTHUR AND SIEMENS INDUSTRY, INC.,
BUILDING TECHNOLOGIES DIVISION FOR TIME
EXTENSION OF 90 DAYS, DUE TO DELAYS, TO A NEW
CONTRACT TERM OF 450 CALENDAR DAYS WITH A
NEW CONTRACT COMPLETION DATE OF
FEBRUARY 05, 2016.
WHEREAS, pursuant to Resolution Numbers 12-147, authorizing the original
Performance Contract Phase I for energy improvement and upgrades with Siemens; and,
WHEREAS, pursuant to Resolution Numbers 13-393, authorizing a Performance
Contract Phase II for the Police Department's HVAC improvement and upgrades with Siemens;
and,
WHEREAS, pursuant to Resolution Numbers 14-406, authorizing a Performance
Contract Phase III specifically addressing the City's water infrastructure and upgrades with
Siemens Industry, Inc.; and,
WHEREAS, Siemens Industry, Inc. recommends proposed Change Order No. 1 for a
time extension of 90 days, attached as Exhibit"A", to accomplish this work.
NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE
CITY OF PORT ARTHUR:
THAT, the City Manager of the City of Port Arthur is hereby authorized and directed to
execute, on behalf of the City of Port Arthur, Change Order No. 1 (attached as Exhibit "A") to
the contract between the City of Port Arthur and Siemens Industry, Inc., of Houston, Texas,
increasing the total contract time by ninety (90) days due to delays; and,
THAT, Change Order No. 1 increases the contract time to a new completion date of
February 05, 2016; and,
THAT, Change Order No. 1 will require no additional funding; and,
P. R. No. 19180
10/22/15jt
Page 2
THAT a copy of the caption of this resolution be spread upon the minutes of the City
Council.
READ, ADOPTED AND APPROVED THIS day of , 2015
at a Regular Meeting of the City Council of the City of Port Arthur, Texas, by the following vote:
AYES: Mayor ,
Councilmembers:
NOES:
Debris Prince
Mayor
ATTEST: APPROVED FOR ADMINISTRATION:
Sherri Bellard Brian McDougal
City Secretary City Manager
P. R. No. 19180
10/22/15 jt
Page 3 of 3
APPROVED AS TO FORM:
)10
Valecia Ti no Clifton Williams, CPPB
City Attorney Acting Purchasing Manager
Dr. Jimmie Johnson, PhD
Director of Utility Operations
APPROVED AS TO THE AVAILABILITY
OF FUNDS:
t+• !mac , eel.uP,'g,l/-
Jerry Dale, CPA, GFOA
Interim Director of Finance
Exhibit "A"
(Siemens Change Order No. 1)
SIEMENS
July 28, 2015
Brian McDougal
City of Port Arthur
444 4th Street
Port Arthur, Texas 77641
Mr. McDougal
Change Order 1: Contract amendment to extend the contractual completion date from
November 7th, 2015 to February 5th, 2016.
Due to circumstances outlined below, Siemens is requesting to amend section 2.1 of
Exhibit A in contract provided in resolution No. 14-406 executed between Siemens
Industry Inc. and The City of Port Arthur to extend the contract additional ninety days.
Proposed changes to Exhibit A section 2.1:
Exhibit A
2.1 Commencement of Work: SIEMENS shall commence the Work sixty (60)
Calendar days from the Effective Contract Date, shall perform the Work
diligently, and shall complete the Work no later than 369 450 calendar days from
the day of Commencement.
Issues encountered resulting in delays in project schedule:
1.) In the current contract, the City was to provide electrical power to the repeaters.
However, after the contract was executed, the City asked Siemens to assist help
facilitate with supplying the power to the repeaters and Siemens agreed to help.
While attempting to coordinate the locations and installation of the electrical
power for the repeaters, Siemens encountered numerous issues that delayed
execution of this portion of the project. City personnel provided Siemens with
their appropriate contact at Entergy and on December 16th, 2014 made contact
with Entergy. Siemens began negotiations with the City's' representative from
Entergy in an effort to coordinate installation of repeaters on street lights leased
by the City from Entergy. Siemens had communications with Entergy and on
January 7th, 2015 provided information on the repeater sites and needed
requirements. Per Entergy's request, Siemens supplied further information on
January 22st, 2015. On January 26th, 2015, Siemens received communications that
their request would be presented to Entergy's legal department. Siemens
Siemens Industry,Inc—Building Technologies Division Phone:(832)492-9110
8850 Fallbrook Road Fax:(281)949-3100
Houston,Texas 77064
Page 1 of 5
SIEMENS
attempted to set up a meeting with Entergy on January 21st, 2015 to discuss the
matter, but Entergy did not offer any dates to meet. Siemens again contacted
Entergy on February 4th, 2015 to obtain an update regarding a decision,
concerning the matter, but Entergy was not able to provide any information
regarding this. Siemens attempt to try and negotiate an agreement with Entergy
ended unsuccessfully. Siemens eventually determined that this course of action
would not result in any form of resolution and after a meeting between Siemens,
City of Port Arthur, and Entergy on February 25th, 2015 all parties decided not to
engage in this option. Therefore, Siemens and the City decided to install new
utility poles and provide new service in all locations needed for repeaters. Since
Entergy does not provide pricing structures for minimum monthly billings
anymore, they informed Siemens and the City that they would require an
electrical meter at each location. To satisfy city staff request and F.E.M.A.
guidelines regarding new electrical service, Siemens had to retain an outside
engineering firm to review all locations and provide certificates of elevation for
each location prior to installing any poles. These new certificates took another 8
weeks to research and deliver to the City. These delays have inhibited installation
of the infrastructure needed for the AMI network.
2.) In Exhibit A of the contract, Siemens provided a list of repeater locations to the
City. However, after the contract was signed, City staff wanted to further review
that list and asked that changes be made to various locations of repeaters. On
February 26th, 2015, Siemens provided City personnel with spreadsheets and a
map with planned locations of the repeater poles for the city to review per there
requested changes. Siemens later provided the documentation expanded to include
more information, as per requested by City staff, to further assist in getting
approval for these repeater sites. In an effort to further assist the City in resolving
several conflicts that were identified by city staff, Siemens contracted with an
outside firm to provide further assistance for the city. However, no direction was
provided to resolve these conflicts and review of these sites are still unresolved.
It is imperative that these issues be resolved in the next two weeks or the City can
expect additional delays.
3.) One of the key milestones for the project to remain on schedule was the need for
the City to sign an Indirect Sales Agreement between Itron Inc. and The City of
Port Arthur for software license. This agreement was essential in getting the
software approved so that the Itron AMI infrastructure could be set up to begin
reading the meters. This document was delivered to the City in November 2014
Siemens Industry,Inc—Building Technologies Division Phone:(832)492-9110
8850 Fallbrook Road Fax (281)949-3100
Houston,Texas 77064
Page 2 of 5
SIEMENS
and discussed in detail at the project kickoff meeting. Additionally Siemens
provided copies of the agreement on Jaunary20th, 2015, February 26th, 2015 and
March 1 lth, 2015. A meeting with Valecia Tizeno was held on April 7th, 2015 and
May 5th, 2015 to review the document and make necessary modifications.
Siemens expected to have the document signed and returned no later than early
January 2015. After numerous requests to get this document signed, this
agreement was finally approved by city council on May 12th, 2015 and returned to
Itron on May 21st, 2015. The Itron MVRS system was set up on June 1st, 2015 to
begin collecting data.
4.) Starting replacement of the 18,706 radio transmitters was dependant on the AMI
network system being operational. This would allow the meters being replaced to
immediately report usage once they were changed out and programmed. Due to
the delays affecting the AMI network system becoming operational, the actual
date the radio replacements began had slipped 3 months past its established start
date and did not begin until May 12, 2015.
5.) Once the meter replacements started, our installers have encountered extensive
vegetation growth, and in some cases debris, in the easements between houses.
The vegetation growth has impacted the installers by inhibiting their ability to
locate the meters and reducing access into the easements thereby slowing down
their rates of production. We have asked City staff to assist us with requesting the
Cities residence to remove debris and maintain foliage in the easements, but there
has been no resolution to address this matter. Siemens has also requested
assistance from the city in locating meters but,the City informed Siemens on June
9th, 2015 they were unable to support the locates due to issues with the
availability of manpower. With the list of un-located meters continuing to grow,
installers will have to return to these areas to complete these routes once the listed
items are addressed. Another ongoing issue that has impacted the installers'
progress is an inconsistency in the radio ID numbers at accounts that differ from
what is in the database provided to Siemens for the project. Each instance these
variations are encountered results in the account to be skipped and returned to
later or the installers remaining at the account until the discrepancy can be
addressed with the billing department. This issue was discussed in a meeting held
on June 9th, 2015 and Siemens made a request that the city provide an updated
database to help synchronize some of the mismatches in the radio numbers. The
billing department did try to provide access to the current database file, but
Siemens Industry,Inc—Building Technologies Division Phone:(832)492-9110
8850 Fallbrook Road Fax:(281)949-3100
Houston,Texas 77064
Page 3 of 5
SIEMENS
encountered access issues to which they requested that the Cities IT department
provide the file or access to it. To this date,July 21St 2015 the file has not been
produced. Until the updated refresh file is provided, it was decided that each
instance would have to be resolved through coordination between the cities'
billing department and Siemens installation coordinator as every inconsistency is
encountered causing further delays in production.
6.) On March 31st, 2015, it was established that the Fire Hydrant replacements would
begin on April 27th, 2015 and a schedule of hydrants was provided. A discussion
was held on April 21St, 2015 to assure that water mains were being identified
according to the provided schedule, so that the installation crews would not have
to wait for the water utility personnel to find the main valves and shut them off.
During this discussion Siemens was informed that there would be a shortage of
manpower during the week of April 27th, and the city would not be able to support
the fire hydrant replacements. The start date was then rescheduled to start on May
4th, 2015. Siemens' installing contractor mobilized on the rescheduled start date
and experienced difficulties starting the scheduled replacements for that day due
to issues with city personnel identifying and isolating the main water lines. Two
fire hydrants were scheduled for replacement that first day but the installing crews
were only able to replace one hydrant. The following day, (May 5th, 2015)during
the weekly meeting, it was discussed with the water utility department personnel
that water main isolation valves would need to be identified and tested the
previous week of the scheduled replacements so not to impede the installing
crews. Additionally hydrants scheduled for the following week would have to be
submitted to 811 for locates of the underground utilities at each location. The
utility company's contractor allows ten locate request be submitted at a time and
this limited re-arranging the schedules because of faulty main water valves which
contributed to the need to have main valves identified previous to the scheduled
day of replacements. It was also stated that the afternoon water utility crews
would turn mains back on if the replacements went past four o'clock in the
afternoon. During this meeting it was also determined that the cities blackboard
system for notifications be utilized to inform customers of all water outages. Due
to continuous problems with city main isolation valves being identified and shut
off, only eight fire hydrants had been replaced by May 19th, 2015. The
expectation was to perform two hydrant replacements per day and was what was
being scheduled. On June 2nd,2015, during the weekly meeting,the city discussed
that they were receiving a tremendous amount of calls due to water utility outages
and that the need to schedule blackboard notifications and posting on the cities
Siemens Industry,Inc—Building Technologies Division Phone:(832)492-9110
8850 Fallbrook Road Fax (281)949-3100
Houston,Texas 77064
Page 4 of 5
SIEMENS
web site was needed to better inform customers of the outages. Through the
month of June and July the installing crew has experienced issues of starting
replacements later than needed while waiting for city crews to get water shut off
so that the hydrant replacements could begin. The resulting effect would delay
starting the next hydrant scheduled for that day and the hydrant replacement
would be cancelled by city water utility personnel,due to the consideration of the
amount of time the work would take and the later start time. The weekly meeting
on July 14th,2015 established that the installation crews would wait no longer
than one and one half hours for the main water lines to be isolated off, before
moving to the next hydrant. There have been several occasions when work was
canceled for a particular day due to water utility personnel absences. The weekly
production rates have increased but still fall short of the expected weekly numbers
causing the scheduled completion date for fire hydrants to be extended.
Siemens is committed to completing this project as scheduled and has increased its
manpower to improve the rate of production to compensate for the delays.However, due
to the issues described above we will not be hitting the targeted completion date and are
asking for a contract extension. Should you have any questions,please give me a call and
we look forward to hearing back from you next week.
Sincerely,
Brian McDougal
City of Port Arthur City Manager
(Signature)
Date
Siemens Industry,Inc.
(Signature)
Date
Siemens Industry,Inc—Building Technologies Division Phone:(832)492-9110
8850 Fallbrook Road Fax:(281)949-3100
Houston,Texas 77064
Page 5 of 5