HomeMy WebLinkAboutPR 19269: CHANGE ORDER NO. 1 BDS CONSTRUCTORS DBA MK CONSTRUCTORS, 80 DAY EXTENSION DUE TO WEATHER AND MATERIALS City of P.R. No. 19269
cei� 1/04/16 jt
nrl rth [tr ��-
�— ras
INTEROFFICE MEMORANDUM
UTILITY OPERATIONS DEPARTMENT-ADMINISTRATION
Date: January 4, 2016
To: Brian McDougal, City Manager
From: Jimmie Johnson, Ph.D., Director of Utility Operations
RE: Proposed Resolution No. 19269
Nature of the Request:
The City awarded a contract to BDS Constructors dba MK Constructors of Vidor, Texas, for
the construction of the Pleasure Island Metering Station. There are three (3) 10"water meters
at this location. This is part of the system that helps supply water to Sabine Pass
Liquefaction/Cheniere LNG facility. MK Constructors has submitted Change Order No. 1 for
a time extension of 80 days, 17 due to weather delays, and 63 days for material delays. To a
new contract completion date of April 01, 2016.
StaffAnalysis, Considerations:
City staff will assist in construction. Upon completion of this project, the City will accept the
public improvements.
Recommendation:
I recommend that the City Council approve Proposed Resolution No. 19269 authorizing the
City Manager to execute Change Order No. 1 to the contract between the City of Port Arthur
and BDS Constructors dba MK Constructors of Vidor, Texas for time extension of 80
days, due to delays in weather and materials listed in Exhibit "A" to a new contract
completion date of April 01, 2016.
Budget Considerations:
This project is charged through City Account No. 429-1258-532.59-00, Project No. WSI002.
CCfEA/Lsit IA-TTR. Zhn p,0legif Nf.9µ1 AVO
P. R. No. 19269
01/04/16 jt
RESOLUTION NO.
A RESOLUTION AUTHORIZING THE CITY MANAGER
TO EXECUTE CHANGE ORDER NO. 1 TO THE
PLEASURE ISLAND METERING STATION CONTRACT
AGREEMENT BETWEEN THE CITY OF PORT
ARTHUR AND BDS CONSTRUCTORS DBA MK
CONSTRUCTORS OF VIDOR, TEXAS, FOR TIME
EXTENSION OF 80 DAYS, DUE TO DELAYS IN
WEATHER AND MATERIALS TO A NEW CONTRACT
COMPLETION DATE OF APRIL 01, 2016. ACCOUNT
NO. 429-1258-532.59-00, PROJECT NO. WSI002.
WHEREAS, pursuant to Resolution Number 15-264, authorizing a contract to
BDS Constructors dba MK Constructors of Vidor, Texas to provide the Pleasure Island
Metering Facility; and,
WHEREAS, BDS Constructors dba MK Constructors has requested proposed Change
Order No. 1 for a time extension of 80 days for weather and material delays; and
WHEREAS, Arceneaux Wilson & Cole, LLC.,, of Port Arthur, Texas reviewed and
recommended Change Order No. 1 of the contract to BDS Constructors dba MK Constructors of
Vidor, Texas. (Attached hereto as Exhibit"A")
NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE
CITY OF PORT ARTHUR:
THAT, the City Manager of the City of Port Arthur is hereby authorized and
directed to execute, on behalf of the City of Port Arthur, Change Order No. 1 (attached as
Exhibit "A") to the contract between the City of Port Arthur and BDS Constructors dba MK
Constructors of Vidor, Texas increasing the total contract time by eighty (80) days due to delays
P.R. No. 19269
01/04/16 jt
Page 2 of 3
in weather and materials; and,
THAT, Change Order No. 1 increases the contract time to a new completion date of
April 01, 2016; and,
THAT, Change Order No. 1 will require no additional funding; and,
THAT a copy of the caption of this resolution be spread upon the minutes of the City
Council.
READ,ADOPTED AND APPROVED THIS day of , 2016 at a
Regular Meeting of the City Council of the City of Port Arthur, Texas, by the following vote:
AYES: Mayor ,
Councilmembers:
NOES: .
Deloris Prince
Mayor
ATTEST: APPROVED FOR ADMINISTRATION:
Sherri Bellard Brian McDougal
City Secretary City Manager
P.R. No. 19269
01/04/16 jt
Page 3 of 3
APPROVED AS TO FORM:
()Akin-
Valecia Tizeno V Clifto Williams, CPPB
City Attorney Purchasing Manager
Dr. Jimmie Johnson, PhD
Director of Utility Operations
APPROVED AS TO THE AVAILABILITY
OF FUNDS:
}ZI /< 6,,v/p4o(fee
Jerry Dale, CPA, GFOA k'SI1b
Interim Director of Finance
Account#429-1258-532.59-00, Project No. WSI002.
P.R. No. 19269
01/04/16 jt
Exhibit "A"
(AWC Change Order No. 1)
ARCENEAUX WILSON & COLE LLC
rceneaua Wilson 6 Colo---ti.,-
AWCEngineering • Surveying • Planning
December 29, 2015
Dr. Jimmie Johnson
Director of Water Utilities
City of Port Arthur
444 Fourth Street
Port Arthur, Texas 77640
RE: PROPOSAL FOR CHANGE ORDER NO. I
Pleasure Island Metering Facility
Job No, CPA-665
Dear Mr. Johnson:
Attached is Change Order No. 1 for the Pleasure Island Meting Facility. This change order is for
time extension of 17 days due to weather delays during the month of December and 63 days
due to material delivery delay for pumps and meters. I recommend that the City of Port Arthur
authorize this change to the contract. I have attached Change Order No. 1 which modifies the
contract to reflect this change for your consideration and action. Should you have any
questions or require additional information, please contact our office.
Very truly yours,
Arceneaux Wilson & Cole LLC
TEXAS REGISTERED ENGINEERING FIRM F-16194
Keestan Cole, PE
Vice-President
(409) 724-7888 • 2901 Turtle Creek Drive • Suite 320 • Port Arthur. Texas 77642
www.awceng.com
l 2'
•r, . ua WUton 8 Cols--.-...
AWC
CHANGE ORDER No. 1
DATE: December 29, 2015 JOB NO. CPA-665
AGREEMENT DATE: August 27, 2015
NAME OF PROJECT: Pleasure Island Metering Faculty
OWNER: CITY of PORT ARTHUR
CONTRACTOR: BDS Constructors dba MK Constructors
The following changes are hereby made to the CONTRACT DOCUMENTS:
1. Add the following Items to the Contract and Scope of Work:
a. Extend contract time by 80 days
CHANGE ORDER NO. 1
December 29f 2015
AtCeflt u. Wliton • Cola---
AWCJob No. CPA-665, Contract No. 1
CHANGE TO CONTRACT PRICE:
ORIGINAL CONTRACT PRICE: $626,253.00
CURRENT CONTRACT PRICE adjusted by previous CHANGE ORDER(S): $626.253.00
The CONTRACT PRICE due to this CHANGE ORDER will be [inereased} [decreased]
by: $0.00 Dollars
The new CONTRACT PRICE, including this CHANGE ORDER, will be $626.253.00
CHANGE TO CONTRACT TIME:
ORIGINAL CONTRACT TIME: 120 Calendar Days
CURRENT CONTRACT TIME adjusted by previous CHANGE ORDER: 0 Calendar Days
CURRENT DATE OF COMPLETION: January 12, 2016
CONTRACT TIME due to this CHANGE ORDER will he increased by 80 Days
The New DATE OF COMPLETION: April 1, 2016
No other Terms and Conditions of the Contract are changed as a result of this Change Order.
Contractor's acceptance of Change Order relieves OWNER of any liability for additional costs
incurred by Contractor in his performance of the work covered by the Change Order.
RECOMMENDED BY ENGINEER: ACCEPTED BY:
ARCENEAUX WILSON & COLE LLC (CONTRACTOR,OFFICER OR OWNER)
BDS CONSTRUCTORS DBA MK
CONSTRUCTORS
ACCEPTED BY:
CITY of PORT ARTHUR
2 of 2
REQUEST FOR EXTENSION OF TIME DUE TO WEATHER OR SUPPLIES
CITY OF PORT ARTHUR
DATE: \'Z-"A- \5 , 20
MONTH OF: P C ,20\
CITY of PORT ARTHUR,TEXAS
WATER UTILITIES DEPARTMENT
P.O. BOX 1089
CITY of PORT ARTHUR,TEXAS 77641-1089
ATTENTION: Dr. Jimmie Johnson
Utilities Director
Gentlemen:
We request extension of completion time on our Contract due to the days of work lost as
specified(list dates actually lost: do not include days not normally worked such as Saturdays,
Sundays, or holidays):
Dates Lost:
Days Lost ('\, )/ 5 x 7 + Calendar Days Requested
Reasons for Request .
.\
Contractor -`Sc1`(, C.tN\5\4' CovS
By:
ronon000000uaxcocoaaouooeaeurcuraacrrerrcrrreerrrrrcrrerorcrooccrr rorrrr a■errrr
Approved for extension of calendar days.
Disapproved.
Date: , 20 CITY OF CITY OF PORT ARTHUR,TEXAS
BY:
City Manager
Distribution by City
Original: Water Utilities Department
xc: Engineer
Contractor
CPA Federally Funded
REQUEST FOR EXTENSION OF TIME DUE TO WEATHER OR SUPPLIES
CITY OF PORT ARTHUR
DATE: \*" .-..a%- , 20 V
MONTH OF: e� 20\S
CITY of PORT ARTHUR,TEXAS
WATER UTILITIES DEPARTMENT
P.O. BOX 1089
CITY of PORT ARTHUR,TEXAS 77641-1089
ATTENTION: Dr. Jimmie Johnson
Utilities Director
Gentlemen:
We request extension of completion time on our Contract due to the days of work lost as
specified(list dates actually lost: do not include days not normally worked such as Saturdays,
Sundays, or holidays):
Dates Lost:
Days Lost(' )/ 5 x 7 + col Calendar Days Requested
Reasons for Request: %S"\ ,S,a\ �e��v� d
4 .
Contractorpc S
f O p p O p 0 p p p G p M G O O D O C p fl G o p o p C p o p o p®o r W p p p p p s a G p p 0........p e O p G G p a E p p p p p a C p s a E a E a G
Approved for extension of calendar days.
Disapproved.
Date: , 20 CITY OF CITY OF PORT ARTHUR,TEXAS
BY:
Distribution by City City Manager
Original: Water Utilities Department
xc: Engineer
Contractor
CPA Federally Funded